C101 - Project Notes - Sheet 1 - Rev 2

of 1
      GENERAL NOTES                                                                                                    EARTHWORKS NOTES                                                                                ROADWORKS NOTES                                                                               PAVEMENT SPECIFICATIONS
      1.    ALL SITE EXISTING TOPSOIL TO BE STRIPPED WITHIN DEVELOPMENT FOOTPRINT AND STOCKPILED                       1.     SOILS REPORT                                                                             1.    LEVELS AND GRADIENTS AT JUNCTIONS WITH EXISTING WORKS MAY BE VARIED AS REQUIRED TO      1.   FIRE ACCESS TRACK FLEXIBLE PAVEMENT -
            ON SITE FOR REUSE. LOCATION FOR STOCKPILE TO BE AS ADVISED BY SUPERINTENDENT.                                     ALL EARTHWORKS AND SITE PREPARATION TO BE CARRIED OUT IN ACCORDANCE WITH THE                   ACHIEVE SATISFACTORY CONNECTIONS AND THE COSTS DEEMED INCLUDED IN THE RELEVANT                 REFER DRAWINGS IF25-STC006-001 TO IF25-STC006-002
            SHOULD EXISTING TOPSOIL NOT BE SUITABLE FOR REUSED. CONTRACTOR TO ALLOW TO DISPOSE                                RECOMMENDATIONS IN THE GEOTECHNICAL REPORT 226707 DATED ON 06/03/2024 PREPARED BY              SCHEDULE ITEMS.
            OF OFFSITE WITHIN THEIR TENDER SUBMISSION.                                                                        DOUGLAS PARTNERS. A COPY OF THIS CAN BE OBTAINED FROM THE SUPERINTENDENT.                2.    THE LOCATION OF EXISTING SERVICES AS SHOWN ON THE PLAN IS INDICATIVE ONLY AND THE       2.   CONCRETE PAVEMENT -
      2.    ALL UNSUITABLE OR UNCONTROLLED FILL THAT IS DEEMED NOT SUITABLE FOR REUSE WITHIN                           2.     SITE PREPARATION                                                                               CONTRACTOR MUST ASCERTAIN THE POSITION OF ALL SERVICES (I.E. WATER, ELECTRICITY,              150mm THICK N32 CONCRETE
            THE PROJECT GEOTECHNICAL REPORT IS TO BE DISPOSED OF OFF SITE.CONTRACTOR TO                                       EXCAVATE AND REMOVE ALL VEGETATION, ORGANIC TOPSOIL, UNCONTROLLED FILL AND OTHER               TELECOM, GAS ETC.), BEFORE COMMENCING CONSTRUCTION.
                                                                                                                                                                                                                                                                                                                           SL82 MESH 50mm TOP COVER
            INCLUDE DUE ALLOWANCE FIR DISPOSAL OFF SITE WITHIN THEIR TENDER SUBMISSION.                                       DELETERIOUS MATERIAL FROM SITE. EXCAVATE AND TRIM THE BUILDING OR PAVEMENT               3.    ALL EXISTING SERVICES AND STRUCTURES ARE TO BE MAINTAINED IN GOOD ORDER FOR THE
                                                                                                                                                                                                                             DURATION OF THE CONTRACT AND WHERE RELOCATION IS REQUIRED REFER SPECIFICATION.                150mm THICK TMR TYPE 2.4 SUB-BASE COURSE
      3.    CONTRACTORS AND SUB-CONTRACTORS TENDERING ON THIS PROJECT ARE TO MAKE                                             PLATFORMS AS REQUIRED.
            THEMSELVES FULLY AWARE OF ALL REQUIREMENTS. IF IN DOUBT OR FURTHER CLARIFICATION IS                               SITE PREPARATION TO BE IN ACCORDANCE WITH THE RECOMMENDATIONS OF THE                     4.    SUBSOIL DRAINS TO BE PROVIDED UNDER ALL KERB AND CHANNEL AND KERB.
            REQUIRED, THE CONTRACTOR IS TO OBTAIN CLARIFICATION FROM THE ENGINEERS PRIOR TO                                   GEOTECHNICAL REPORT.                                                                     5.    NOT WITHSTANDING THE LIMITS OF EARTHWORKS SHOWN ON THE DRAWINGS, THE ACTUAL LIMITS      3.   CONCRETE PATHWAYS, RAMPS, LANDINGS & DRIVEWAY-
            SUBMITTING TENDER PRICES. SHOULD THE CONTRACTOR FAIL TO OBTAIN CLARIFICATION FROM                                 IF THE GEOTECHNICAL REPORT DOES NOT PROVIDE ADVICE ON SITE PREPARATION THEN PROOF              SHALL BE DETERMINED ON SITE BY THE SUPERINTENDENT.                                            100mm N32 CONCRETE
            THE ENGINEERS IT IS DEEMED THAT THE CONTRACTOR HAS BEEN PROVIDED SUFFICIENT                                       ROLL THE EXPOSED SUBGRADE USING SIX PASSES OF A 10 TONNE MINIMUM STATIC WEIGHT           6.    ROADS AND STRUCTURAL FORMATIONS INCLUDING EMBANKMENTS, FOOTPATHS, PAVED AREAS                 SL72 MESH CENTRAL
            INFORMATION TO ADEQUATELY PRICE THE ENTIRE WORKS AND THAT THE CONTRACTOR HAS                                      VIBRATORY PAD TYPE ROLLER TO IDENTIFY ANY SOFT SPOTS. THESE ZONES MUST BE INSPECTED            AND SHOULDERS ARE TO BE COMPACTED TO 100% STANDARD DRY DENSITY LESS THAN 0.3m                 50mm APPROVED COMPACTED SAND BEDDING
            ALLOWED FOR ALL WORKS REQUIRED. IN PROVIDING CLARIFICATION, THE ENGINEER HAS NOT                                  BY AN APPROVED GEOTECHNICAL ENGINEER TO ASSESS THEIR EXTENT.                                   BELOW SUBGRADE AND 98% STANDARD DRY DENSITY MORE THAN 0.3m BELOW SUBGRADE TO
            ASSUMED A DUTY OF CARE TO THE CONTRACTOR OR SUBCONTRACTOR, BUT IS ONLY ACTING AS                                  SOFT SPOTS SHALL BE EXCAVATED AND REPLACED WITH SELECT BACKFILL COMPACTED IN                   AS1289 5.1.1. AND LOCAL GOVERNMENT AUTHORITY SPECIFICATIONS.                            4.   CARPARK FLEXIBLE PAVEMENT -
            THE OWNER’S AGENT.                                                                                                LAYERS NOT EXCEEDING 150mm COMPACTED THICKNESS TO COMPACTION LISTED UNDER "FILL          7.    ELECTRICAL AND COMMUNICATIONS CONDUIT LOCATIONS ARE SHOWN FOR INFORMATION ONLY.               35mm ASPHALT SEAL WITH AMCO PRIMER SEAL
      4.    PRIOR TO COMMENCEMENT OF WORKS THE CONTRACTOR IS TO IDENTIFY AND BE SATISFIED OF                                  MATERIAL".                                                                                     FOR EXACT LOCATIONS REFER TO ELECTRICAL CONSULTANTS LAYOUT PLANS. FOR WATER                   150mm THICK TMR TYPE 2.1 BASE COURSE
            THE CORRECT LOCATION OF ALL EXISTING SERVICES WHETHER INDICATED OR NOT ON THE                                     THE CONTRACTOR IS RESPONSIBLE FOR THE DESIGN AND CERTIFICATION OF A SUITABLE                   CONDUIT LOCATIONS REFER WATER RETICULATION DRAWINGS.
