               39.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging, are removed from the building prior to demolition or relocation.
               40.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.
               41.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.
               42.    All building materials containing asbestos products are wrapped and disposed of in
                      accordance with the Public Health Regulation 2006 and the Environmental Protection
                      Regulation 2008.
                      Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
                      businesses that transport asbestos waste, and landfills that accept this waste.
                      General
               43.    Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
                      protected from damage and made safe to the standard required by the regulatory authority.
               44.    Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
                      bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
                      pre-existing conditions.
                      Plumbing and Drainage
               45.    It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                      demolition of a building, the existing sanitary drain upstream from the connection point for a
                      service provider’s sewerage system must be sealed water tight. This work is deemed as
                      notifiable Work and must be carried out by a suitably licenced plumber who must submit an
                      As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
                      Construction Commission) within 10 days of completing the work.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
               Infrastructure Charges
               1.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further information, please refer to Infrastructure Charges | Noosa Shire Council
               7.     PROPERTY NOTES

               Not applicable.
               8.     VARIATION APPROVAL DETAILS

               Not applicable.




                                                                                                       Page 7 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Used in these records

About this file

File size
170 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 51989 294 03 (As Published).pdf · 170 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.