Decision Notice - Approved by Delegation of Authority DBW24 0090 · DBW24/0090

of 7

Text shows just the words. Original shows the document exactly as it was published.

                                                             Officer:            Cameron Smith
                                                             Direct Telephone:   07 53296178
                                                             Our Reference:      DBW24/0090 & RAP24/0025
                                                             Your Reference:     n/a

               29 August 2024


               RA Stead
               C/- Brennan Planning Pty Ltd
               44 Maple St
               COOROY QLD 4563
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 27 August 2024, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              DBW24/0090

                   Street address:              26 Attunga Hts Noosa Heads

                   Real property description:   Lot 14 RP 89506

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Building Work Assessable Against the Planning Scheme - Dwelling
                       House (Cut/Fill & Slope)
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

                       When Conditions must be Complied With
               1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                       the use of the building commencing, and then compliance maintained at all times while the
                       use continues.




               ABN 97.969.214.121                                                                    PO Box 141
               noosa.qld.gov.au                                                               Tewantin QLD 4565
               [email protected]                                                               07 5329 6500
                                                                                                           Page 1 of 7
Document Set ID: 23215511
Version: 3, Version Date: 29/08/2024
Full text of the other 6 pages

Page 2

                      Currency Period
               2.     This development approval lapses if the works have not substantially started by 27 August
                      2026, unless an application to extend the currency period is approved by Council.
                      Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below.

                      Plan No.                Rev.   Plan/Document Name                               Date

                      AJH43_WD-B 3/14         B      Site Plan, prepared by alexjhobbs design & 14 May 2024
                                                     drafting
                                                     Annotated by Council

                      AJH43_WD-B 5/14         B      Ground Floor, prepared by alexjhobbs 14 May 2024
                                                     design & drafting

                      AJH43_WD-B 6/14         B      Subfloor, prepared by alexjhobbs design & 14 May 2024
                                                     drafting

                      AJH43_WD-B 8/14         B      Elevations East and West, prepared by 14 May 2024
                                                     alexjhobbs design & drafting

                      AJH43_WD-B 9/14         B      Elevations North and South, prepared by 14 May 2024
                                                     alexjhobbs design & drafting

                      AJH43_WD-B 10/14        B      Section through internal staircase, prepared 14 May 2024
                                                     by alexjhobbs design & drafting

                      AJH43_WD-B 11/14        B      Section through E to W, prepared by 14 May 2024
                                                     alexjhobbs design & drafting

                      AJH43_WD-B 12/14        B      Section through New Wing, prepared by 14 May 2024
                                                     alexjhobbs design & drafting

                      Building Height
               4.     The maximum height of the development must not exceed 8.0 metres above the ground level
                      including where excavation is undertaken the exposed portion of the external façade of the
                      building.
               5.     Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
                      certifies that the building does not exceed the maximum height requirement of this Decision
                      Notice.
                      Car Parking
               6.     A minimum of 2 covered car parking spaces must be provided on site and made available
                      and accessible at all times for residents.
                      Lighting Amenity
               7.     No flood lighting must be used on site. Any vertical illumination resulting from direct, reflected
                      or other incidental external lighting emanating from the site must not exceed 8 lux when
                      measured at any point 1.5 metres outside the boundary and at any level from ground level
                      upward.
                      Environment
               8.     Sediment or any other material including building materials or waste products must not be
                      deposited or released into the road reserve, stormwater drain or adjacent properties.


