2009/1058

 

Sewer Mains

37.

33.

The site shall be connected to Council’s existing sewerage reticulation systems and be
constructed in accordance with Council's standards and requirements at no cost to Council.

The applicant is advised that this approval does not relate to sewer main setbacks within the
site or adjacent to the site, as a Building Certifier will assess this during the Building
Application process and after consultation with Council's Water & Sewerage section. Should
any Council sewer mains be affected as a result of non-compliance with this condition, the
Building Certifier will be held personally liable. To this end, all Building Applications will need
a site plan prepared & certified by a licensed surveyor clearly illustrating the exact location of
any séwer mains and the ‘zone of influence’ of these mains.

Town Water Supply

39.

40.

The site shall be connected to Council's existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.

Each individual water connection to the water reticulation system shail extend to the property
boundary and be metered. All fees for the’ supply of water meters shall be paid to the
Council.

Earthworks

41.

42.

Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences or structures that border the development site. Fences that are affected shall be
replaced prior to the Building Certifier issuing the Certificate of Classification. In this regard
any fences to be replaced shall be clearly shown on the plans submitted for Building Works
approval.

Earthworks required on site shall be carried out in accordance with Council's Planning
Scheme Policy PSP5 Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or concentrate or direct overland flow on to an
adjoining property.

Site Stability

43.

A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
determine the soil classification, establish whether any measures are required to protect the
stability of adjoining buildings and/or structures and/or land, and make recommendations on
the type of foundation system(s) best suited for the proposed development and recommend
any measures to prevent slumping during excavations. The recommendations of this report
shall be incorporated into the design and construction of the proposed development.

Erosion and Sediment Control

44,

Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controled gravel access to the site and
controlled disposal of waste, will be necessary.

in this regard, plans detailing the methods of controlling erosion and sediment in accordance
with the Healthy Waterways document and fact sheet series titled Controlling Stormwater
Pollution on your Building Site dated 2006 are required to be submitted with the application
for a Building Works Permit.

General Engineering

45.

46.

Any damage caused to any public utility during the course of construction shail be repaired
to Council’s standards and at no cost to Council.

Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council

Page 6 of 17

Used in these records

About this file

File size
2.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

09_1058 - Change a Development Approval [As Published].pdf · 2.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.