Appendix J - Code Assessment · RAL25/0004

of 26

Text shows just the words. Original shows the document exactly as it was published.

                                                             RECONFIGURING A LOT CODE

 Application for a Development Permit for Reconfiguring a Lot by Subdivision (1 Lot into 3 Lots + Balance Lot), involving land
                  described as Lot 105 on SP118458, situated at 62 Lake MacDonald Drive, Cooroy QLD 4563.


                  Performance Outcomes                                             Acceptable Outcomes                       Comment
Growth Management
PO1                                                                  No acceptable outcome provided.     Complies.
Urban residential development:
                                                                                                         The purpose of this application is to enable the
(a) is confined to land within the Urban boundaries;                                                     remainder of the land (proposed Lots 1, 2 & 3) to
(b) provides a mix of lot sizes and configurations to cater for                                          be utilised for future land uses and is generally in
    variety in housing choice;                                                                           accordance with the subdivision layout approved by
(c) contributes to efficient use of land and infrastructure;                                             Council resolution on 23 January 2025 (extract
(d) increases residential densities and reduces lot sizes in close                                       from resolution below):
    proximity to public transport and centre zones;
(e) provides appropriate buffer areas between sensitive land                                             A.   ‘Note the report by the Principal Strategic
    uses, ecologically important areas and conflicting uses;                                                  Planner to the General Committee dated 20
(f) contributes positively to the amenity and landscape value                                                 January 2025 regarding Cooroy Affordable
    of the local area                                                                                         Housing Project at 62 Lake Macdonald Drive,
                                                                                                              Cooroy;
                                                                                                         B.   Approve the revised Proposed Subdivision of
                                                                                                              Lot 105 on SP118458, Rev. C, prepared by
                                                                                                              Murray & Associates and dated 9/12/24
                                                                                                              contained in Attachment 1 to the report;
                                                                                                         C.   In accordance with Council Resolution on 16
                                                                                                              May 2024, approve all remediation and
                                                                                                              subdivision works required to occur for the
                                                                                                              delivery of the revised subdivision layout
                                                                                                              contained in Attachment 1 to the report;
                                                                                                         D.   Support advancing the subdivision and
                                                                                                              remediation works subject to securing a loan
                                                                                                              facility, whilst continuing to actively pursue
                                                                                                              grant funding opportunities; and
                                                                                                         E.   In endorsing this option any process to
                                                                                                              consider future uses of the remaining 2 sites
                                                                                                              should consider investigating options for the
                                                                                                              sites, including open space, cultural heritage,
                                                                                                              housing, community uses, landscape and
                                                                                                              amenity and other land use planning matters
Full text of the other 25 pages

Page 2

                                                                                                                            and ensure this process involves community
                                                                                                                            consultation.’

                                                                                                                        Key design aspects include a mostly 10m wide
                                                                                                                        planted buffer zone within road reserve to be
                                                                                                                        established adjacent to the existing residential
                                                                                                                        allotments to the east of the site (accessed via
                                                                                                                        Dianella Court) providing a substantial separation
                                                                                                                        to any future land uses within proposed Lots 1-3.

                                                                                                                        The proposed 10m width well exceeds the usual 5m
                                                                                                                        deep planting width for added privacy and amenity
                                                                                                                        to the adjoining residents and will provide a
                                                                                                                        treed/green visual aspect from nearby and
                                                                                                                        surrounding areas as well as enhanced ecological
                                                                                                                        values in contrast to the existing pine plantation
                                                                                                                        which inhibits biodiversity.

                                                                                                                        Additionally, a 1,000m2 and 1,542m2 area of the
                                                                                                                        subject site will be dedicated to Council as open
                                                                                                                        space park linkages (minimum 20m width) through
                                                                                                                        the site for recreation and future pedestrian
                                                                                                                        connectivity (see Appendix C for details) which will
                                                                                                                        be embellished with landscaping treatments to
                                                                                                                        enhance the visual amenity of the site.

                                                                                                                        Proposed Lots 1, 2 & 3, and balance lot 100 will
                                                                                                                        connect to the following infrastructure services
                                                                                                                        (Appendix E, F & G):
                                                                                                                         Reticulated electricity;
                                                                                                                         Reticulated sewerage;
                                                                                                                         Reticulate telecommunications; and
                                                                                                                         Reticulated water.
PO2                                                            No acceptable outcome provided.                          Not applicable.
Rural residential development is confined to land within the
Rural Residential zone and included within either the Urban                                                             The subject site is not within the Rural Residential
Footprint or Rural Living designations of the South East                                                                Zone.
Queensland Regional Plan



PO3                                                            Development of land:                                     Not applicable.
Development of land for business and employment functions
occurs within the activity centres and the industrial zones.   (a) at the Noosa Business Centre is to be generally in   The proposed development does not involve
                                                                   accordance with Figure 7.2.4.5 (Noosa Business       development of land for business and employment
                                                                   Centre Framework and Character Plan);                functions.

Page 3

                                                                    (b) at the former Bowls site Lot 3 RP884396, Noosa
                                                                        Junction is to be generally in accordance with Figure
                                                                        7.2.5.4 (Noosa Junction Framework and Character
                                                                        Plan).
PO4                                                                                                                             Not applicable.
With the exception of lots intended to be used by the Council
or State for community infrastructure, conservation purposes                                                                    The site is in the Community Facilities Zone.
or public utilities, including road widening, no additional lots
are created:

(a) in the Rural zone unless resultant lots have a minimum
    area of 100 hectares;
(b) in the Environmental Management and Conservation zone;
(c) on Noosa North Shore;
(d) in the Low density residential zone at Cooroibah;
(e) in the Low density residential zone where access is gained
    via:
    (i) Noosa Banks Drive, Tewantin;
    (ii) Golf Course Drive, Griffith Avenue or Carramar Street,
          Tewantin;
    (iii) Lake Entrance Boulevard, Noosaville;
    (iv) Lake Weyba Drive Noosaville, south of Eenie Creek
          Road; or
    (v) Habitat Place, Noosa Heads;
(f) within a Water Supply Buffer Area as shown on Regional
    Infrastructure Overlay.
Lot areas and dimensions
PO5                                                                 AO5.1                                                       Performance Solution:
New lots have areas and dimensions that:                            New lots are of a size and shape that can accommodate
                                                                    the land uses intended by the zone.                         In accordance with Table 9.5.1.4 - Minimum Lot
(a) are consistent with the purpose and overall outcomes of                                                                     Size of the Noosa Plan the Community Facilities
    the applicable zone or zones;                                   AO5.2                                                       Zone ‘No Minimum Specified’. The following lot
(b) are consistent with the size and character of surrounding       In general, lots have a predominantly regular,              areas and dimensions are proposed (Appendix C):
    lots;                                                           rectangular shape.
(c) can accommodate land uses that are consistent with the                                                                       Proposed         Proposed Lot      Proposed
    purpose and overall outcomes of the applicable zone;            Editor's note-topographical constraints or                   Lot Number       Area              Frontage
(d) allow for siting and construction of buildings,                 environmental values may call for irregular property
                                                                    boundaries.                                                                                     38.6m &
    structures, access ways and car parking while:-                                                                              1                3,158m2
                                                                                                                                                                    45.4m
    (i) retaining ecologically important areas and ecological
          linkages;                                                 AO5.3                                                        2                6,281m2           111.4m
    (ii) minimising risk of soil erosion, landslide, flooding and   In residential zones, lots are generally arranged so
                                                                    that:                                                        3                7,917m  2
                                                                                                                                                                    23m
          bushfire;
    (iii) minimising earthworks or retaining walls associated

