Stormwater Management Plan

Attached to the e-mail MCU18/0097 - Response to Further Advice - Traffic and Stormwater - 115 Eumundi Noosa Rd, Noosaville.

of 40

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.8 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 16, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
GOOD SHEPHERD LUTHERAN COLLEGE                                                         ODYSSEY CONSULTING GROUP
Lot 30 on SP170751                                                          Conceptual Stormwater Management Plan
115 Eumundi Noosa Road, Noosaville                                                                Project No: K4277

5.3.5 Reporting
         An inspection report shall be written by a suitably qualified and experienced scientist/engineer
         following each water quality monitoring episode. The report shall include at least the following
         information.

              Name, address and real property description for the development site;
              Council file reference number (if known);
              Monitoring locations;
              Performance criteria;
              Results for each monitoring location, identifying any breaches of performance criteria, and
              Recommended corrective actions to be taken and additional sediment and erosion controls, if
               required.

         Inspection reports shall be provided to the contractor for their action and compilation in an on-site
         register. If the above-mentioned performance criteria are exceeded and results from the downstream
         monitoring stations show significant deterioration from upstream results (if applicable), the
         contractor shall implement all recommendation of the inspection report within (1) working day of
         receipt of the report.

5.4      Operational Phase

         The following sections provide details of the stormwater quality improvement devices (SQID’s)
         proposed for the operational phase of the development. Odyssey Consulting Group, Stormwater
         Management Plan (Ref: K4277/P007/E) and Odyssey Consulting Group, Stormwater Detention and
         Bioretention Details (Ref: K4277/P010/D) included as Appendix F illustrates the size and location of
         the proposed SQID’s.

         MUSIC Version 6.3.0 has been used for modelling of the proposed treatment train.

5.4.1 Stormwater Quality Improvement Devices
         Site runoff from Catchment A1 and Catchment B will be directed onto permeable pavements before
         draining into two bio-retention basins located at the West (basin 1) and South (basin 2) of the site
         respectively. Catchment A2 will bypass permeable pavement and be directed into bio-retention basin
         1 on the west of the site. Catchment C will bypass treatment and discharge direct to Council
         stormwater infrastructure. For further details see Odyssey Consulting Group, Stormwater
         Management Plan (Ref: K4277/P007/E) included in Appendix F. The proposed treatment train for the
         development is shown in Figure 4.




         Figure 4:      Music Modelling Treatment Train



K4277-0002-D                                       14 February 2019                                   Page 12 of 16
Log in to download the original file

Stormwater Management Plan.pdf · 13.8 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.