the CMHA has submitted an application for incorporation to the Office of Fair Trading which has
been approved.
On January 10 members of the CMHA building sub-committee met with the Director of Community
Services to discuss how they might go about assessing the condition of the building with a view to
developing a project plan to undertake the necessary repairs to open the building asap.
Following this meeting on January 11°" the CHMA building sub-committee undertook an inspection
of the Hall to ascertain the condition of the building for themselves.
After this inspection the building sub-committee has agreed with Council that the repairs proposed
by Independent Building Services are necessary, and that the costs of repairs would be in excess of
the $40,000 which the sub-committee previously believed would be needed to undertake the work.
A further meeting with the Cooroy Memorial Hall Association Executive Committee and the Director
of Community Services and the Libraries and Galleries Manager occurred on January 30.
5. Options for the future use of the Hall
The public consultation undertaken over the past two months has found that while there are a wide
range of opinions about what could be done with the Hall, most people in Cooroy value the Hall as
an important part of their local history, and see it as an important memorial to those killed in WW1.
Members of the community are also prepared to contribute to the refurbishment and ongoing
management of the Hall. As such they want to see Council quickly resolve the status of the Hall and
from there the Hall restored and re-opened as soon as possible. The majority also want to see the
Hall continue to be used for community rather than commercial purposes into the future.
The four potential options for the future use and management of the Hall identified below have been
evaluated against this background.
5.1. Option 1: Demolish the Hall
Indicative costings to demolish the Hall are $165,000 with an unknown cost to create a Memorial
Park.
There is little expressed public support for demolishing the Hall and replacing it with a memorial or
recreational Park.
Option 1 is not recommended.
5.2 Option 2: Council repairs and manages the Hall itself
As the trustee of the building, Council has been clear that it will not reopen the building until the
repairs identified in the Independent Building Services report as being essential for public safety are
completed.
The Independent Building Inspections report estimates the cost for Council to undertake the
necessary maintenance works to safely reopen the Hall at between $300,000 to $400,000 and up to
$1million to bring it up to a high standard of repair.
Page 5
Page 19 of 59See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.