                                                                                                                                                                                                                                                                                                                           150mm THICK TMR TYPE 2.4 SUB-BASE COURSE
            PLANS. ANY DAMAGE TO EXISTING SERVICES IS TO BE RECTIFIED AT THE CONTRACTOR'S                                     WORKING PLATFORM FOR THE SITE, INCLUDING BUT NOT LIMITED TO CRANES AND MACHINERY.        8.    MINIMUM COVER TO ROOFWATER PIPES TO BE 450MM EXCEPT WHERE LESS COVER IS
            EXPENSE.                                                                                                          THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING SAFE BATTERS AND EXCAVATIONS.                      NECESSARY TO DISCHARGE TO STREET KERB AND CHANNEL.
                                                                                                                                                                                                                       9.    CONTRACTOR TO APPLY FOR AND RECEIVE APPROVAL FROM THE LOCAL GOVERNMENT                  ALL PAVEMENT DESIGNS HAVE BEEN BASED OF CBR RECOMMENDATIONS
      5.    CONTRACTOR TO PROVIDE DILAPIDATION REPORT OF EXISTING SERVICES AND STRUCTURES                                     BUILDING PAD, SUBGRADE AND PREPARATION TO EXTEND 1m PAST STRUCTURAL SLAB EXTENTS.
            PRIOR TO CONSTRUCTION.                                                                                     3.     FILL MATERIAL                                                                                  AUTHORITY FOR THE PROPOSED FOOTPATH AND CROSSOVER WORKS PRIOR TO CONSTRUCTION.          FROM THE PROJECT GEOTECHNICAL REPORT 226707.00 PREPARED BY
      6.    CONTRACTOR TO ALLOW FOR ALL SERVICE STRUCTURES (FOR EXAMPLE, POWER POLES,                                         BUILDING PAD FILL SHALL BE COMPACTED IN MAXIMUM 150mm THICK LAYERS (COMPACTED            10.   CONTRACTOR TO ARRANGE INSPECTION OF PROPOSED CROSSOVERS AND FOOTPATHS WITH              DOUGLAS PARTNERS DATED 06.03.24
            COMMUNICATIONS PITS OR VALVE BOXES) TO BE MODIFIED TO SUIT THE FINISHED SURFACE                                   THICKNESS) TO 98% STANDARD DRY DENSITY RATIO.                                                  COUNCIL IN ACCORDANCE WITH DEVELOPMENT APPROVAL AND OPERATIONAL WORKS APPROVAL.
            LEVEL IN ACCORDANCE WITH THE SERVICE PROVIDES SPECIFICATIONS.                                                     FILL UNDER ROADS TO BE IN ACCORDANCE WITH ROADWORKS NOTES.                               11.   CONTRACTORS AND SUB-CONTRACTORS TO CONFIRM CROSSOVER AND ADJACENT PAVEMENT
      7.    PRIOR TO COMMENCEMENT OF WORKS THE CONTRACTOR WILL PROVIDE SCOUR AND EROSION                                      ALL BUILDING PADS AND STRUCTURE FILLING SHALL BE UNDER LEVEL 1 GEOTECHNICAL                    LEVELS AND GRADES PRIOR TO THE START OF CONSTRUCTION. IF IN DOUBT OR FURTHER
            PROTECTION INCLUDING PROVISION OF SEDIMENT TRAPS AND FENCES TO MINIMISE DEPOSITION                                SUPERVISOR BY RPEQ GEOTECHNICAL ENGINEER AND SHALL BE IN BULK EARTHWORKS TENDER
                                                                                                                              ALLOWANCE.
                                                                                                                                                                                                                             CLARIFICATION IS REQUIRED, THE CONTRACTOR IS TO OBTAIN CLARIFICATION FROM THE
                                                                                                                                                                                                                             ENGINEERS PRIOR TO CONSTRUCTION.
                                                                                                                                                                                                                                                                                                                     PROVISION FOR TRAFFIC & EXTERNAL WORKS
            OF MATERIAL ONTO DOWNSTREAM OF THE PROPERTY AS INDICATED ON THE DRAWINGS.
      8.    THIS DRAWING SHALL BE READ IN CONJUNCTION WITH ALL OTHER WORKING DRAWINGS AND                                     THE FREQUENCY OF TESTING FILL COMPACTION SHALL BE AS SPECIFIED IN SECTION 8 OF AS 3798   12.   CONTRACTOR TO PROVIDE CBR TEST RESULTS A MINIMUM OF TWO WEEKS PRIOR TO ROAD             1.   THE CONTRACTOR HEREBY COVENANTS THAT IT WILL AT ALL TIMES INDEMNIFY AND KEEP
            SPECIFICATIONS AND WITH SUCH OTHER WRITTEN INSTRUCTIONS AS MAY BE ISSUED DURING THE                               "GUIDELINES ON EARTHWORKS FOR COMMERCIAL AND RESIDENTIAL DEVELOPMENTS" FOR THE                 CONSTRUCTION TO CONFIRM ROAD SUBGRADE DESIGN. TESTS TO BE TAKEN AT A MINIMUM OF              INDEMNIFIED, THE PRINCIPAL FROM AND AGAINST ALL ACTIONS CLAIMS, DEMANDS, LOSSES,
            COURSE OF CONSTRUCTION. ALL DISCREPANCIES AND VARIATIONS SHALL BE REFERRED TO THE                                 LEVEL SPECIFIED IN NOTE 5 BELOW.                                                               50m CENTERS OR TO LOCAL AUTHORITY STANDARDS. TESTS TO BE TAKEN AT SUBGRADE BOX               DAMAGES, COSTS, CHARGES AND EXPENSES, OR OTHER LIABILITIES WHATSOEVER, IN RESPECT
            ENGINEER BEFORE PROCEEDING WITH THE WORK.                                                                         FILL SHALL BE COMPACTED AND MAINTAINED AT MOISTURE CONTENTS AT PLACEMENT WITHIN                DEPTH.                                                                                       OF, OR ARISING FROM, ANY DAMAGES TO THE ROAD FRONTING THE SITE DURING THE
      9.    CONTRACTOR TO OBTAIN ALL APPROVALS AND PERMITS FOR WORKING WITHIN LOCAL                                           THE RANGE PLUS 2% TO MINUS 2% OF STANDARD OPTIMUM MOISTURE CONTENT U.N.O.                13.   PROVIDE KERB RAMP AT ALL PEDESTRIAN CROSSINGS AND WALKWAYS TO LOCAL GOVERNMENT               CONSTRUCTION OF THE WORKS.
