Appendix C - Amended Engineering Plans

Attached to the e-mail MCU17/0551 - Information Response - 20 Trading Post Rd Cooroy.

of 74

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (14.6 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 45, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Conditions

 

STATUTORY OBLIGATIONS

Seqwater currently manages infrastructure which is critical to the delivery of water services within South East Queensland. Great
care must be exercised when working in close proximity to this critical infrastructure to prevent any damage and any risk to supply
and/or public health and safety.

Works that build over, interfere with, interfere with access to, increase or reduce the cover over, or change the surface of land in a
way causing the ponding of water over an access chamber for Seqwater’s infrastructure will require the consent of Seqwater in
accordance with the Water Supply (Safety and Reliability) Act 2008. Failure to obtain Seqwater’s consent may be a statutory
offence.

WRITTEN CONSENT AND DOCUMENTATION

 

Where works or activities:
. are within a Seqwater easement; and/or
. are being undertaken within five (5) metres of Seqwater’s infrastructure; and/ or
. interfere with, build over, interfere with access to, increase or reduce the cover over, or change the surface of land in a
way causing ponding of water over an access chamber for Seqwater’s infrastructure
The constructor as a minimum must:
. Contact Seqwater for further detailed information on Seqwater’s infrastructure by phone 1800 771 497 (24 hours),
07 3035 5500 (8am to 5pm Monday to Friday) or by email [email protected] requested to by an Seqwater Officer, complete and submit the attached ‘Application Form for Proposed Work/Activities
Affecting Seqwater Infrastructure’
Prior to commencing the proposed works or activities requiring Seqwater written consent, the constructor must:
« Apply for a permit to work and receive Seqwater’'s written consent for proposed works or activities
. Provide all necessary plans and details, including Work Method Statements for construction approval
« — Comply with all requests for notice as issued by Seqwater
e Submit a new Dial Before You Dig enquiry should the scope of works change, or plan validity dates expire
On completion of the works or activities the constructor must:
. Provide all necessary ‘As-Constructed’ plans and details to [email protected]

LOCATING OF SERVICES

When locating Seqwater’s underground infrastructure (including communication conduits, cathodic protection, etc) non-destructive
potholing techniques (i.e. careful hand excavation, hydro-vacuum or similar approved potholing practices) must be used (subject to
the approval of Seqwater).

DAMAGE TO SEQWATER INFRASTRUCTURE

All damage to Seqwater’s infrastructure must be reported immediately on FREECALL 1800 771 497. Seqwater reserves all of its
rights with respect to any loss or damage to its infrastructure.

DISCLAIMERS
Seqwater

Seqwater makes no representation or warranty as to the accuracy, completeness, reliability or suitability of the, maps, GIS data and
any other information provided by Seqwater for any specific purpose and disclaims any responsibility or liability for any expenses,
losses, damages and costs which may be suffered or incurred as a result of or in connection with using or relying on the data or the
Information provided by Seqwater. The user acknowledges that use of the Information is subject to the user's own investigations
and due diligence to verify the accuracy, completeness, reliability and suitability for the relevant purpose. Please ensure the map
attached accurately represents the location of proposed works. If you have any queries, please contact Seqwater.

The information provided by Seqwater in this response is only valid for 28 days.

OpenStreetMap

Based on or contains map data provided by (c) OpenStreetMap contributors. Please visit http://www.openstreetmap.org/copyright
to view the disclaimer.

Department of Natural Resources and Mines Data

Based on or contains data provided by the State of Queensland (Department of Natural Resources and Mines). Please visit
www.dnrm.qid.gov.au to view the Department's disclaimer.

CONTACT DETAILS

For further details or queries please contact Seqwater:

In writing: Seqwater, PO Box 16146, City East QLD 4002

By Phone: 1800 771 497 or 07 3035 5500 By Fax: 07 3299 7926
Email: [email protected]
Log in to download the original file

Appendix C - Amended Engineering Plans.pdf · 14.6 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.