Page 4

          with construction on sloping sites;                                (a) there are no more than five lots with                                   1ha                N/A (Balance
    (iv) retaining the scenic amenity and vegetated character                    a frontage width of less than 15 metres grouped in     100
                                                                                                                                                         (10,000m2)         Lot)
          of the landscape;                                                      a row;
    (v) retaining culturally significant features and protecting             (b) there are no more than three lots with                The purpose of this application is to enable the
          views to culturally significant features;                              a frontage width of 7.5 metres or less in a row       remainder of the land (proposed Lots 1, 2 & 3) to
    (vi) minimising detrimental impacts of effluent disposal or                  unless serviced by a rear lane;                       be utilised for future land uses and is generally in
          storm water runoff; including open space for                       (c) lots with a frontage width of less than 15 metres     accordance with the subdivision layout approved by
          landscaping; ensuring safe vehicular manoeuvring                       are not located opposite other lots with              Council resolution on 23 January 2025.
          areas without concentration of driveways in one space;                 a frontage width of less than 15 metres
          and                                                                                                                          In addition, a 1,000m2 and 1,542m2 area of the
    (vii) where not in a water or sewerage service area, allow               AO5.4                                                     subject site will be dedicated to Council as open
          for water storage tanks and suitable effluent disposal.            In activity centres and industry zones, new lots          space park area (see Appendix C for details).
(e) except where otherwise specified in a local area code, comply with the   contribute to a mix of lot sizes that cater for varied
    minimum lot size specified in Table 9.5.1.4 Minimum Lot Size and         commercial and industrial enterprises, such that:         The lots will gain vehicle access from the start of
    Dimensions                                                                                                                         Dianella Court. On street parallel carparking will be
                                                                             (a) smaller lots intended for intensive development are   provided along the western side of the new road.
                                                                                 clustered near centres;
                                                                             (b) new lots adjacent to sensitive land uses include      Proposed Lot 1, 2 & 3 will gain access via the
                                                                                 sufficient area for buffering of incompatible land    establishment of a new 18-23m wide road reserve
                                                                                 uses; and                                             inclusive of a mostly 10m wide buffer along the
                                                                             (c) lot reconfiguration provides for                      eastern edge of the road. Each lot will be provided
                                                                                 shared access arrangements wherever possible.         direct access to this road via new driveway
                                                                                                                                       crossover points (see Appendix C & E for details).

                                                                                                                                       A mostly 10m landscaped buffer will be established
                                                                                                                                       within the eastern verge of the proposed new road
                                                                                                                                       to ensure no adverse amenity outcomes occur with
                                                                                                                                       the neighbouring properties to the east (see
                                                                                                                                       Appendix C & D for details).

                                                                                                                                       This buffer will provide a green corridor from nearby
                                                                                                                                       and surrounding areas as well as enhancing
                                                                                                                                       ecological values in contrast to the existing pine
                                                                                                                                       plantation which inhibits biodiversity.

                                                                                                                                       The landscaping design for the proposed
                                                                                                                                       development will support and complement the
                                                                                                                                       surrounding built form and be native to the local
                                                                                                                                       area.

                                                                                                                                       Additionally, a 1,000m2 and 1,542m2 area of the
                                                                                                                                       subject site will be dedicated to Council as open
                                                                                                                                       space park linkages (minimum 20m width) through
                                                                                                                                       the site for recreation and future pedestrian
                                                                                                                                       connectivity (see Appendix C for details) which will

Page 5

                                                                                                                            be embellished with landscaping treatments to
                                                                                                                            enhance the visual amenity of the site.

                                                                                                                            Given the specific nature of this subdivision
                                                                                                                            proposal described above, the subdivision is
                                                                                                                            justified in terms of lot size, shape and will have no
                                                                                                                            detrimental amenity impacts on the surrounding
                                                                                                                            area.
PO6                                                               No acceptable outcome provided                            Not applicable.
Development provides for irregular shaped lots to be created
only where:

(a) the creation of regular lots is impractical such as at a
    curve in the road or because of topographical constraints;
(b) safe access and visual exposure to and from the site can
    be provided, while not adversely impacting on the
    functionality of the surrounding road network;
(c) it is desirable to avoid clearing of vegetation and the
    fragmentation of habitat in ecologically important areas;
    and
(d) the irregular lot is demonstrably suitable for its intended
    purpose.
Lot Layout
Site Responsive Design                                            AO7.1
PO7                                                               If located in the Low density residential zone, Medium    Complies.
Development provides for a lot layout and configuration of        density residential zone, High density residential
roads and pathways that is responsive to:-                        zone, Tourist accommodation zone or Community             As stated in Section 5.3 of the Planning Report, the
                                                                  facilities zone and intended for a residential use, any   site is identified as comprising Flood and Inundation
(a) the setting of the site within an urban or non-urban          new lot is located outside the modelled flood level of    Extent in accordance with Council’s Flood Hazard
    context;                                                      the 1% AEP (1:100 year ARI) water surface levels or       Overlay. However, this hazard area only encroaches
                                                                  where not modelled, above the highest known flood         into the north-eastern extremity of the site and has
(b) any natural environmental values present on, or adjoining     level.                                                    no impact on the purpose of the subdivision. A bio-
    the site;
                                                                                                                            retention basin will be provided in this small flood
(c) any natural hazards affecting the site or adjoining land                                                                affected area (see Appendix C & E for details).
    such that the number of properties or persons at risk is                                                                Notably a Flood Hazard Assessment of the Lake
    not increased;                                                                                                          Macdonald Drive – Dianella Court Intersection was
(d) the terrain of the land, minimising the need for                                                                        recently prepared for Noosa Shire Council by Hydra
    earthworks;                                                                                                             Logic. This Report found (Appendix I):
(e) any places of cultural heritage significance or character
    areas present on, or adjoining the site; and                                                                            ‘Detailed flood modelling of the catchment and
                                                                                                                            subject intersection has demonstrated the capacity
                                                                                                                            of the existing culverts provides 10% AEP design
                                                                                                                            flood immunity to the intersection. For larger and

Page 6

(f) any important landmarks, views, vistas or other areas of                                                                 rarer flood events of less than 2% AEP the model
    high scenic quality present on, or able to be viewed from,                                                               results show the intersection will experience water
    the site.                                                                                                                over the road to depths of less 0.3 m for a 1% AEP
                                                                                                                             flood event for relatively short durations of less
Editor’s Note— Development of land affected by constraints                                                                   than 1.5 hours.
shown on overlay maps will be subject to overlay codes .
                                                                                                                             The flood modelling has also demonstrated that
                                                                                                                             should a significant blockage of the culverts occur
                                                                                                                             during a major rainfall flood event the depths of
                                                                                                                             inundation across the culvert would not be expected
                                                                                                                             to significantly change, however, the inundation
                                                                                                                             may persist for longer periods.’