            GOVERNMENT AUTHORITY ROADS AND STATE GOVERNMENT ROADS.                                                            FILL MATERIAL SHALL BE OF UNIFORM QUALITY AND FREE FROM VEGETABLE MATTER.                      AUTHORITY STANDARDS.                                                                    2.   THE CONTRACTOR SHALL:
      10.   CONTRACTOR TO ENSURE THAT ALL THE REQUIRED CONDITIONS OF THE DEVELOPMENT                                          IMPORTED STRUCTURAL FILL TO BUILDING PADS OF STRUCTURES TO CONFORM TO THE                14.   ALL ROAD WORKS KERB TRANSITIONING BETWEEN KERB TYPES TO BE CARRIED OUT OVER 1.5m                a. OBTAIN PERMISSION FROM LOCAL COUNCIL AND THE QUEENSLAND DEPARTMENT OF MAIN
            APPROVAL HAVE BEEN SATISFIED PRIOR TO STARTING ON SITE.                                                           FOLLOWING:-                                                                                    MINIMUM.                                                                                            ROADS FOR ACCESS TRACKS BEFORE OR DOING ANY WORK EXTERNAL TO THE SITE.
      11.   ALL WORK TO CONFORM TO NOOSA SHIRE COUNCIL STANDARDS AND SPECIFICATIONS UNLESS                                    CBR                           15% MIN.                                                                                                                                                         b. INDEMNIFY LOCAL COUNCIL, THE PRINCIPAL, STP CONSULTANTS, AND THE QUEENSLAND
            OTHER WISE SHOWN ON PLANS OR DIRECTED BY THE SUPERINTENDENT.                                                      LINEAR SHRINKAGE              8% MAX.                                                                                                                                                              DEPARTMENT OF MAIN ROADS AGAINST CLAIMS RESULTING FROM THE CONTRACTOR'S
      12.   CONTRACTOR TO ENSURE THAT ALL WORK, SERVICES AND PRODUCTS TO BE FIT FOR PURPOSE.                                  LIQUID LIMIT                  35% MAX.                                                   AS CONSTRUCTED                                                                                            OPERATIONS OF PLANT EXTERNAL TO THE SITE.
      13.   ALL 'WORKS AS CONSTRUCTED' INFORMATION SHALL BE SUPPLIED IN BOTH HARD COPY AND                                    PLASTICITY INDEX              15% MAX.                                                   1.    THE CONTRACTOR SHALL ARRANGE FOR AN INDEPENDENT LICENSED SURVEYOR TO CARRY OUT                  c. COMPLY WITH THE DIRECTIONS AND REQUIREMENTS OF LOCAL COUNCIL AND THE
            ELECTRONIC DATA FORMAT TO THE REQUIRED AUTHORITIES.                                                               SHRINK/ SWELL INDEX           1.0% MAX.                                                        'WORKS AS CONSTRUCTED' SURVEY AND SUBMIT DETAILS SHOWN ON A PLAN TO THE                             DEPARTMENT OF MAIN ROADS 'MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES' WITH
      14.   ALL SETOUT TO ARCHITECTS DETAILS UNLESS NOTED OTHERWISE (U.N.O.).                                                 BEARING CAPACITY              TO STRUCTURAL ENGINEERING DESIGN REQUIREMENTS NOT                SUPERINTENDENT AT COMPLETION OF CONSTRUCTION.                                                       RELATION TO WARNING SIGNS AND TRAFFIC CONTROL.
      15.   DIMENSIONS SHALL NOT BE OBTAINED BY SCALING THE DRAWINGS.                                                                                       LESS THAN 100KPa ALLOWABLE. FILL SHALL ALLOW REACTIVITY
                                                                                                                                                                                                                       2.    'WORKS AS CONSTRUCTED' SURVEY IS TO SHOW BUT NOT BE LIMITED TO:                                 d. REPAIR, MAINTAIN AND MAKE GOOD TO THE SUPERINTENDENT'S SATISFACTION, ANY
      16.   STP CONSULTANTS PTY LTD MAY PROVIDE, BY AGREEMENT WITH CERTAIN PARTIES, MATERIALS                                                               TO BE RECLASSIFIED AS 'CLASS S' TO AS2870-2011.
            STORED ELECTRONICALLY. THE PARTIES RECOGNIZE THAT DATA, PLANS, SPECIFICATIONS,                                    AS SIEVE                      % PASSING                                                          · LEVEL AND LOCATION OF RETAINING WALLS, FEATURES, EARTHWORKS AND FINISHED                        DAMAGE.
