SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 12 DECEMBER 2017
Risks & Opportunities
Financial risks
Client request for scope changes. This will be mitigated through Project Control Group
management and limitation of client requested scope variations.
Latent conditions. Typically a geotechnical risk, previous investigations have mitigated much
of this risk. There is some residual risk associated with the large amenities refurbishment and
potential hidden defects that will be carefully monitored.
Costs relating to service connections such as Energex and Unity Water. This has been
mitigated through careful investigation of the scope requirements with some allowances
based on industry experience for similar constructions.
Variation risks. This has been partly mitigated through the lump sum construction
procurement method with further mitigation through post-tender clarifications, committing
Midson Constructions firmly to the scope of works.
Contingency amount being insufficient. This risk may be mitigated through the adoption of
saving options negotiated with Midson Constructions. The risk profile for the nature of the
construction for this project has also informed an appropriate allocation of contingency level.
Customer dissatisfaction leading to lost revenue. This has been mitigated by careful
management of pre-bookings and the development of a construction schedule that seeks to
minimise as much as possible impact on patrons, including limited daily works hours,
downtime during peak holiday periods, on-site pedestrian and traffic management.
Time risks
Wet weather delays. Construction during the typically dry season aims to mitigate this. Some
wet-weather day allocations have been built into the program.
Delays in obtaining final approvals have been built into the pre-construction program.
Delays from complex activities such as asbestos removal have been mitigated through
previous investigations of extent of asbestos and industry-advised timeframes for this type of
activity being built into the program.
Safety Risks
Midson Constructions will be appointed as the Principal Contractor and responsible for
Workplace Health and Safety (WHS) of the construction sites. Prior to construction
commencing, WHS and pedestrian and traffic management plans will be required to be
submitted to Council for approval. Council will undertake regular audits on contractor
compliance with these approved plans throughout construction.
Asbestos removal. Only licensed and accredited subcontractors will be used for this activity,
and a safety management plan will be submitted for approval by them prior to
commencement of this activity.
Scope & Quality
The risk of meeting project objectives will be managed via Council staff reviews supported by
specialist consultants who developed the performance specifications.
Resourcing
Midson Constructions have nominated a highly capable team for this project limiting the
resourcing risks to this project. Council will engage an external superintendent and
architectural / engineering consultants to further mitigate any risk.
Page 35 of 79
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.