MCU23/0096 Application For Material Change Of Use For Educational Establishment (Extension To Existing - Performing Arts Building) And Preliminary Approval For A Master Plan At 115 Eumundi Noosa Rd, Noosaville · Attachment 1 – Mcu 23-0096 – Proposed Conditions
Plans and drawings: the text below has words only, no drawings.
PLANNING & ENVIRONMENT COMMITTEE MEETING REPORT 8TH OCTOBER 2024
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
g. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
h. details on the haulage route, type of vehicle to be utilised during construction activities
and frequency of usage. NB any damage to the existing road system as a result of
haulage operations must be fully repaired at the applicant’s expense
Easements
23. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
24. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
25. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
26. All earthworks and associated retaining structure/batters must be contained entirely within
the subject site unless written permission from the respective landowner(s) is provided to
Council. All earthworks must be undertaken in accordance with the provisions of Australian
Standard AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
Damage to Services and Assets
27. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Preliminary Approval for an Educational Establishment in accordance with a Master Plan
PLANNING
Approved Plans
1. Development authorised by this approval must be undertaken generally in accordance with
the Approved Master Plan listed in the table below.
Plan No. Rev. Plan/Document Name Date
SK02 DA11 College Masterplan prepared by Burling 15.05.2024
Brown
Nature and Extent of Approved Use
2. The total number of enrolled students for the educational establishment must not exceed
1150 and the number of equivalent full-time staff must not exceed 150.