            REPORTS, DOCUMENTS, OR OTHER INFORMATION RECORDED ON OR TRANSMITTED AS                                            75mm                          100%                                                                 SURFACE LEVELS                                                                      3.   THE CONTRACTOR SHALL SUBMIT ANY TRAFFIC DIVERSION SCHEMES TO THE LOCAL COUNCIL
            ELECTRONIC MEDIA (INCLUDING BUT NOT NECESSARILY LIMITED TO "CAD AND 12D DOCUMENTS")                               4.75mm                        30 - 100%                                                          · LEVEL AND LOCATION OF NEW KERB, KERB AND CHANNEL, CONCRETE INVERT AND KERB               FOR APPROVAL, PRIOR TO IMPLEMENTATION OF SUCH A SCHEME AND PROVIDE A FULL COPY OF
            ARE SUBJECT TO UNDETECTABLE ALTERATION, EITHER INTENTIONAL OR UNINTENTIONAL, DUE TO,                              0.0075mm                      3 - 30%                                                              RAMP                                                                                     SUCH SCHEME TO THE SUPERINTENDENT
            AMONG OTHER CAUSES, TRANSMISSION, CONVERSION, MEDIA DEGRADATION, SOFTWARE ERROR,                           4.     SUB-GRADE REPLACEMENT (SUB-BASE 2)                                                               · LEVEL AND LOCATION OF ALL DRAINAGE STRUCTURES, PIPES SIZES AND INVERT LEVELS FOR    4.   ALL TRAFFIC DIVERSION SCHEMES SHALL CONFORM TO THE REQUIREMENTS OF THE
            OR HUMAN ALTERATION. ACCORDINGLY, ALL SUCH DOCUMENTS ARE PROVIDED TO THE PARTIES                                  SUB-BASE 2 MATERIAL SHALL BE ROADBASE MATERIAL OF:-                                                STORMWATER DRAINAGE, SEWERAGE RETICULATION AND WATER RETICULATION                        DEPARTMENT OF MAIN ROADS PUBLICATION 'MANUAL IF UNIFORM TRAFFIC CONTROL DEVICES'.
            FOR INFORMATIONAL PURPOSES ONLY AND NOT AS AN END PRODUCT OR AS A RECORD                                          MINIMUM CBR:                            15%                                                                                                                                            5.   IT IS TO BE CLEARLY UNDERSTOOD THAT THE CONTRACTOR SHALL NOT COMMENCE WORK ON
                                                                                                                                                                                                                               · ANY DETAILS RELATED TO FINAL ROAD TRUNCATION, ROAD WORKS AND SERVICES                    THE SITE UNTIL THE APPROPRIATE PERMITS HAVE BEEN OBTAINED FROM LOCAL COUNCIL.
            DOCUMENT. ANY RELIANCE THEREON IS DEEMED TO BE UNREASONABLE AND UNENFORCEABLE.                                    SUB-BASE 2 MINIMUM THICKNESS:           150mm                                                    · ANY DETAILS REQUIRED BY THE DEVELOPMENT APPROVAL
            THE SIGNED AND/OR STAMPED HARD COPIES OF THE ENGINEERING DRAWINGS ARE THE ONLY                                    MAXIMUM PARTICLE SIZE:                  40mm                                                                                                                                                COPIES OF THE PERMITS SHALL BE FORWARDED TO THE SUPERINTENDENT AND AN ADDITIONAL
                                                                                                                              MAXIMUM LIQUID LIMIT:                   35%                                              3.    AS CONSTRUCTED SURVEY IS TO BE PROVIDED IN .DWG, .PDF AND ADAC FORMATS.                      COPY SHALL BE MAINTAINED ON-SITE.
            TRUE CONTRACT DOCUMENTS OF RECORD.
      17.   IN CASE OF DOUBT, ASK!                                                                                            MAXIMUM PLASTICITY INDEX:               12%                                                                                                                                                    PERMITS SHALL BE OBTAINED FROM THE COUNCIL PRIOR TO:
                                                                                                                                                                                                                                                                                                                             a. CROSSING THE KERB WITH HEAVY VEHICLES.
                                                                                                                              UNLESS OTHERWISE APPROVED BY GEOTECHNICAL ENGINEER.
                                                                                                                              PLACE CBR 15 MATERIAL TO FINAL COMPACTED THICKNESS OF 150mm COMPACTED TO 98%
                                                                                                                                                                                                                       PAVEMENT MARKING AND SIGNAGE NOTES                                                                    b. WORKING IN THE ROAD RESERVE.
      EROSION AND SEDIMENT CONTROL NOTES:                                                                                     STANDARD MAXIMUM DRY DENSITY IN ACCORDANCE WITH AS 1289.                                 1.    PRIOR TO COMMENCEMENT OF WORKS THE CONTRACTOR IS TO IDENTIFY AND BE SATISFIED OF                c. CONNECTION TO A COUNCIL ROAD.
      1.    THE CONTRACTOR SHALL PREPARE AN EROSION AND SEDIMENT CONTROL PLAN AND SUBMIT TO                            5.     EXTERNAL FOOTPATHS & SLABS                                                                     THE CORRECT LOCATION OF ALL EXISTING SERVICES WHETHER INDICATED OR NOT ON THE                   d. STORING OF MATERIAL ON THE FOOTPATH OR ROAD.
                                                                                                                              PROVIDE WATERPROOF DAMP COURSE 0.2µ VAPOUR BARRIER ON 50MM SAND BED & 150MM                    PLANS. ANY DAMAGE TO EXISTING SERVICES IS TO BE RECTIFIED AT THE CONTRACTOR'S                   e. THE PROVISION OF HOARDING AND GANTRIES
            THE SUPERINTENDENT PRIOR TO UNDERTAKING ANY WORKS ON SITE.
                                                                                                                              SUB-BASE 2 IF SUBJECT TO LIGHT VEHICLE TRAFFIC.                                                EXPENSE.
      2.    DEVICES TO BE PLACED BY A BUILDER TO SUIT STAGE OF WORKS & COMPLIANCE WITH THE BEST                                                                                                                                                                                                                      6.   IF DAMAGE IS CAUSED TO EXISTING ROADWAYS OR FOOTPATHS BY THE CONTRACTOR, THE
                                                                                                                       6.     CUT MATERIAL                                                                             2.    ALL PAVEMENT MARKING, SIGNAGE AND RETROREFLECTIVE RAISED PAVEMENT MARKERS (RRPM)
            PRACTICE GUIDELINES AND IECA STANDARDS.                                                                                                                                                                                                                                                                       DAMAGED SECTIONS SHALL BE REPAIRED OR REPLACED AT THE CONTRACTORS COST TO THE
                                                                                                                              ALL CUT AREAS ARE TO BE COMPACTED TO 100% COMPACTION. ALL EXCESS CUT                           TO BE IN ACCORDANCE WITH THE TMR AND AS 1742 MANUAL FOR UNIFORM TRAFFIC CONTOUR
      3.    CONSTRUCTION OF ALL SEDIMENT MANAGEMENT DEVICES SHALL BE COMPLETED AND EFFECTIVE                                                                                                                                                                                                                              ENTIRE SATISFACTION OF THE SUPERINTENDENT. IN THE EVENT THAT THE CONTRACTOR FAILS TO
                                                                                                                              MATERIAL,TOPSOIL, DEBRIS AND WASTE TO BE REMOVED FROM SITE.                                    DEVICES.
