Operation Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
Site Establishment #
New Access Path #
Construct Working Platform #
Install Micro Piles Terrace #
Construct Moving Working
Platform over lift access tunnel #
Install Micro Piles to Lift shaft and #
access tunnel
Construct Pipe Caps #
Excavate to Soffit level of Access #
walkway Concrete roof.
Construct Suspended Concrete
Slab Roof over Access Tunnel #
Complete excavation of lift shaft
and access walkway and fill over #
to re-establish original ground
above access tunnel
Erect Scaffolding #
Construct Lift Shaft and walkway
#
Extend existing main house deck
and lift shaft glazing/waterproofing #
Install Lift equipment &
commission Lift #
Construct steel columns and #
bearers together with timber
joists and decking to terrace.
Install Stormwater Reticulation #
Install Landscaping including #
stone cladding to lift and tunnel
entrance.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.