34. All carparking shall be kept maintained and line-marked in a condition fit for use, or delineated
in another approved manner, to the reasonable satisfaction of Council.
Power
35. An underground electricity service shall be provided to each lot.
In this regard, an approved ENERGEX Electrical Design Consultant shall work in conjunction
with Council’s Manager - Works Support to prepare detailed designs of the electrical proposal.
The detailed designs shall then be submitted to ENERGEX for approval and a copy of their
approval submitted to Council in conjunction with a “Certificate of Electricity Supply for
Proposed Subdivisions” (prepared by an approved ENERGEX Electrical Design Consultant)
prior to Council endorsing the Plan of Survey.
Any agreement with ENERGEX or an approved ENERGEX Electrical Design Consultant shall
be wholly at the applicant’s expense and shall not entail a financial encumbrance on future
purchasers of the proposed lots.
36. Street lighting and pathway lighting throughout the subdivision shall have a high energy
efficient rating to the reasonable satisfaction of Council and shall generally be provided in
accordance with the principles of Council’s Engineering Design Standards.
Telecommunication
37. The requirements for TELECOMMUNICATION services shall be satisfied in relation to the
provision of new underground telephone services to the proposed lots. In this regard written
confirmation from an approved telecommunication agency shall be submitted to the Council
prior to Council endorsing the Plan of Survey.
Roof Water
38. Roof runoff from any new dwelling/building shall be directed to a rainwater storage system or
tank that is installed to ensure water from the rainwater storage system or tank is used for
external uses (such as watering gardens, irrigation, ornamental ponds, water features,
topping-up swimming pools, outdoor cleaning, etc) and for internal (ground floor) use in
washing machine cold taps and toilet cisterns. All rainwater tanks are to be designed and
installed in accordance with the Queensland Development Code (QDC) current at the time of
building approval, and shall be part of the plumbing application for approval. The location and
capacity of the tanks shall be clearly shown on the plans submitted for Building Works
approval and any overflow shall be directed to the stormwater drainage system.
Stormwater Management
39. A Stormwater Management Plan (SMP) for the construction and operational phase of the
development shall be submitted in conjunction with any application for a Development Permit
for Operational Works that demonstrates that the proposed stormwater treatment train can
meet the water quality objectives for the Noosa Springs development and that the lakes have
the capacity to treat the runoff from this additional development. Experts in the relevant field
shall prepare the SMP.
40. The Applicant shall be responsible to oversee that the Council approved SMP is implemented.
The Applicant shall engage a suitably qualified and experienced environmental engineer with
RPEQ accreditation to recommend corrective actions in the event of any breach of the SMP
that is likely to result in a public health risk, environmental harm and/ or non- compliance with
the objectives of the SMP. The Applicant shall implement all corrective actions recommended
by the environmental engineer/environmental scientist, unless directed otherwise by Council.
8 of 27
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Negotiated Decision Notice - Advice Agency - EPA [As Published]Related documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.