            PRIOR TO :                                                                                                                                                                                                                                                                                                    MAKE ANY NECESSARY REPAIRS, OR THE COUNCIL MOVES TO RECOVER THE COST OF ANY
                                                                                                                       7.     CUT AND FILL                                                                             3.    GUIDE POSTS TO BE IN ACCORDANCE WITH THE TMR AND AS 1742 MANUAL FOR UNIFORM TRAFFIC
                                                                                                                                                                                                                                                                                                                          REPAIRS FORM THE PRINCIPAL, THE PRINCIPAL SHALL BE EMPOWERED, ON THE CERTIFICATION
            - STRIPPING OF TOPSOIL AND GRASS                                                                                  IS THE RESPONSIBILITY OF THE EARTHWORKS CONTRACTOR WHO IS TO PROVIDE COMPACTION                CONTROL DEVICES.
                                                                                                                                                                                                                                                                                                                          OF THE SUPERINTENDENT AS OFTEN AS THE SAME SHALL HAPPEN, TO DEDUCT FROM MONIES, OR
            - BULK EARTHWORKS TO THE SITE                                                                                     CERTIFICATION BY A SUITABLY QUALIFIED AND EXPERIENCED GEOTECHNICAL ENGINEER THAT         4.    FOR SIGNAGE AND ASSEMBLY DETAILS REFER TMR STANDARD DWG.
                                                                                                                                                                                                                                                                                                                          WHICH MAY BECOME DUE, TO THE CONTRACTOR THE AMOUNT PAID IN SUCH CASES TO THE
            - SERVICE INSTALLATION                                                                                            THE WORKS HAVE BEEN COMPLETED TO THE REQUIRED LEVEL.                                     5.    STREET NAME SIGNS SHALL BE TO LOCAL GOVERNMENT STANDARDS.
                                                                                                                                                                                                                                                                                                                          COUNCIL.
      4.    ALL SEDIMENT MANAGEMENT DEVICES ARE TO REMAIN IN PLACE UNTIL COMPLETION OF WORKS.                                 PROVIDE SUB-BASE AS DETAILED IN NOTES ABOVE.                                             6.    FOR ROADWORK DELINEATOR DETAILS REFER TMR STANDARD DWG.
                                                                                                                                                                                                                                                                                                                     7.   ALL OTHER PERMITS REQUIRED TO COMPLETE THE WORKS FROM BUT NOT LIMITED TO THE
                                                                                                                              EARTHWORKS UNDER PROPOSED STRUCTURES TO BE TO THE STRUCTURAL ENGINEERS                   7.    EXISTING PAVEMENT MARKING ARE TO BE REMOVED BY GRINDING.
      5.    BOTH TEMPORARY AND PERMANENT SEDIMENT MANAGEMENT DEVICES SHALL BE MAINTAINED AT                                                                                                                                                                                                                               QUEENSLAND POLICE SERVICE, QUEENSLAND FIRE AND RESCUE AUTHORITY AND QUEENSLAND
                                                                                                                              SPECIFICATIONS. REFER TO STRUCTURAL ENGINEERS DETAILS FOR SAFE BEARING CAPACITY          8.    LONGITUDINAL LINE MARKING SHALL BE DULUX A1 SOLVENT BASED PAVEMENT MARKING OR
            A SUITABLE LEVEL/CONDITION THROUGHOUT CONSTRUCTION. SEDIMENT FENCES ARE TO BE                                                                                                                                                                                                                                 AMBULANCE SERVICE SHOULD BE OBTAINED BY THE CONTRACTOR.
                                                                                                                              REQUIREMENTS.                                                                                  APPROVED EQUIVALENT. TRANSVERSE LINE MARKING SHALL BE THERMOPLASTIC OR APPROVED
            CLEANED WHEN CAPACITY IS REDUCED BY 30%.                                                                                                                                                                                                                                                                 8.   ANY ASSOCIATED FEES WITH OBTAINING THE REQUIRED PERMITS SHALL BE PAID BY THE
                                                                                                                       8.     GEOTECHNICAL INSPECTIONS AND TEST CERTIFICATES                                                 EQUIVALENT.
      6.    IF EROSION AND SEDIMENT CONTROL DEVICES HAVE BEEN FOUND TO BE DEFECTIVE OR FAILED IN                                                                                                                                                                                                                          CONTRACTOR AND INCLUDED IN THE LUMP SUM GENERALLY.
                                                                                                                              THE GEOTECHNICAL ENGINEER SHALL PROVIDE ALL SERVICES AS REQUIRED TO SATISFY LEVEL 1      9.    PEOPLE WITH DISABILITY PARKING SPACE, SYMBOLS, BOLLARDS AND SHARED SPACE TO BE IN
            SERVICE, DUE TO UNFORESEEN CIRCUMSTANCES, CORRECTIVE ACTION IS TO BE UNDERTAKEN                                                                                                                                                                                                                          9.   WHENEVER WORK UNDER THIS CONTRACT ABUTS ON EXISTING ROADS, THE CONNECTION
                                                                                                                              SUPERVISION AS SPECIFIED IN SECTION B OF AS 3798.                                              ACCORDANCE WITH AS2890.
                                                                                                                                                                                                                                                                                                                          THERETO SHALL BE NEAT, SMOOTH AND WORKMANLIKE AND TO THE SUPERINTENDENTS
            IMMEDIATELY.                                                                                                      WHERE THE GEOTECHNICAL ENGINEER IS NOT APPOINTED BY THE PRINCIPAL. THE CONTRACTOR        10.   ALL LINE MARKING SUBJECT TO PEDESTRIAN TRAFFIC SHALL MEET THE MINIMUM PENDULUM OR
                                                                                                                                                                                                                                                                                                                          SATISFACTION.
                                                                                                                              SHALL BE RESPONSIBLE FOR APPOINTING THE GEOTECHNICAL ENGINEER AND ORGANISING THE               RAMP RECOMMENDATIONS IN THE PEDESTRIAN SURFACES NOTES.
      EXISTING SERVICES NOTES:                                                                                                COMPACTION TESTS. THE COST OF THESE SHALL BE ALLOWED FOR BY THE CONTRACTOR.