                                                                                                                             The proposed development will factor in these
                                                                                                                             findings, noting the bio-retention basin and
                                                                                                                             additional drainage infrastructure should aid in
                                                                                                                             reducing inundation periods at the Lake Macdonald
                                                                                                                             Drive    –  Dianella   Court    Intersection (see
                                                                                                                             Appendix C, E & I for details).
                                                                 AO7.2                                                       Not applicable.
                                                                 Flood immunity for development areas is not achieved
                                                                 by filling land below the 1% AEP (1:100 year ARI) flood
                                                                 level.
                                                                 AO7.3                                                       Not applicable.
                                                                 All reconfigured lots on land subject to a constraint or
                                                                 valuable feature identified on an overlay map contains
                                                                 a building envelope marked on a plan of
                                                                 development that demonstrates that there is an area
                                                                 sufficient to accommodate the intended purpose of the
                                                                 lot, that is not subject to the constraint or valuable
                                                                 feature or that appropriately responds to the constraint
                                                                 or valuable feature.
                                                                 AO7.4                                                       Not applicable.
                                                                 New lots with a site area less than 4,000m² in area
                                                                 have a slope not exceeding:

                                                                 (a) 10% side slope (crossfall); or
                                                                 (b) 5% lengthwise slope (longitudinal fall).
                                                                 AO7.5                                                       Complies.
                                                                 Lot boundaries, services, utilities and roads are aligned
                                                                 to avoid traversing ecologically important                  As stated in Section 5.1 of the Planning Report, the
                                                                 areas and ecological linkages.                              subject site is included in the Biodiversity Overlay –
                                                                                                                             Area of Biodiversity Significance. the mapped area
                                                                                                                             is dominated by slash pine and Gympie messmates

Page 7

                                                                                                                           which are both plantation timber and were planted
                                                                                                                           in 1973 / 74 for future harvest and reducing weed
                                                                                                                           infestation at the time. These species are not
                                                                                                                           endemic to the area and accordingly a tree clearing
                                                                                                                           permit has been granted (OPW23/0190). While
                                                                                                                           the pine plantation may provide some low value
                                                                                                                           habitat, it has a more negative effect on
                                                                                                                           surrounding native biodiversity values. The new
                                                                                                                           native plantings in the 2,500m² of open space plus
                                                                                                                           the landscaped buffer will provide high value
                                                                                                                           ecological benefits.
                                                                 AO7.6                                                     Complies.
                                                                 Development does not result in significant modification
                                                                 to natural landform or landscape features including:      See Appendix C to G for details.

                                                                 (a)   waterways and drainage lines;
                                                                 (b)   native vegetation or significant character trees;
                                                                 (c)   understorey vegetation;
                                                                 (d)   slope;
                                                                 (e)   rock outcrops; or
                                                                 (f)   views.
                                                                 AO7.7                                                     Not applicable.
                                                                 Development retains or provides viable ecological
                                                                 corridors for wildlife movement.
                                                                 AO7.8                                                     Not applicable.
                                                                 Where no riparian buffer is nominated through
                                                                 the Biodiversity, Waterways and Wetlands
                                                                 Overlay Map in Schedule 2, a vegetated buffer is
                                                                 provided no less than 10 metres wide, measured from
                                                                 the centreline of any stream.
                                                                 AO7.9                                                     Not applicable.
                                                                 Ecologically important areas are formally protected for
                                                                 the long term through environmental covenant or           Refer to comment above in relation to AO7.5.
                                                                 transferal to public ownership or through gazettal of a
                                                                 nature reserve.
Climate Responsive Design                                        AO8.1                                                     Not applicable given the nature of the subdivision
PO8                                                              The lot design maximises the number of lots where the     proposal and the size of the resulting lots.
The street design and lot orientation facilitates the
                                                                 longest axis of the lot has a general east-west
construction of energy efficient buildings that respond to the
local climate conditions by:                                     orientation.
                                                                 AO8.2                                                     Not applicable.
(a) maximising solar access to the north;                        The street pattern maximises the number of streets
(b) minimising solar access to the west;                         running in a general north-south direction.

Page 8

(c) proportioning lots and building envelopes to accommodate        AO8.3                                                  Not applicable.
    energy efficient building orientation;                          For development within the Low density residential
                                                                                                                           The subject site is not included in the Low Density
(d) maximising access to any prevailing summer breezes; and         zone each lot contains a rectangular house site
                                                                                                                           Residential Zone
(e) minimising exposure to prevailing winter winds                  area where the long axis faces true north or is no
                                                                    more than 20 degrees off true north and has minimum
                                                                    dimensions of 10 metres x 15 metres.
Neighbourhood Design                                                                                                       Complies.
PO9                                                                 AO9.1
Development provides for a lot layout, land use and                 Lots are arranged to front streets and public open     The lots will gain vehicle access from the start of
infrastructure configuration that:                                  space.                                                 Dianella Court. On street parallel carparking will be
                                                                                                                           provided along the western side of the new road.
(a) provides for an efficient land use pattern;
                                                                                                                           Proposed Lot 1, 2 & 3 will gain access via the
(b) creates compact and walkable neighbourhoods that are well                                                              establishment of a new 18-23m wide road reserve
    connected to centres, employment, education facilities,
                                                                                                                           inclusive of a mostly 10m wide buffer along the
    community services, open space and recreation facilities;
                                                                                                                           eastern edge of the road. Each lot will be provided
(c) creates useable and interconnected movement and open                                                                   direct access to this road via new driveway
    space networks;                                                                                                        crossover points (see Appendix C & E for details).
(d) effectively connects and integrates the site with existing or                                                          Complies
    planned development on adjoining sites;                         AO9.2
(e) provides for moderate and large size developments to have       Development maximises opportunities for casual         Proposed open space areas and new road will be
    multiple access points;                                         surveillance and avoids areas of concealment by        designed in accordance with AO9.2 & AO9.3 (see
                                                                    ensuring pathways and public open space have           Appendix C for details).
(f) promotes a sense of community identity and belonging;           defined edges and are visually exposed to roadways.
(g) promotes a variety of streetscapes;
                                                                                                                           Complies
(h) provides for a high level of amenity, having regard to          AO9.3
    potential noise, dust, odour and lighting nuisance sources;     Neighbourhoods (including roads, pathways and open     Proposed open space areas and new road will be
(i) integrates prominent site features including landmarks,         space) are designed with a high degree of legibility   designed in accordance with AO9.3 (see
    native vegetation and views into the design;                    with public spaces and corridors easy to find and      Appendix C for details).
(j) discourages crime or antisocial behaviour by facilitating       recognise.
    casual surveillance of streets, paths and public open space;
(k) avoids the sporadic or out-of- sequence creation of lots;
    and
(l) protects and enhances ecologically important areas and
    provides for the clustering of lots into cleared areas.

 Infrastructure                                                      No acceptable outcome provided.                       Complies.
 PO10
 Development accommodates and provides for the                                                                             Proposed Lots 1, 2 & 3, and Balance Lot 100 will
 efficient and timely delivery of infrastructure                                                                           connect to the following infrastructure services
 appropriate to the site’s setting and intended use.                                                                       (Appendix E, F & G):
                                                                                                                            Reticulated electricity;
                                                                                                                            Reticulated sewerage;

Page 9

                                                                                                                          Reticulate telecommunications; and
                                                                                                                          Reticulated water.
 PO11                                                             No acceptable outcome provided                       Complies.
 Roadway and pathway layout are predominantly rectilinear
 with a high degree of permeability.                                                                                   The proposed new road and pathway have been
                                                                                                                       designed in accordance with PO11 (see
 Editor’s Note— Further detail on traffic and the road                                                                 Appendix E for details).
 network is addressed in Part 9.4.8 Transport Code.
Infrastructure and services
PO12                                                             AO12.1                                                Proposed Lots 1, 2 & 3, and Balance Lot 100 will
New lots are located, sized and configured so as to ensure       All lots are connected to power supply and            connect to the following infrastructure services
each lot is capable of being serviced by appropriate levels of   telecommunications services and where located         (Appendix E, F & G):
infrastructure including:                                        within the Urban boundaries, power supply and            Reticulated electricity;
                                                                 communications infrastructure are provided
(a)   power supply;                                              underground.                                             Reticulated sewerage;
(b)   telecommunications; and                                                                                             Reticulate telecommunications; and
(c)   where within Local Plan Areas                                                                                       Reticulated water.
(d)   reticulated water supply;
                                                                 AO12.2                                                Complies.
(e)   reticulated sewerage; and
                                                                 If located in a water service area each new lot can
(f)   stormwater drainage.
                                                                 be connected to Unitywater’s water supply
 .                                                               network.                                              See AO12.1 comment.

