Appendix D Stormwater Management Plan · MCU22/0038

of 37

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn

Original PDF page 13, section 1. The text section number identifies this passage in the reader.

 15 March 2022




5.3.3.5 Water Quality Objectives
The Water Quality Objectives of the receiving waters for the proposed development have been
obtained from State Planning Policy July 2017. The State Planning Policy load reduction targets are
summarised in Table 3 below.


                                             WATER QUALITY OBJECTIVES


 Total Suspended              Total Nitrogen                  Total                     Litter/Gross
  Solids (TSS) %                 (TN) %                   Phosphorous                   Pollutants %    Oils/Grease
    Reduction                   Reduction               (TP) % Reduction                 Reduction

                                                                                                       No visible films
           80                         45                          60                        90
                                                                                                         or odours

                                            Table 3 – Water Quality Objectives
5.3.3.6 Treatment Plan
In order to achieve the Water Quality Objectives for the proposed development, it is proposed to
use natural treatment methods to treat the runoff prior to discharge from the site.

Stormwater runoff from the roof will be captured in a series of new gutters, downpipes and pits,
which will discharge along with the remaining on ground catchments to bioretention basins, where
Q1 flows will receive treatment while additional flows with discharge into the external stormwater
network.

The bioretention basins are located in the south west and along the western boundary of the site.

Runoff from the existing landscape areas at the northern boundary of the site will remain generally
as per pre-development conditions and will be treated by the existing grassed swale.

Treated water from the bio basins will connect into the basement drainage system for pump out to
the existing drainage network. This is required due to the high invert levels of the surrounding
drainage network. The treatment plan for the proposed development is depicted on MPN Plan
8662-CP.1.01 attached in Appendix 3, with MUSIC excerpt below.




 Excellence with Economy in Engineering                                                                                   12
 l:\8000-8999\8600-8699\8662\reports\15-03-22 stormwater management plan_issue a.docx

Used in these records

About this file

File size
4.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix D Stormwater Management Plan.pdf · 4.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.