Please refer to the electronic MUSIC model attached.
2.2 MUSIC Model Results
The results of the MUSIC model are shown in Table 2.2 below.
Table 2.2 Treatment Train Effectiveness
Flow TSS TP TN Gross
ML/y Kg/y Kg/y Kg/y Pollutant
Kg/y
Source Load 8652 3210 5.399 20.19 179.6
Residual Load 8526 600.1 1.874 10.96 0
% Reduction 1.45 81.31 65.28 45.71 100
%Target Reduction - 80 65 45 90
Inspection of Table 2.2 shows that the target pollutant load reductions will be
achieved for the developed site.
2.3 Maintenance
A recommended maintenance schedule for elements of the water quality and
attenuation treatment train appears at Appendix E.
________________________________________________________________________
A6880/24/ENG/Noosaville 7
June SH/pl
ALTA PROJECTS PTY LTD
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.