Table 2 – Maintenance of ESC measures
Timeframe for Completion of
ESC Measure Maintenance Trigger
Maintenance
When settled sediment exceeds the
Sediment basins Within 7 days of the inspection.
volume of the sediment storage zone
The capacity of ESC measures falls
Other ESC measures By the end of the day.
below 75%.
Sediment accumulation on ESC devices is to be removed and disposed of to the satisfaction of Noosa Council.
5 CONCLUSION
This SWMP outlines how stormwater runoff from the site will be managed in order to not adversely impact the
receiving environment.
The proposed lawful point of discharge for the proposed development is to an existing stormwater grate located on
the northeastern corner of the allotment. Stormwater detention is not considered to be required as the proposal is
for a residential duplex on an existing lot. Stormwater runoff from the development site will need to be collected on
site and directed to the stormwater grate at the built phase to ensure no adverse impacts to neighbouring properties
as a result of the development.
The site is not impacted by flooding or tidal inundation.
Stormwater treatment should be managed through the implementation of best management practices on site. Based
on the scale of the proposed development, and typical pollutants produced, these measures are considered adequate.
By implementing the proposed stormwater management system, and providing adequate maintenance, the
downstream environment and neighbouring properties will not experience any adverse deterioration of water quality
as a result of the proposed development.
S25-107 Stormwater Management Report Page 5 of 6
Uncontrolled When Printed
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (S25-107-Stormwater Report.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.