                                                                 AO12.3                                                Complies.
                                                                 If located in a sewerage service area each new lot
                                                                 can be connected to Unitywater’s sewerage
                                                                 network.                                              See AO12.1 comment.

                                                                 AO12.4                                                Complies.
                                                                 If located in a Local plan area lots can be
                                                                 connected to Council’s stormwater drainage
                                                                 network.                                              The proposal will provide additional stormwater
                                                                                                                       drainage infrastructure (see Appendix E for
                                                                                                                       details).

                                                                 AO12.5                                                Not applicable.
                                                                 If not in a sewerage service area each lot has        Site is in a sewerage service area.
                                                                 sufficient area and other attributes to ensure
                                                                 efficient and effective on-site sewerage disposal.
PO13                                                             AO13.1                                                Complies.
Each lot is provided with safe and convenient vehicle access     Vehicular access for the development is consistent    The lots will gain vehicle access from the start of
                                                                 with the function and design of the road it           Dianella Court. On street parallel carparking will be
                                                                 takes access from.                                    provided along the western side of the new road.

Page 10

                                                                                                                     Proposed Lot 1, 2 & 3 will gain access via the
                                                                                                                     establishment of a new 18-23m wide road reserve
                                                                                                                     inclusive of a mostly 10m wide buffer along the
                                                                                                                     eastern edge of the road. Each lot will be provided
                                                                                                                     direct access to this road via new driveway
                                                                                                                     crossover points (see Appendix C & E for details).
                                                                AO13.2                                               Not applicable.
                                                                Development does not require new or
                                                                changed access to a state-controlled road that is    Site does not adjoin a State-Controlled Road.
                                                                a limited access road unless in accordance with
                                                                the limited access policy for the state-controlled
                                                                road.
                                                                AO13.3                                               Not applicable.
                                                                Access easements are in appropriate locations for
                                                                safe access and egress, and supply appropriate       No access easements proposed (see Appendix C
                                                                widths and levels of service for the number of       for details).
                                                                vehicles that will utilise them as per the
                                                                requirements of Council’s Planning Scheme Policy
                                                                PSP6 Engineering design standards – Roads,
                                                                drainage and earthworks.

                                                                Editor's note- Reference should be made to the
                                                                Queensland Government's Development
                                                                Assessment Mapping System to confirm which are
                                                                state-controlled roads or limited access roads.
Movement Network
Traffic                                                          No acceptable outcome provided                      Complies.
PO14
Traffic generated by the development is within the acceptable                                                        The proposed development has / will implement all
capacity of external roads and does not have an adverse                                                              findings and recommendations of the Traffic Impact
impact upon the functioning of the road network.                                                                     Assessment to ensure the traffic generated is within
                                                                                                                     the acceptable capacity of external roads (see
Editor’s Note— Further detail on traffic and the road network                                                        Appendix H for details).
is addressed in Part 9.4.8 Transport Code

Roads and Pathways                                               AO15.1                                              Complies.
PO15                                                             Where involving the construction of a new road,
Development involving the creation of new roads and              road planning and design supports the hierarchy     The proposed new road will achieve compliance
pathways ensures infrastructure—                                 and functional aspects identified in Council’s      with AO15.1 to AO15.4. Details will be provided
                                                                 Planning Scheme Policy PSP6 on Engineering          during the subsequent Operational Works Phase.
(a) provides convenient, safe and efficient movement for all     design standards – Roads, drainage and
    modes of transport between land use activities;              earthworks.

                                                                 Editor’s Note— Further detail on road and

Page 11

(b) prioritises pedestrian movement and bicycle use over            pathway networks is provided in Part
    vehicle movements;                                              9.4.8 Transport Code
(c) facilitates efficient, safe and accessible bus services that
    connect to existing and future public passenger transport       AO15.2
    facilities;                                                     The street layout is generally rectilinear and does
(d) provides through roads and minimises the use of culs-de-        not rely on culs-de-sac, or where the use of a cul-
    sac;                                                            de-sac is unavoidable because of the natural
(e) minimises the extent of earthworks required by being            features of the site, it does not exceed a length of
    sympathetic to the terrain;                                     200 metres.
(f) allows for unimpeded and practical access to each
    proposed lot; and                                               AO15.3
(g) provides for mature street trees.                               Pathways and pedestrian routes are planned to
                                                                    provide clear, safe connections between
                                                                    residential, open space, transit stops and retail
                                                                    areas, and are located along, or are visible from,
                                                                    streets or other public spaces.

                                                                    AO15.4
                                                                    Sufficient space and soil depth is provided for the
                                                                    planting of street trees for shade, amenity and
                                                                    habitat purposes.




                                                                   AO16                                                       Not applicable.
 PO16                                                              If within 1 kilometre of the Pathways Network identified
 The subdivision layout is designed to facilitate pedestrian       in the Local Government Infrastructure Plan located in
 and cyclist linkages with adjoining sites in the immediate        Part 4, the subdivision design and layout includes
 area.                                                             pathways:

                                                                   (a) located in accordance with the Pathways Network
                                                                       identified in the Local Government Infrastructure
                                                                       Plan; or
                                                                   (b) linking to the Pathways Network identified in
                                                                       the Local Government Infrastructure Plan.

Page 12

                                                                 No acceptable outcome provided                             Not applicable.
 PO17
 Development on land within activity centres with active
 frontages are provided with access from a rear lane or
 other access streets to reduce potential conflicts with
 pedestrians and cyclists.
Open Space Network
PO18                                                             AO18.1                                                     Not applicable.
Development provides for parks, drainage reserves and open       Active parkland or open space which links to active
space infrastructure that:-                                      parkland is provided in accordance with the Council’s      A 1,000m2 and 1,542m2 area of the subject site
                                                                 infrastructure network planning;                           will be dedicated to Council as open space park
(a) provides for a range of passive and active recreation                                                                   area (see Appendix C for details).
    settings, offering a range of informal and formal            OR
    experiences to the community;
(b) accommodates adequate facilities to meet the needs of        AO18.2
    the community and is designed to maximise use by the         Park contributions are paid in accordance with the
    community it serves;                                         applicable infrastructure instrument.
(c) provides opportunities for all age groups and levels of
    mobility;                                                    AO18.3
(d) is well distributed and contributes to the legibility and    Land intended for public open space complements
    character of the specific town, village or locality;         existing adjacent and surrounding open space areas
(e) creates attractive settings and focal points for the         and physical linkages to these areas are provided.
    community, designed as attractive and enjoyable,
    functional and safe places to meet and recreate;             AO18.4
(f) benefits the amenity of adjoining land uses;                 Open space is provided adjacent to waterways, with
                                                                 roads servicing the linear parkland and lots located on
(g) facilitates the retention and protection of ecologically
                                                                 the opposite side of the road to the waterways.
    important areas, wetlands, waterways, drainage lines and
    native habitat areas, their associated buffers, ecological
                                                                 AO18.5
    linkages and other natural and cultural features;
                                                                 A park has direct road frontages of a minimum of 25%
(h) incorporates appropriate measures for stormwater and
                                                                 of the total allotment boundary of the park to provide
    flood management;
                                                                 physical access and visibility.
(i) is cost effective to maintain; and
(j) is dedicated as public land in the early stages of the       AO18.6
    subdivision.                                                 Public open space has good connectivity for users via
                                                                 pedestrian and cycle paths.