                                                                                                          Page 2 of 7
Document Set ID: 23215511
Version: 3, Version Date: 29/08/2024

Page 3

                      Landscaping Works
               9.     A minimum of 20% of the site must be retained as soft landscaping.
               10.    Existing trees on the site must be retained, except where required to be removed to
                      accommodate the approved dwelling. In this regard, the removal of vegetation must not
                      extend beyond works shown on the approved plans.
               11.    Existing vegetation in the road reserve must be retained, unless written authorisation from
                      Council is granted for the clearing.
               12.    Trees to be retained must be protected from clearing or construction activities by:
                      a.      clearly marking vegetation to be retained with flagging tape
                      a.      installing protective fencing around the drip line of the vegetation
                      b.      restricting stockpiling, storage and vehicle parking to those areas which are already
                              cleared
                      c.      using low impact construction techniques around vegetation.
               13.    All landscape works must be established and maintained for the life of the development, and
                      in a manner that ensures healthy, sustained and vigorous plant growth. All plant material
                      must be allowed to grow to full form and be refurbished when its life expectancy is reached.
                      Earthworks
               14.    All earthworks and associated retaining structures/batters, both above and below ground,
                      both temporary and permanent, must be contained entirely within the subject site unless
                      written permission form the respective landowner(s) is provided to Council. All earthworks
                      must be undertaken in accordance with the provisions of Australian Standard AS3798:
                      Guidelines on Earthworks for Commercial and Residential Developments.
               15.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height.
                      All retaining walls that are publicly accessible and exceed 1.0m in height must be fitted with
                      a commercial grade safety fence.
                      Site Access and Driveways
               16.    A sealed access driveway must be provided from Attunga Heights to all parking and
                      manoeuvring areas of the development. The works must be undertaken in accordance with
                      an Operational Works approval, be generally in accordance with Alexjhobbs’ Site Plan
                      (AJH43_WD-B, Rev. B) and must include a driveway crossover in accordance Council’s
                      standard drawings (RS-049, RS-050 and any associated addendum).
                      Stormwater Drainage
               17.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge or be disposed of on-site without causing scour or damage to the subject site or
                      any adjoining properties.
                      Easements
               18.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               19.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               20.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.




                                                                                                       Page 3 of 7
Document Set ID: 23215511
Version: 3, Version Date: 29/08/2024

Page 4

                      Damage to Services and Assets
               21.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
                      Geotechnical Stability
               22.    All works must be carried out in accordance with the recommendations contained in section
                      4 of Tectonic’s Geotechnical Investigation Report (20248-001-Rev0) dated 3 September
                      2020.
               5.     REFERENCE DOCUMENTS

                Doc No.                Rev.   Document Name                                         Date

                20248-001-             -      Geotechnical Investigation for Proposed Extension 3 September 2020
                Rev0                          to a Residence
                                              Prepared by Tectonic

               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
               PLANNING
                      Aboriginal Cultural Heritage Act 2003
               1.     There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
                      approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                      The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
                      carries out an activity must take all reasonable and practicable measures to ensure the
                      activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
                      duty of care. Substantial monetary penalties may apply to individuals or corporations
                      breaching this duty of care. Injunctions may also be issued by the Land and Resources
                      Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
                      that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
                      of Aboriginal cultural heritage.
                      You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
                      Equitable Access and Facilities
               2.     The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      a.      the Disability Discrimination Act 1992 (Commonwealth);
                      b.      the Anti-Discrimination Act 1991 (Queensland); and



                                                                                                             Page 4 of 7
Document Set ID: 23215511
Version: 3, Version Date: 29/08/2024

Page 5

                      c.      the Disability (Access to Premises – Buildings) Standards.
                      Infrastructure Charges
               3.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue.
                      Property Driveway and Vehicle Crossover
               4.     The planning scheme declares for the construction of a driveway and vehicle crossover to
                      the property to be Accepted Development subject to meeting the requirements of the Low
                      Density Housing Code. If the proposed driveway and vehicle crossover does not comply with
                      each Acceptable Outcomes contained in the Code, a Development Permit for Operational
                      Work is required to be obtained from Council.
                      *http://www.noosa.qld.gov.au/documents/40217326/40415739/Vehicle%20Crossover%20Application%20Pack.pdf
                      Sustainability
               5.     Council encourages sustainable and energy efficient building design for all development,
                      including the use of sustainable building materials, energy efficient fittings, solar hot water,
                      photovoltaic systems (including the use of inverter/charges), solar panels, water saving
                      devices and rainwater harvesting.
                      Fires in Urban Areas
               6.     In urban areas fires are prohibited except where in an appliance is used for domestic heating
                      or cooking purposes, which must comply with particular standards. Any area identified as a
                      fire pit area on approved plans is to be in accordance with Local Law & Subordinate Local
                      Law No. 3, Schedule 3. Refer to the following link for details:
                      https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview
               ENGINEERING
               7.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.

                Type of Development Permit Required                     Subject of the required Development Permit

                Development Permit for Building Works                   All building work.

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If



                                                                                                                     Page 5 of 7
Document Set ID: 23215511
Version: 3, Version Date: 29/08/2024

Page 6

               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               Cameron Smith
               Development Planner

               Enc:   Appeal Rights
                      Approved Plans/Documents




                                                                                                       Page 6 of 7
Document Set ID: 23215511
Version: 3, Version Date: 29/08/2024

Page 7

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 7 of 7
Document Set ID: 23215511
Version: 3, Version Date: 29/08/2024

Used in these records

About this file

File size
154 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Approved by Delegation of Authority DBW24 0090.pdf · 154 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.