Final Order 25.10.2021

of 31

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

      Earthworks and Retaining Walls
33.   All fill and associated batters must be undertaken in accordance with an Operational
      Works approval, and contained entirely within the subject site unless written permission
      from the respective landowner(s) is provided to Council.
      Damage to Services and Assets
34.   Any damage caused to existing services and assets as a result of the development
      works must be repaired at no cost to the asset owner at the following times:
      a.    where the damage would cause a hazard to pedestrian or vehicle safety,
            immediately; or
      b.    where otherwise, upon completion of the works associated with the development.
      Any repair work which proposes to alter the alignment or level of existing services and
      assets must first be referred to the relevant service authority for approval


5.    ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form
part of the assessment manager conditions:
1.    All developments and/or changes to existing developments may require payment of
      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges
      Resolution” made pursuant to the planning legislation and regulations current at the time
      of issue.
      Development Compliance Inspection
2.    Prior to the commencement of the use, please contact Council's Development
      Assessment Branch to arrange a Development Compliance Inspection.
      Performance Bond
3.    Where the works include Council assets (construction of new or modifications to
      existing) a portion of the performance bond will be retained as a “maintenance bond” as
      described in Council’s Planning Scheme Policy 6 Engineering Design Standards.
      Alternatively the developer may submit a separate “maintenance bond” at the
      completion of the works.
      The bond amount will be:
       a)    5% of the agreed value of the works or
       b)    $1500, whichever is the greater amount


6.    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit Required          Subject of the required Development Permit

 Development Permit for Building Works        All building works

 Development Permit for Building Works        Demolition

 Development Permit for Operational Works     Civil, Earthworks,   Stormwater,   Landscaping,
                                              Driveway




                                                                            5642942_1

                                                                                                  6
Log in to download the original file

Final Order 25.10.2021.pdf · 7.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.