                                                                 AO18.7
                                                                 Landscaping is designed to create aesthetically pleasing
                                                                 open space areas and to suit the type, setting and
                                                                 purpose of the particular park.

                                                                 AO18.8
                                                                 Active parkland in all areas other than the Low impact
                                                                 industry zone and Medium impact industry zone will

Page 13

                                                               contain embellishment in accordance with the Local
                                                               Government Infrastructure Plan in Part 4 such as:

                                                               (a) children’s play facilities catering for various ages
                                                                   including a soft fall surface where required and a
                                                                   shade cover over play equipment;
                                                               (b) seating;
                                                               (c) picnic table/s with seats; and
                                                               (d) landscaping.

                                                                Editor’s Note— Further detail on Landscaping is
                                                                addressed in Part9.4.5 Landscaping Code
PO19                                                           AO19.1                                                     Not applicable.
Land provided for active recreation areas is of a physical     Active parkland is of a usable shape free of irregular
standard and condition suitable for the intended uses and is   boundaries.
not subject to physical or other constraints including
contamination, environmental or biophysical constraints or     AO19.2
legislative protection that would encumber its use.            Active parkland is located on land that is exclusive of—

                                                               (a) flood    inundation   below     the   20% AEP (1:5
                                                                   year ARI level);
                                                               (b) land affected by stormwater or overland flow
                                                                   discharge from adjacent allotments;
                                                               (c) drainage reserves and detention basins, which
                                                                   cannot be shown to safely and effectively contribute
                                                                   to the network of parks and open space areas;
                                                               (d) land with a slope, or subject to cut or fill with a
                                                                   batter slope, that exceeds a slope of 15%;
                                                               (e) areas of land less than 15 metres wide, such
                                                                   as access and service and utility easements;
                                                               (f) land required to serve primarily as a buffer area to
                                                                   any existing development or major transport
                                                                   corridor; and
                                                               (g) power easements.

                                                                AO19.3
                                                                At least 10% of the total open space provision for
                                                                active parkland is exclusive of flood inundation below
                                                                the 1% AEP (1:100 year ARI level or the highest
                                                                recorded flood level), whichever is the greatest.
Small Residential Lots

Page 14

PO20                                                               AO20                                                       Not applicable.
Residential lots less than 600m2:                                  Within the Low Density Residential zone, new lots of
                                                                   less than 600m²:
(a) occur only where they are consistent with the size of
    established adjacent lots;                                     (a) are no smaller than the size of established adjacent
(b) are not less than 500m2 in area;                                   lots;
(c) are free of physical constraints or encumbrances that would    (b) are free of easements;
    restrict the siting of a house;                                (c) are regular in shape with a width to depth ratio of
(d) have area and dimensions that can accommodate an                   approximately 1:2;
    appropriate house site area without siting variations;         (d) do not have a slope greater than 10%;
(e) are distributed across a development to create diversity in    (e) can accommodate a house and sufficient car
    lots; and                                                          parking without encroaching into boundary
(f) do not result in excessive driveways at intersections or           clearances or prescribed building setbacks;
    corners.                                                       (f) allow for landscape and tree planting in deep soil
                                                                       zones to soften built form elements;
                                                                   (g) are not created by further dividing an existing rear
                                                                       (battle-axe) lot; and
                                                                   (h) are not located at the end of a T-intersection or at
                                                                       a bend in the road.
Rear Lots
PO21                                                                AO21.1                                                    Not applicable.
Rear (battle-axe) lots are created only where:-:                    The minimum area of the rear lot, exclusive of
                                                                    any access strip, complies with the lot reconfiguration   No rear lots proposed (see Appendix C for
(a) it would not be desirable nor practicable for the site to be    outcomes in Table 9.5.1.4 Minimum lot size and            details).
    reconfigured so that all lots have full frontage to a road;     dimensions providing that no rear access lot has a lot
(b) located in the Low density residential zone, Rural              size less than 600m2 exclusive of access strip.
    residential zone or Rural zone;
(c) development positively contributes to the character of the      AO21.2
    neighbourhood;                                                  No more than 10% of lots within a subdivision are
(d) development provides a high standard of amenity for             rear lots or lots accessed via an access strip.
    residents and other users of the rear lot and adjoining
    properties;                                                     AO21.3
(e) the lot is large enough to accommodate anticipated land         No more than two rear lots are located at the end of a
    uses including car parking and manoeuvring;                     cul-de-sac.
(f) development is not detrimental to the use and amenity of
    adjoining lots through loss of privacy, sunlight or breezes     AO21.4
    once buildings are constructed;                                 No rear lot shares a common boundary with more
                                                                    than four other lots.
(g) vehicular access to rear lots will not have a detrimental
    impact on lots adjoining the access strip due to excessive
                                                                    AO21.5
    noise, light, dust, stormwater runoff and the like;
                                                                    No more than two rear lots or rear lot access strips
(h) access arrangements do not adversely affect the safety and
                                                                    directly adjoin each other.
    efficiency of the road from which access is gained;
(i) their creation does not prejudice the anticipated               AO21.6
    development of adjoining land.

Page 15

                                                                  No existing lot with a primary street frontage of less
                                                                  than 12 metres is further divided unless safe access to
                                                                  the new lot is provided to a secondary street to which
                                                                  a frontage of at least 12 metres is provided.

                                                                  AO21.7
                                                                  Where two rear lots adjoin each other, a single
                                                                  common driveway and reciprocal access easements
                                                                  are provided.

                                                                  AO21.8
                                                                  No more than three lots gain access from the
                                                                  same access strip.

                                                                  AO21.9
                                                                  Any lot with a road frontage has no more than
                                                                  one rear lot created to its rear and has a rear
                                                                  lot access strips located on no more than one side.

                                                                  AO21.10
                                                                  The gradient of the access strip does not exceed 10%.

