180307_GIA Request_Civil
Attached to the e-mail Generally in Accordance Request OPW12/0095.
2.0 DESRIPTION OF PROPOSAL
In recognition of the most recent change approval issued in relation to the higher order Material Change of Use
approval (Council Ref. 132004.5744.09), we note that the approved operational works are required to be
amended to reflect the changes to approved development layout and built form. Updated plans, specific to Stage
5, have been appropriately prepared and include:-
Plan No. Rev. Plan Name Date
M1717E5 L01 A Construction Staging Plan, prepared by JFP Consulting Engineers 28/02/18
M1717E5 L02 A Existing Services and Site Survey Plan, prepared by JFP Consulting 28/02/18
Engineers
M1717E5 EW01 A Earthworks Layout Plan, prepared by JFP Consulting Engineers 28/02/18
M1717E5 EW02 A Earthworks Details Plan, prepared by JFP Consulting Engineers 28/02/18
M1717E5 R01 A Roadworks Layout Plan, prepared by JFP Consulting Engineers 28/02/18
M1717E5 R02 A Roadworks Details Plan, prepared by JFP Consulting Engineers 28/02/18
M1717E5 R03 A Roadworks Intersection Details Plan, prepared by JFP Consulting 28/02/18
Engineers
M1717E5 R04 A Roadworks Longitudinal and Typical Cross Sections – Swallow Street, 28/02/18
prepared by JFP Consulting Engineers
M1717E5 R05 A Roadworks Cross Sections – Swallow Street, prepared by JFP Consulting 28/02/18
Engineers
M1717E5 R06 A Roadworks Longitudinal and Cross Sections – Blue Gum Street, 28/02/18
prepared by JFP Consulting Engineers
M1717E5 R07 A Roadworks Cross Sections – Blue Gum Street, prepared by JFP 28/02/18
Consulting Engineers
M1717E5 R08 A Roadworks Longitudinal and Cross Sections – Silver Gull Boulevard, 28/02/18
prepared by JFP Consulting Engineers
M1717E5 R09 A Roadworks Details, prepared by JFP Consulting Engineers 28/02/18
M1717E5 D01 A Drainage Catchment Plan, prepared by JFP Consulting Engineers 28/02/18
M1717E5 D02 A Drainage Layout Plan, prepared by JFP Consulting Engineers 28/02/18
M1717E5 D03 A Drainage Longitudinal Sections, prepared by JFP Consulting Engineers 28/02/18
M1717E5 D04 A Drainage Calculation Table, prepared by JFP Consulting Engineers 28/02/18
M1717E5 E01 A Erosion and Sediment Control Layout Plan, prepared by JFP Consulting 28/02/18
Engineers
M1717E5 E02 A Erosion and Sediment Control Details, prepared by JFP Consulting 28/02/18
Engineers
M1717E5 S01 A Sewer Reticulation Layout Plan, prepared by JFP Consulting Engineers 28/02/18
M1717E5 S02 A Sewer Reticulation Details, prepared by JFP Consulting Engineers 28/02/18
M1717E5 S03 A Sewer Longitudinal Section, prepared by JFP Consulting Engineers 28/02/18
In view of the minor nature of the proposed changes, and the ratification of the changes to the most recently
approved changes to the higher order Material Change of Use approval, we request Council’s written
confirmation that the enclosed plans are ‘generally in accordance’ with the approved operational works package.
This will then allow our client to continue with construction of the final stage of approved development.
We can confirm that generally in accordance fee of $542.00 will be payed upon receipt of the payment advice
from Council.
JFP Ref: M1717 Page 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.