      1.    THE CONTRACTOR IS MAKE THEMSELVES FULLY AWARE OF ALL EXISTING SERVICES, FOR                                       TEST CERTIFICATES ON THE FILL MATERIAL SHALL BE SUPPLIED TO THE SUPERINTENDENT FOR       PEDESTRIAN SURFACES NOTES                                                                     REQUIRED HOLD POINT INSPECTIONS
                                                                                                                              APPROVAL PRIOR TO THE USE OF THE FILL MATERIAL
            EXAMPLE DIAL BEFORE YOU DIG TO BE CONTACTED FOR THE LOCATION OF EXISTING PUBLIC                                                                                                                            1.    ALL SURFACES SUBJECT TO PEDESTRIAN TRAFFIC SHALL MEET THE MINIMUM PENDULUM OR           CONTRACTOR IS REQUIRED TO COMPLETE ALL HOLD POINT INSPECTIONS. FAILURE TO DO SO WILL
                                                                                                                       9.     SERVICES
            UTILITIES PRIOR TO EXCAVATION.                                                                                    PRIOR TO THE COMMENCEMENT OF WORKS THE CONTRACTOR IS TO IDENTIFY AND BE SATISFIED              RAMP RECOMMENDATIONS CONTAINED IN TABLE 3 OF AUSTRALIAN STANDARD HANDBOOK               RESULT IN NON-ISSUANCE OF FORM 12. REQUIRED HOLD POINT INSPECTIONS LISTED BELOW:
      2.    THE ALIGNMENT & LEVEL OF EXISTING SERVICES SHOWN ON THIS DRAWING HAS BEEN COMPILED                                OF THE CORRECT LOCATIONS OF ALL EXISTING SERVICES WHETHER INDICATED OR NOT ON THE              HB197:1999 - AN INTRODUCTORY GUIDE TO THE SLIP RESISTANCE OF PEDESTRIAN SURFACE         ·    PRE-START MEETING
            FROM SURVEY DATA & COUNCIL RECORDS & IS INDICATIVE ONLY. PRIOR TO COMMENCING                                      PLANS. ANY DAMAGE TO EXISTING SERVICES IS TO BE RECTIFIED AT THE CONTRACTORS                   MATERIALS. COMPLIANCE WITH THE RECOMMENDATIONS SHALL BE VERIFIED BY TESTING TO          ·    SUBGRADE INSPECTION PRIOR TO PLACEMENT OF GEOCELL, COUNCIL TO ATTEND ALSO
            CONSTRUCTION OR ORDERING ANY MATERIALS THE CONTRACTOR IS TO CONFIRM THE                                           EXPENSE.                                                                                       EITHER:- AS/NZS 4586:2004 - SLIP RESISTANCE CLASSIFICATIONS OF NEW PEDESTRIAN SURFACE   ·    PROOF ROLL AFTER COMPLETION OF GRAVEL FILL OF GEOCELL
            ALIGNMENT & LEVEL OF ALL SERVICES AFFECTED BY THE PROPOSED WORKS.                                          10.    EARTHWORKS VOLUMES                                                                             MATERIALS, OR AS/NZS 4663:2004 - SLIP RESISTANCE MEASUREMENT OF EXISTING PEDESTRIAN     ·    STORMWATER PRIOR TO BACKFILL INSPECTION
      3.    WHILE DUE CARE IS TAKEN BY STP CONSULTANTS IN CONFIRMING THE LOCATION OF EXISTING                                 ALL VOLUMES PROVIDED EXCLUDE ANY COMPACTION OR BULKING FACTORS.                                SURFACES AS APPROPRIATE IN BOTH INSTANCES COMPLIANCE SHALL BE DEMONSTRATED BY           ·    RETAINING WALL FOUNDATION REINFORCEMENT INSPECTION (IF APPLICABLE)
            SERVICES IT IS THE CONTRACTORS RESPONSIBILITY TO CONFIRM THESE SERVICE LOCATIONS. IN                              ALL VOLUMES PROVIDED EXCLUDE LANDSCAPE TOPSOIL REQUIREMENTS, DETAILED EXCAVATION,              APPLYING CLAUSE 5.3 - MEANS OF DEMONSTRATING COMPLIANCE OF AS/NZS 4586:2004 - SLIP      ·    PRE-BACKFILL INSPECTION
            SOME INSTANCES SERVICES MAY BE OMITTED FROM THE DRAWINGS.                                                         FOOTING AND TRENCHING REQUIREMENTS.                                                            RESISTANCE CLASSIFICATION OF NEW PEDESTRIAN SURFACE MATERIALS.
                                                                                                                              ALL VOLUMES PROVIDED ARE INDICATIVE AND ARE TO BE CONFIRMED ON SITE BY THE                                                                                                             ·    ON MAINTENANCE PROOF ROLL OF FIRE TRAIL WITH COUNCIL
      4.    A REPRESENTATIVE FOR EACH SERVICE PROVIDER TO BE PRESENT ON SITE WHEN WORKING                                                                                                                              2.    IN GENERAL, THE CLASSIFICATION OF A SURFACING MATERIAL OR FINISH SHALL BE MADE ON A     ·    OFF MAINTENANCE INSPECTION WITH COUNCIL
                                                                                                                              CONTRACTOR.
            WITHIN 3.0m OF EACH SERVICE IF THE SERVICES ARE PUBLIC ASSET SERVICES.                                     11.    EROSION CONTROL                                                                                WORST CASE BASIS AS DETERMINED BY PENDULUM TESTING USING BOTH THE FOUR S AND TRL        ·    PRACTICAL COMPLETION
      5.    SHOULD INVERT LEVELS OR LOCATION OF ANY SERVICE CONNECTION POINTS DIFFER TO THAT                                  REFER TO EROSION AND SEDIMENT CONTROL PLAN AND NOTES FOR DETAILS.                              RUBBER SLIDER. WHERE ADDITIONAL TEST RESULTS ARE AVAILABLE (OIL -WET RAMP, WET/
            INDICATED ON THE DRAWINGS THEN THE SUPERVISING ENGINEER SHALL BE NOTIFIED                                         ALL DISTURBED GROUND IS TO BE GRASS SEEDED AND HYDROMULCHED TO ENSURE THAT ALL                 BAREFOOT RAMP) THESE MAY BE TAKEN INTO CONSIDERATION.
            IMMEDIATELY.                                                                                                      EXPOSED AREAS ARE STABILISED WITHIN ONE MONTH OF BEING DISTURBED. ALL BATTERS            3.    ALL PITS, STRUCTURES AND INLETS WITHIN A PEDESTRIAN TRAFFIC AREA ARE TO HAVE HEEL
      6.    ANY WORK ON EXISTING SERVICES THAT REQUIRE RELOCATION SHALL BE CARRIED OUT BY THE                                 STEEPER THAN 1V:6H ARE TO BE TOPSOILED AND TURFED U.N.O.                                       PROOF, NON-SLIP, BOLT DOWN LIDS.