                                                                  AO21.11
                                                                  Access strips have a minimum width of 4.5 metres.
Rural lots severed by a road
PO22                                                                                                                        Not applicable.
                                                                  No acceptable outcome provided
In the Rural Zone, one lot may be divided into two lots less
than 100 hectares in area where there is a compliance with
the South East Queensland Regional Plan and each resultant
lot is relatively free of physical constraints such that it can
accommodate a dwelling house, effluent disposal,
vehicular access and other improvements and land uses that
are consistent with the purpose of the Rural Zone.
Volumetric Subdivisions
 PO23                                                                                                                       Not applicable.
 Development provides that the subdivision of space above         No acceptable outcome provided
 or below the surface of land facilitates efficient
 development in a manner that is consistent with the overall
 outcomes for the zone and Local plan area in which
 the site is located.
Stormwater Management

Page 16

PO24                                                                                                                    Complies.
                                                                No acceptable outcome provided
Development provides for the effective drainage of lots and
roads in a manner that:-                                                                                                Water Quality Objectives are mandated by the
                                                                                                                        State Government. They are identified in the State
(a) maintains the natural flow regime;                                                                                  Planning Policy 2017 (SPP). The SPP includes the
(b) effectively manages stormwater quality and quantity; and                                                            following triggers to that are required to achieve
(c) ensures no adverse impacts on receiving waters and                                                                  water quality objectives:
    surrounding land.
                                                                                                                        “(2) Reconfiguring a lot for an urban purpose that
                                                                                                                        involves premises 2500m2 or greater in size and will
 Editor’s Note— Requirements for the design and
                                                                                                                        result in six of more lots”.
 construction of stormwater management infrastructure
 are addressed in Part 9.4.9 Water Quality and Drainage
                                                                                                                        Based on the above, there are no water quality
 code
                                                                                                                        objectives that are required to be achieved for this
                                                                                                                        development. However, it is noted that a bio-
                                                                                                                        retention basin will be provided at the northeastern
                                                                                                                        corner of the subject site to aid in maintaining
                                                                                                                        stormwater quality for the subject site.

                                                                                                                        Stormwater for any development on proposed Lot
                                                                                                                        1 and 2 will have a lawful point of discharge
                                                                                                                        connected to the bio-retention basin. Stormwater
                                                                                                                        from the new road will be captured and discharged
                                                                                                                        into the bio-basin. Lot 3 will be provided with a
                                                                                                                        lawful point of discharge in the south east corner of
                                                                                                                        the Lot which will drain to the drainage reserve
                                                                                                                        beyond (see Appendix E for details).

                                                                                                                        The proposed measures will provide a significant
                                                                                                                        amenity improvement to properties along the
                                                                                                                        adjoining Dianella Court by providing additional
                                                                                                                        infrastructure for stormwater discharge and a bio-
                                                                                                                        retention basin for stormwater quality management
                                                                                                                        as opposed to sheet flowing to the east under the
                                                                                                                        current scenario.
Conflicting land uses
 PO25                                                                                                                   Not applicable.
 New lots for residential development do not adjoin land        No acceptable outcome provided
 located in the Medium impact industry zone or the Low
 impact industry zone.
Rearrangement of Lot Boundaries
 PO26                                                          AO26                                                     Not applicable.
 Development provides that the rearrangement of lot            The rearrangement of lot boundaries results is an
 boundaries is an improvement on the existing situation.       improvement to the existing situation whereby the size

Page 17

                                                                  and dimensions of proposed lots comply more fully with     The proposed development does not involve a
                                                                  Table 9.5.1.4 Minimum lot size and dimensions. and at      boundary realignment.
                                                                  least one of the following is achieved:

                                                                  (a) the rearrangement of lots remedies an existing
                                                                      boundary encroachment by a building or structure;
                                                                  (b) the rearranged lots will be made more regular in
                                                                      shape;
                                                                  (c) access is provided to a lot that previously had
                                                                      no access or an unsuitable access;
                                                                  (d) the rearranged lots better meet the overall
                                                                      outcomes for the zone and the local plan area in
                                                                      which the site is situated;
                                                                  (e) the rearrangement of lots provides for a significant
                                                                      improvement in rural productivity; or
                                                                  (f) the rearrangement of lots results in a significant
                                                                      improvement in the protection of environmental
                                                                      values.
If involving a standard format lot with common property such as requiring a community management scheme under the Body Corporate and Community
Management Act 1997
 PO27                                                                                                                        Not applicable.
 Community title subdivision only occurs once construction of      No acceptable outcome provided
 approved buildings on site is completed.

 Editor’s Note—As a building is to be constructed prior to
 sealing of subdivision plans, assessment of the development
 is to be undertaken as part of the development application
 for a material change of use if that development is
 assessable under the planning scheme. Reconfiguring a
 lot can be assessed simultaneously or subsequently against
 the relevant parts of this code.
PO28                                                                                                                         Not applicable.
Development provides internal access ways and driveways            No acceptable outcome provided
which:

(a) are designed to clearly indicate the function of
    the access way; and
(b) provide acceptable levels of access, functionality, safety,
    amenity and convenience for users, as well as catering for
    car parking facilities.
PO29                                                               No acceptable outcome provided                            Not applicable.
Community title subdivision for residential purposes only

Page 18

occurs—

(a) where lots are located close to services and facilities;
(b) in the Low density residential zone, Medium density
    residential zone, High density residential zone, Tourist
    accommodation zone or Centre zone;
(c) where they are consistent with the character of the locality
    they are located in;
(d) if appropriate house site areas and car parking needs can
    be accommodated;
(e) where they are supplied with adequate infrastructure to
    meet the needs of users;
(f) where they minimise adverse effects on the environment;
(g) if they are of suitable shape and slope to minimise
    constraints to development; and
(h) if they are sufficient areas to provide reasonable amenity
    for users.
PO30                                                               No acceptable outcome provided   Not applicable.
Community title subdivisions intended for business uses:

(a) only occur in a centre zone or industry zone; and
(b) provide adequate areas on site for vehicular parking,
    private and        communal     open space,     landscaping
    and site facilities to meet the needs of users.

Page 19

                                                              COOROY LOCAL PLAN CODE

Application for a Development Permit for Reconfiguring a Lot by Subdivision (1 Lot into 3 Lots + Balance Lot), involving land
                 described as Lot 105 on SP118458, situated at 62 Lake MacDonald Drive, Cooroy QLD 4563.


             Performance Outcomes                                            Acceptable Outcomes                      Comment
Development in Cooroy Local Plan Area generally (All Zones)

PO1                                                        No acceptable outcome provided          Complies.
Development enhances the role of Cooroy as the
largest centre in the Noosa Hinterland, providing a wide                                           The purpose of the proposed development was to
range of business and employment services, recreation                                              consolidate future cemetery land within the
facilities, community services, housing choice and a                                               proposed / approved Lot 100 (Balance Lot) and
limited range of visitor services.                                                                 enable the remaining Lots to be remediated from
                                                                                                   any land contamination (see Appendix C
                                                                                                   & RAL24/0014 for details). This will allow Lot 1,
                                                                                                   2 & 3 to be utilised for future housing / community
                                                                                                   purposes.

                                                                                                   In addition, a 1,000m2 and 1,542m2 area of the
                                                                                                   subject site will be dedicated to Council as open
                                                                                                   space park area (see Appendix C for details).

PO2                                                        No acceptable outcome provided          Complies.
Development contributes to the lifestyle and amenity
of residents of Cooroy and its surroundings.                                                       Proposed Lot 1, 2 & 3 will gain access via the
                                                                                                   establishment of a new 18-23m wide road
                                                                                                   inclusive of drainage infrastructure stemming
                                                                                                   from Dianella Court.

                                                                                                   A 5-10m landscaped buffer will be provided on the
                                                                                                   eastern extent of the proposed new road to
                                                                                                   ensure no adverse amenity outcomes occur with
                                                                                                   the neighbouring properties to the east (see
                                                                                                   Appendix C & D for details).

                                                                                                   The proposed drainage infrastructure and bio-
                                                                                                   retention basin will provide a significant amenity
                                                                                                   improvement to properties along the adjoining
                                                                                                   Dianella    Court     by   providing     additional
                                                                                                   infrastructure for stormwater discharge and a bio-

Page 20

                                                                                                                         retention basin   for  stormwater      quality
                                                                                                                         management (see Appendix E for details).




