SUPERSEDED - Decision Notice MCU22/0082 OPW22/0134 [As Published]

of 14

Page text shows just the words. Original shows the document exactly as it was published.

               8.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, On and Off Maintenance Inspections Request
               9.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days’ notice of preferred inspection time.
               10.    If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               11.    A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise
                      Environmental Advisory Notes
               12.    The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               13.    Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control
               14.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               15.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •        appropriate for slopes and slope lengths; and
                              •        are consistent with best practice environmental management practices such as
                                       in the Manual for Erosion and Sediment Control or the IECA Manual; and
               Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of
               sedimentation or erosion, or lead to water contamination.
                      Building and Construction Industry (Portable Long Service Leave) Levy
               16.    The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
                      Qualified Person
               17.    For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
                      for the development, a qualified person is considered to be a person who:
                      a.      is a Registered Professional Engineer of Queensland (RPEQ); and
               has a degree in civil engineering or engineering geology; and
                      b.      has a minimum of 5 years experience in the field of geotechnical engineering or
                              engineering geology.




                                                                                                      Page 12 of 14
Document Set ID: 22208842
Version: 4, Version Date: 14/12/2022
Log in to download the original file

SUPERSEDED - Decision Notice MCU22_0082 OPW22_0134 [As Published].pdf · 223 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.