            RELEVANT AUTHORITY SHALL BE CO-ORDINATED BY THE CONTRACTOR. CONTRACTOR TO OBTAIN
            REQUIRED APPROVALS FROM THE RELEVANT AUTHORITY.
                                                                                                                       DILAPIDATION SURVEY                                                                             EXCAVATION OF TRENCHES, SHORING AND LIABILITY FOR
      SAFETY NOTE                                                                                                      1.    CONTRACTOR SHALL ARRANGE A FULL DILAPIDATION CONDITION REPORT (AT BUILDERS COST_          DAMAGE
                                                                                                                             FOR THE FOLLOWING EXISTING BUILDINGS PRIOR TO UNDERTAKING ANY DEMOLITION AND CIVIL
      STP CONSULTANTS RECOGNIZES THE IMPORTANCE OF OCCUPATIONAL HEALTH AND SAFETY. HOWEVER,                                  EARTHWORKS                                                                                1.    THE CONTRACTOR SHALL SUPPLY AND DISPLAY ON SITE OF WORKS, ALL APPROPRIATE
      STP CONSULTANTS HAS NOT BEEN ENGAGED TO DEVELOP, CHECK, SUPERVISE OR CONTROL WORKERS                                      ALL EXISTING STRUCTURES WITHIN 5m OF PROPOSED WORKS INCLUDING COUNCIL                        NOTIFICATION SIGNS AND SAFETY MARKING APPLICABLE FOR A CONSTRUCTION SITE IN
      OR METHODS OF WORK. STP CONSULTANTS DOES NOT HAVE THE CAPACITY OR AUTHORITY TO                                                                                                                                         ACCORDANCE WITH ALL REQUIRED REGULATORY GUIDELINES AND LEGISLATION.
                                                                                                                                STORMWATER INFRASTRUCTURE
                                                                                                                                                                                                                       2.    IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO ENSURE THAT ALL TRENCH
      CONTROL WORKERS OR METHODS OF WORK. NOTHING IN THESE DESIGNS SHOULD BE INTERPRETED AS                                                                                                                                  EXCAVATION IS CARRIED OUT IN ACCORDANCE WITH THE MINES REGULATION ACTS, THE
      GOING BEYOND THE STRUCTURAL INTEGRITY OF THE SUBJECT MATTER OF THE DESIGNS AND THEY                              2. UPON COMPLETION THE CONTRACTOR SHALL PREPARE A FINAL DILAPIDATION SURVEY IF ANY                    WORKPLACE HEALTH AND SAFETY ACT 2011.
      SHOULD NOT BE USED AS AN INDICATOR OF THE APPROPRIATE METHODS OF WORK ON, IN OR AROUND                              DAMAGE IS CAUSE TO THE EXISTING BUILDINGS THE CONTRACTOR SHALL ARRANGE FOR                   3.    DURING THE EXCAVATION, ET CETERA AND CONSTRUCTION OF THE WORKS OF THE CONTRACT,
      THE SUBJECT MATTER. CONCERNS ABOUT THE CONDUCT OF WORKERS OR METHODS OF WORK SHOULD                                 APPROPRIATE REPAIR AT FULL COST                                                                    THE CONTRACTOR IS TO ADOPT EVERY PRECAUTION AND PROVIDE ALL MATERIALS, LABOUR, ET
      BE RAISED WITH THE APPROPRIATE SAFETY OFFICIAL ON SITE.                                                                                                                                                                CETERA AND CAREFULLY EXECUTE AT HIS OWN COST WHENEVER CONSIDERED NECESSARY BY
                                                                                                                       MAINTENANCE NOTE                                                                                      THE SUPERINTENDENT AND TO HIS ENTIRE SATISFACTION, STRONG SHORING AND IN SANDY OR




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      C:\Users\aaron\DC\ACCDocs\STP Consultants\STP24-0253 Ozcare Noosa\Project Files\STP-Civil\STP24-0253-NOTE.dwg
                                                                                                                                                                                                                             LOOSE SOIL, CLOSE TIMBERING AND OTHER WORK THAT MAYBE REQUIRED TO PREVENT EARTH
                                                                                                                       1.     CONTRACTOR TO ATTEND ON-MAINTENANCE INSPECTION WITH ENGINEER AND LOCAL COUNCIL
      SURVEY                                                                                                                  OFFICERS IF REQUIRED.                                                                    4.
                                                                                                                                                                                                                             OR OTHER MATERIALS AT SIDES OF EXCAVATION FROM BEING SHAKEN, SLIPPING OR FALLING IN.
                                                                                                                                                                                                                             THE CONTRACTOR SHALL ENSURE THAT ALL TRENCHES OVER 1.5m IN DEPTH ARE SHORED IN
      1.    ALL LEVELS ARE TO BE TO A.H.D LEVEL DATUM. REFER TO SURVEY DRAWING No. 200070-005-VER                      2.     SUCH MAINTENANCE SHALL BE CARRIED OUT IN ACCORDANCE WITH THE PROVISIONS OF THE                 ACCORDANCE WITH THE REQUIREMENTS OF THE WORKPLACE HEALTH AND SAFETY ACT 2011.
                                                                                                                              GENERAL CONDITIONS OF CONTRACT WITH RESPECT TO MAKING GOOD DEFECTS AND OTHER                   WHERE APPROVED BY OFFICERS OF THE DIVISION OF OCCUPATIONAL SAFETY, TRENCHES MAY BE
      DISCLAIMER                                                                                                              FAULTS DUE TO FAULTY REPAIR AND/OR WORKMANSHIP AND SHALL INCLUDE CLEANING UP AND
      WHILST EVERY EFFORT HAS BEEN MADE TO ENSURE THAT THE INFORMATION PROVIDED IN THIS DRAWING/DESIGN WAS                                                                                                                   BATTERED BACK, THE ABSOLUTE MAXIMUM SLOPE OF THE BATTER IS TO BE FORTY-FIVE (45)
      ACCURATE AT THE TIME IT WAS COMPILED, AS PART OF THE LOCAL COUNCILS "AS CONSTRUCTED" RECORDS, IT REMAINS THE
                                                                                                                              REPAIR DUE TO STORM DAMAGE.                                                                    DEGREES FROM THE HORIZONTAL FROM A POINT 1.5m MAXIMUM ABOVE THE BOTTOM OF THE
      RESPONSIBILITY OF PROPERTY OWNERS AND THEIR CONTRACTORS, SUB-CONTRACTORS, EMPLOYEES, SERVANTS AND AGENTS         3.     THE DEFECTS LIABILITY PERIOD FOR MINOR DEFECTS SHALL BE 12 MONTHS FROM THE DATE OF             TRENCH. THE ACTUAL MAXIMUM BATTER SLOPE IS TO BE DETERMINED AFTER INSPECTION OF THE
      AS APPROPRIATE IN THE CIRCUMSTANCES TO MAKE ALL REASONABLE EFFORTS TO ASCERTAIN THE PRECISE LOCATION OF                 PRACTICAL COMPLETION OR DATE WORKS ARE ACCEPTED ON MAINTENANCE BY LOCAL COUNCIL,               STABILITY OF THE TRENCH.