PO3                                                   AO3.1                                                              Not applicable.
Development contributes to the establishment of       Development adjacent to a gateway or special place or on land
attractive streetscapes and gateways to enhance the   identified as a key corner on Figure 7.2.2.4 (Cooroy Framework     The subject site is not located on or in close
sense of arrival and the character of Cooroy.         and Character Plan):                                               proximity to the Figure.
                                                      a) incorporates architectural and landscape treatments which
                                                          emphasise the corner location as shown in figure AP3-
                                                          10A and figure AP3-10B; and
                                                      b) incorporates building materials such as varied roof forms,
                                                          changes in materials and variations in projected and
                                                          recessed elements and facades.
                                                      AO3.2                                                              Not applicable.
                                                      Development adjacent to a primary streetscape treatment area
                                                      identified on Figure 7.2.2.4 (Cooroy Framework and Character       The subject site is not located on or in close
                                                      Plan) provides streetscape improvements appropriate to the         proximity to the Figure.
                                                      location, setting and context of the development and
                                                      complements existing or proposed streetscape works in the local
                                                      area.
                                                      AO3.3                                                              Not applicable.
                                                      Development on Key Development Sites identified on Figure
                                                      7.2.2.4 (Cooroy Framework and Character Plan) incorporates a       The subject site is not located on or in close
                                                      high standard of architectural design and landscape treatment      proximity to the Figure.
                                                      consistent with the streetscape character.

                                                      Editor’s Note— For further guidance and context in interpreting
                                                      the Framework and Character Plans please refer to PSP7 -
                                                      Framework and Character Plans.
PO4                                                   AO4                                                                Not applicable
The visual amenity surrounding the major road         Development adjacent to Myall Street, Mary River Road, Elm
network and entry is protected and enhanced.          Street, Cooroy Noosa Road, Tewantin Road and Diamond Street        The subject site is not adjacent to the identified
                                                      incorporates landscaping that complements the natural species      streets.
                                                      occurring in the local area, protects existing vegetation within
                                                      the road reserve and incorporates design elements that add
                                                      visual interest to the streetscape.
PO5                                                   AO5.1                                                              Not applicable
Development retains and enhances key heritage and     Development retains landmarks, memorials and monuments
landscape elements including historical landmarks,    including but not necessarily limited to those identified on
existing character trees and areas of                 the Heritage and Character Areas Overlay maps in Schedule 2.

Page 21

significant vegetation contributing to the setting and   AO5.2                                                                 Not applicable.
character of the local plan area.                        Development retains and enhances existing mature trees and
                                                         character vegetation contributing to the vegetated backdrop and       The subject site is not identified in the areas
                                                         streetscape character of the local plan area including:               outlined in AO5.2.

                                                         a)   mature trees, particularly along Maple and Emerald Avenue,
                                                              Mary River Road, Myall Street and Elm Street;
                                                         b)   riparian vegetation adjacent to the Cooroy Creek and
                                                              tributaries of Six Mile Creek within the local plan area; and
                                                         c)   other character vegetation and landscaping where identified
                                                              on Figure 7.2.2.4. (Cooroy Framework and Character Plan)
PO6                                                      AO6.1                                                                 Complies.
Development retains and enhances key contextual          Development enhances and does not intrude upon important
views, to Mt Cooroy, Black Mountain range and other      sightlines to Mt Cooroy.
views to the rural and open spaces around Cooroy.        AO6.2                                                                 Not applicable.
                                                         For Cooroy district centre, buildings and structures do not
                                                         significantly interrupt or encroach upon key contextual views as
                                                         identified on Figure 7.2.2.4 (Cooroy Framework and Character
                                                         Plan) and shown in Figure 7.2.2.6.
Built form and streetscape
PO7                                                      AO7.1                                                                 Not applicable.
Buildings, structures and landscaping are consistent     Development retains or reuses buildings that have cultural
with and reflective of the traditional country town      heritage or townscape significance, including where subject to        No built form proposed. All existing built form will
character of Cooroy in terms of form, proportion,        the Heritage and Character Overlay (as mapped in Schedule 2) or       be retained (see Appendix C & E for details).
composition and use of materials.                        identified as a heritage site or character area on Figure
                                                         7.2.2.4 (Cooroy Framework and Character Plan).

                                                         Editor’s Note— Section 8.2.7 (Heritage and Character
                                                         Overlay) sets out requirements for development on heritage
                                                         places and in character areas.
                                                         AO7.2                                                                 Not applicable.
                                                         Development is compatible with existing buildings including
                                                         Federation and Art Deco styles, without mimicking such styles.        See AO7.1 comment.
                                                         AO7.3                                                                 Not applicable.
                                                         Roof forms use traditional Queensland style roof designs,
                                                         including gable, hip and valley, pitched, or multiple gable roof      See AO7.1 comment.
                                                         forms with a roof pitch of no less than five degrees, examples
                                                         shown in Figure AP3-6B.
                                                         AO7.4                                                                 Not applicable.
                                                         For residential buildings, roof form is visible from the street and
                                                         not concealed behind parapets.                                        See AO7.1 comment.

Page 22

                                                         AO7.5                                                                Not applicable.
                                                         Buildings are designed to:
                                                         a) reflect the traditional Queensland vernacular;                    See AO7.1 comment.
                                                         b) suit the local subtropical climate;
                                                         c) incorporate lightweight materials such as timber;
                                                         d) be elevated above the ground on sloping or low-lying lots;
                                                         e) incorporate open verandahs, open balconies with transparent
                                                              or open balustrades or shaded patios for outdoor living; and
                                                         f) allow for landscaping integrated with the buildings on site.

                                                         Editor’s note—Refer to Figure AP3-6B for examples of traditional
                                                         Queensland vernacular design.
                                                         AO7.6                                                                Not applicable.
                                                         Boundary setbacks provide space for trees between buildings.
                                                                                                                              See AO7.1 comment.
Centres and Services
PO8                                                      No acceptable outcome provided                                       Not applicable
Cooroy town centre functions as a district centre with
a wide range of business and community functions,                                                                             The subject site is not in the Cooroy City Centre.
servicing Cooroy and surrounding hinterland
communities.
PO9                                                      AO9                                                                  Not applicable
Maple Street and Emerald Street function as              Development maintains the primacy of Maple Street and Emerald
traditional pedestrian orientated main streets and are   Street as attractive and pedestrian-friendly main streets with a     The subject site is not in the Cooroy City Centre.
the primary retail and commercial focus of the town.     concentration of retail and commercial uses.
Development in the District Centre zone:                 AO10                                                                 Not applicable
a) is sympathetic to the country town character and      Development in the District Centre zone:
   identity of Cooroy;                                   a) respects the layout, scale and character of development on        The subject site is not in the District Centre Zone.
b) complements the traditional built form, street           adjoining sites;
   pattern and streetscape;                              b) provides detailing and articulation for horizontal emphasis
c) is low-set single or double storey with second           including awnings, parapet walls or first floor balconies;
   storeys set back from the property frontage;          c) steps buildings to reflect the natural topographic character of
d) addresses the street;                                    the street as shown in figure 7.2.2.7 and figure 7.2.2.8;
e) creates vibrant and active spaces in the public
                                                         d) incorporates a fine grain shop front appearance extending to
   realm;
                                                            roof forms which are to vary between single tenancies,
f) provides continuous weather protection for               see figure 7.2.2.7 and figure 7.2.2.8;
   pedestrians; and
g) provides integrated and functional parking
                                                         e) where identified as primary active street frontage on Figure
                                                            7.2.2.4 (Cooroy Framework and Character Plan)-- provides
   and access arrangements that do not dominate
                                                            active street frontages that incorporate shopfronts,
   the street.
                                                            indoor/outdoor cafes and restaurants and other activities
                                                            that foster casual social and business interaction for

