PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the Ordinary Meeting dated 19 March 2026 - Item 12.2) · 2026-06-09 ATTACHMENT 1 to Minutes of General Committee 9.06.2026 - Peregian Beach Active Street - Further Information
2. Base Case Opportunities
a. Existing infrastructure: The project provides the opportunity to address inadequacy and
requirement for emergent works to repair storm water assets prior to/during project
implementation. Further project timeline delays and cost impacts.
b. Leverage funding structure: As the ATF grant is for construction only funding, matching
the SEQ Liveability contribution. The potential exists to expand the scope of works using
council reserves, matched by the ATF grant, to address emergent and repair works.
3. Scenario Analysis
The following table further details alternative scenarios and the differentiated risks anticipated.
Scenario Description Likely Outcome
Base case - construction Current Scope, Programme, Re-instates programme float as stormwater
commencement mid- Budget/funding - no mitigation renewal opportunities have been factored into
October (working new programme but not recommended to
assumption: approvals of proceed, project budget contingency mostly
EOT from both funding consumed.
bodies)
Reputational damage associated with project
continuation in spite of immediate resident
resistance, particularly without implementing
recommended design changes influenced by
community engagement activities.
Adjust as per Implement mitigations, actively Re-instates project float, enable more time to
recommendations enhance opportunities close out community interactions, minimise
Council exposure to project costs, maintain
opportunity to leverage funding structure to
deliver more at lower cost to council, and
reduces reputation damage risk by including
community requests and/or suggestions into
the project where possible.
Further recommendations Additional Community Project will need to be fully funded by Council.
outside of those drafted by Consultation and or significant
Alternative design treatments will likely be more
staff change to planning and design
expensive than the currently proposed project.
approach
Delays to delivery of walking and cycling
infrastructure.
Do not proceed Stop working on design and Council will need to fund works to date at an
cancel planned construction approximate value of $210k.
works.
May damage relationships with funding bodies
and potentially limit further funding
opportunities.
Reputational damage for not following through
with Walking and Cycling Strategy objectives
and negative impact on future projects
proposals across the shire.
Loss of funding for "practical" components of
the projects such as construction of shared
pathway and rectification of stormwater
infrastructure.
Delays to delivery of walking and cycling
infrastructure.
Following is an update to Attachment 8 (that was provided in the original report):