    MAINTENANCE OF CONTROL MEASURES

All erosion, sediment and drainage control measures need to be regularly
checked and maintained in good working order. Best practice includes
anticipation of potential risks and being prepared for abnormal
circumstances and emergencies. These measures include:

•     Stockpile extra sediment fence fabric and posts on-site to facilitate
      emergency repairs.                                                                                                   ✓
•     Reapply crushed rock to the entry/exit pad (rumble pad) when               All measures require regular inspection
      sediment build-up occurs.
•     Repair eroded drainage channels with rock, turf or erosion control
      blankets or matting.
•     Ensure built-up sediment is removed at regular intervals from
      sediment barriers.
•     Check and replace/repair sediment barriers daily if they are ripped,
      damaged or no longer anchored.
                                                                                                                           ✓
                                                                                 Excessive sediment deposits must be removed
                                                                                 from entry/exit point (rumble pad) and

Drainage control                  SEE FACT SHEET 5
                                                                                 additional crushed rock applied


    DIVERSION OF UP-SLOPE WATER

•     Where practicable, divert up-slope water around the disturbed area.
•     Stormwater can be diverted with the use of small turf or geotextile lined catch drains, or with the use of
      diversion banks.
•     Diverted stormwater should be discharged onto stable ground (for example turfed areas) and should not
      be diverted into neighbouring properties unless written permission is obtained from the land owner(s).

                                                     EARLY ROOF WATER CONNECTION

                                               • Temporary or permanent downpipes should be installed as soon as
                                                 practicable after the roof is laid.
                                               • Early connection of roof water to the stormwater system will reduce site
                                                 wetness and the generation of on-site mud. This has been shown to
                                                 reduce downtime following storm events and decrease the average
                                                 building construction time.




                                       ✓
Temporary roof water connection




                                                                                                                            6

Used in these records

About this file

File size
4.4 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

REFERENCED DOCUMENT MCU13_0171.pdf · 4.4 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.