Page 23

                                                                extended periods. Refer to Figure AP3-8A for design
                                                                outcomes for active streetscapes;
                                                           f)   has building openings overlooking the street, with the main
                                                                entrance visually emphasised in the ground floor facade; and
                                                                addressing key corner sites where indicated on Figure
                                                                7.2.2.4 (Cooroy Framework and Character Plan) and Figure
                                                                AP3-7A
                                                           g)   provides all-weather protection in the form of continuous
                                                                awnings and or light verandah structures, supported by
                                                                timber posts that match the position and distance between of
                                                                adjoining awnings where that is the dominant character of
                                                                the street, otherwise cantilevered as
                                                                per Figure 6.4.2.4, figure 6.4.2.5 and figure 7.2.2.7;
                                                           h)   incorporates signage mounted above awnings on parapet
                                                                walls reinforcing the fine grain appearance in the main
                                                                streets as per figure 7.2.2.7 and figure 7.2.2.8;
                                                           i)   includes the provision of landscaping, shaded seating and
                                                                consistent and simple paving materials on footpaths
                                                                consistent with the character of its setting including where
                                                                shown as primary streetscape treatment area on Figure
                                                                7.2.2.4 (Cooroy Framework and Character Plan);
                                                           j)   Retains a pedestrian-friendly low-speed traffic environment
                                                                with on-street parking and provides off-street car parking at
                                                                the rear or to one side of the development.
PO11                                                       No acceptable outcome provided                                       Not applicable
Development for centre activities on the eastern side
of the rail line retains a service level role supporting
the centre on the western side of the rail line by:
a) providing a range of small-scale destination
     businesses, local convenience goods and services
     for nearby residents and visitors; and
b) having a domestic scale and not resulting in
     reduced amenity for adjoining residential uses.
Housing Choice
PO12                                                       No acceptable outcome provided                                       Not applicable
Sites currently used or approved for the use of,
relocatable home parks, retirement facilities or
residential aged care facilities such as Palm Lakes
Resort, Cooroy Villages and Kabara continue to
provide such residential accommodation into the
future.

Page 24

PO13                                                     No acceptable outcome provided                                   Not applicable
Additional sites suitable for future use as aged care
are preserved and protected for aged care.
PO14                                                     AO14                                                             Not applicable.
Development provides for sites within and in close       Residential dwellings within the District centre zone:
proximity to the District centre zone to contribute to   a) do not exceed 100m2; and                                      No built form proposed. All existing built form will
housing diversity by providing small attached            b) form part of a mixed-use building with non-residential uses   be retained (see Appendix C & E for details).
dwellings, including single level apartments.                at ground level
Visitor Facilities
PO15                                                     No acceptable outcome provided                                   Not applicable
A variety of visitor accommodation options are
provided in the Cooroy local plan area to meet the
needs of visitors.
Access and connectivity
PO16                                                     No acceptable outcome provided                                   Complies.
Development is sited and designed such that it does
not diminish the ability of laneways to:                                                                                  The proposed access is suitable to service the
a) relieve traffic on streets;                                                                                            scale of the development and not negatively
b) provide convenient and safe rear access to                                                                             impact on the surrounding road network (see
    premises including service vehicles where                                                                             Appendix E & H for details).
    relevant;
c) provide safe pedestrian linkages;
d) add to the heritage character of Cooroy.
PO17                                                     No acceptable outcome provided                                   Not applicable.
Development facilitates the widening and upgrading of
laneways in the Cooroy Local Plan Area to                                                                                 The subject allotments will gain access via the
accommodate anticipated levels of traffic. Where:                                                                         establishment of a new road (see Appendix C
                                                                                                                          & E for details).
a)   access to development is taken from a laneway, a
     2 metre resumption from the laneway frontage is
     required for widening and the laneway is to be
     upgraded to the appropriate standard; or
b)   development is undertaken on a property with a
     laneway frontage, and access is not taken, a 2
     metre easement is provided for future widening
     and upgrading purposes.
PO18                                                     No acceptable outcome provided                                   Complies.
Development improves local connectivity by providing
safe and convenient pedestrian and bicycle pathways                                                                       A concrete pedestrian footpath will be provided
to and between key destinations such as the town                                                                          (see Appendix E – Pg. 3 for details).

Page 25

centre, railway station, community and sports facilities
and schools.
PO19                                                       AO19                                                               Not applicable
Development integrates with and extends the existing       Development on land including or adjoining a key
street and pathway networks including but not limited      pedestrian/cycle link shown on Figure 7.2.2.4 (Cooroy Framework
to those identified on Figure 7.2.2.4 (Cooroy              and Character Plan) facilitates these connections.
Framework and Character Plan) such that connections
to and between key local destinations are provided
and reinforced.
Environment, natural resource and recreation values
PO20                                                       AO20                                                               Complies.
Development has no significant adverse effects on          Connecting Habitat Areas as identified on Map SFM-4 -
biodiversity, natural vegetation, native fauna habitat,    Biodiversity (Strategic Framework Map) are protected from          The identified habitat area is contained within the
landscape quality, water quality or cultural heritage      fragmentation and encroachment by development.                     proposed / approved Balance Lot (Lot 100). 2
values, including those related to:                                                                                           open space areas will be dedicated to Council to
a) changes to natural drainage;                            Editor’s Note— Council may request additional information on       function as access laneways and ensuring fauna
b) disturbance to any of the wetland systems;              the proposed method of effluent disposal to ensure the nature of   movements are not disturbed (see Appendix C
                                                           the development is compatible with environmental values. Refer     & RAL24/0014 for details).
c) management of landslide and fire risk;                  to PSP1 – Preparing a well made application..
d) erosion and the transport of sediments off-site;
e) unmanaged public access;
f) effluent disposal; and
g) changes to fauna habitat and behaviour.
PO21                                                       AO21                                                               Not applicable.
Development maintains and protects an integrated           Open space corridors identified as Ecological Linkages and Major
open space network throughout the locality to—             Recreation areas on Map SFM-1 - Settlement and Map SFM-4 -
                                                           Biodiversity (Strategic Framework) are enhanced and protected
a)   provide for both passive and active recreational      from fragmentation and encroachment by development.
     pursuits;
b)   provide connectivity for pedestrians, cyclists, and
     horse riders;
c)   provide habitat connectivity for wildlife and fish
     passage;
d)   protect watercourses and drainage lines;
e)   protect vegetation on steep slopes; and
f)   form a scenic backdrop for residential
     development.
PO22                                                       No acceptable outcome provided                                     Not applicable.
Development does not adversely impact on the Lake
Macdonald water supply.                                                                                                       The subject site is not located within the Lake
                                                                                                                              Macdonald Water Supply catchment area.
Editor's Note— Section 8.2.9 (Regional

Page 26

Infrastructure Overlay code) sets out requirements for
the provision of the Lake Macdonald Water Supply
catchment.
PO23                                                     No acceptable outcome provided   Not applicable
The number and location of access points to
watercourses is controlled and managed to prevent
adverse impacts on water quality in Lake Macdonald.

Used in these records

About this file

File size
430 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix J - Code Assessment.pdf · 430 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.