Stormwater Management Plan
Attached to the e-mail MCU16/0081 Geotechnical report, Landscape Plan, SMP, Traffic report - Email 3 of 3.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnSC5594 – Walter Hay Dr, Noosaville 7
During the construction phase of the development, silt fences should be erected downstream of all
disturbed areas. In addition erosion and sediment control devices should be regularly inspected and
maintained following storm events. An Erosion and Sediment Control Plan will be provided as part of the
operational works application.
3.3 Operational Phase
During the operational stage of the development, the following impacts have been identified in relation to
stormwater runoff and water quality of the receiving waterways:
Gross pollutants which include human derived litter, course sediment and vegetation
Sediment and suspended solids
Nutrients such as phosphorous and nitrogen
To target these potential pollutants stormwater quality improvement devices (SQID’s) are proposed to be
incorporated within the design.
3.3.1 Water Quality Objectives
The water quality objectives (WQO’s) for this site were determined in accordance with Appendix 2 of the
State Planning Policy (SPP) Dec 2013.
Table 3.2 indicates the minimum load reduction targets required to be met:
Pollutant Minimum Reduction Targets
Total Suspended Sediments (TSS) 80%
Total Phosphorus (TP) 60%
Total Nitrogen (TN) 45%
Gross Pollutants (>5mm) 90%
Table 3.2 - Water Quality Objectives
3.3.2 Pollutant Export Modelling
The Model for Urban Stormwater Improvement Conceptualisation (MUSIC) has been utilised to calculate
pollutant loads from the proposed development and to predict performance characteristics of the proposed
treatment train. Modelling parameters used were adopted from the Water by Design “Music Modelling
Guidelines for South-East Queensland”, and the updated MUSIC Version 5 recommended parameters for
Bio-retention basin nodes. MUSIC modelling setup and results are attached within Appendix B.