      EXISTING INFRASTRUCTURE INCLUDING WATER MAINS, SEWERS AND DRAINS BEFORE UNDERTAKING EXCAVATION OR                       WHICHEVER OCCURS LAST.
      CONSTRUCTION WORK.                                                                                                                                                                                               5.    THE CONTRACTOR SHALL BE WHOLLY RESPONSIBLE SHOULD AN ACCIDENT OCCUR OR DAMAGE
      USERS OF THE INFORMATION SHOULD BE AWARE THAT SINCE THE ORIGINAL RECORDING OF THE DEPTHS IN RELATION TO
                                                                                                                       4.     THE DEFECTS LIABILITY PERIOD FOR MAJOR DEFECTS OR STRUCTURAL FAILURE SHALL BE SEVEN            TO PROPERTY RESULT FROM THE CONTRACTORS WORK AND SHALL RESTORE SAME AT HIS OWN
      GROUND LEVELS, CHANGES MAY HAVE OCCURRED AS A RESULT OF SUBSEQUENT WORK OR ACTIVITIES INVOLVING FILLING OR              YEARS FROM THE DATE OF PRACTICAL COMPLETION OR DATE WORKS ARE ACCEPTED ON                      COST.
      EXCAVATION. CONSEQUENTLY, THE LOCAL GOVERNMENT AUTHORITY AND STP CONSULTANTS TAKES NO RESPONSIBILITY FOR                MAINTENANCE BY LOCAL COUNCIL, WHICHEVER OCCURS LAST.                                     6.    THE CONTRACTOR SHALL ENSURE THAT ALL TRENCHES IN UNSUITABLE MATERIAL ARE SHORED
      ANY APPARENT ERROR OR INACCURACIES THAT ARE SHOWN TO EXIST AS AT THE DATE INFORMATION WAS PROVIDED OR AT A       5.     CONTRACTOR TO ATTEND OFF-MAINTENANCE INSPECTION WITH ENGINEER AND LOCAL COUNCIL
      LATER DATE.                                                                                                                                                                                                            OR SHIELDS ARE USED DURING PIPE LAYING OPERATIONS. AT ALL TIMES WHEN TRENCHES AND
      THE ABOVE ALSO APPLIES TO LOCATION AND DEPTH OF ALL OTHER PUBLIC UTILITIES.
                                                                                                                              OFFICERS AFTER TWELVE MONTH DEFECTS LIABILITY PERIOD.                                          EXCAVATIONS ARE OPEN AND THE CONTRACTOR AND HIS EMPLOYEES ARE NOT IN ATTENDANCE
                                                                                                                                                                                                                             THE TRENCHES SHALL BE BARRICADED. THIS SHALL APPLY PARTICULARLY TO MANHOLES AND
                                  DIAL BEFORE YOU DIG TO BE CONTACTED                                                                                                                                                        CHAMBERS PRIOR TO AND DURING CONSTRUCTION.
                                  FOR THE LOCATION OF EXISTING PUBLIC                                                                                                                                                  7.    TRENCH WIDTHS SHALL CONFORM TO INSTITUTE OF PUBLIC WORKS ENGINEERING AUSTRALIA
                                  UTILITIES PRIOR TO EXCAVATION                                                                                                                                                              QUEENSLAND DIVISION INC. STANDARD DRAWINGS AND BE OF WIDTH TO SUIT NUMBER OF
                                                                                                                                                                                                                             SERVICES.
                                                                                                                                                                                                                       8.    DEPTHS TO PIPE INVERTS SHOWN ON JOB DRAWINGS SHALL BE INCREASED TO ALLOW FOR
                                                                                                                                                                                                                             BEDDING. PIPE BEDDING REQUIREMENTS VARY WITH STRATA AND MUST COMPLY WITH THE
                                                                                                                                                                                                                             REQUIREMENTS OF THE RELEVANT STANDARD PLANS AND SPECIFICATION.


                                                                                                                                                                                                                                Client:                                                                                                                                                Design          AS        Scale                                      Approved:
                                                                                                                     IN ASSOCIATION WITH                                                                                                        WOOLLAM CONSTRUCTIONS                                                                                     CIVIL                                                                                                                         Digitally signed by Leigh Stegeman
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        DN: C=AU,
                                                                                                                                                                                                                                                                                                                                                                                                                                                              Leigh Stegeman [email protected],
 2    REVISED NOTES                                                                    AS       LS      10.04.25                                                                                                                                                                                                                                                                       Drawn           NP                                                                                                    O=STP
                                                                                                                                                                                                                                                                                                                                                                                                                                                                             Consultants Pty Ltd, CN=Leigh Stegeman
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        Date: 2025.04.10 14:18:24+10'00'



                                                                                                                                                                                                                                Project:
 1    FOR CONSTRUCTION ISSUE                                                           AS      MCW      22.01.25                                                                                                                                OZCARE NOOSA                                                                                                                           Date         JUN 2024                                                Job Number.                                                      Drawing No.   Revision
                                                                                                                                                                                                                                                                                                                                                                                                                 THIS DRAWING IS COPYRIGHT © DO NOT
Rev                                   Description                                      By      Appd       Date                                                                                                                                  80 COOYAR STREET, NOOSA HEADS                                                                                                          Checked         MW        SCALE DRAWING ORIGINAL DRAWING IS A1
                                                                                                                                                                                                                                                                                                                                                                                                                                                            STP24-0253                                                            C101        2
                                                                                                                                                                                                                                                                                                                                                                                       Approved                  SIZE. THIS DRAWING IS NOT TO BE USED FOR
                                                                                                                                                                                                                               Drawing Title:                                                                                                                                                          MW        CONSTRUCTION UNLESS THE APPROVED
                                                    AMENDMENTS                                                                                                                                                                                  PROJECT NOTES - SHEET 1                                                                                                                RPEQ No.       30796      SIGNATURE HAS BEEN ADDED.                               FOR CONSTRUCTION

Log in to download the original (C101 - PROJECT NOTES - SHEET 1 - REV 2.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.