21-2999-21 Nannygai St Noosaville-Site Entry-Exit-One Property and Design - Notes and Risk assessment
Attached to the e-mail Operational Works Application OPW21/0213 - 21 Nannygai Street Noosaville (Lot 54 on RP76937).
AACTION TRAFFIC CONTROL PTY LTD
ABN: 37 128 649 445
UNIT 3 14-16 IMBOON STREET
DECEPTION BAY QLD 4508
PHONE: 07 3204 9988 FAX: 07 3204 9179
TRAFFIC GUIDANCE SCHEME
NOTES AND RISK ASSESSMENT
TGS #: 21-2999
Project Address: 21 Nannygai St Noosaville
Bells CLIENT: One Property and Design Pty Ltd
CLIENT CONTACT: David Liekari
PHONE NUMBER: 0403 788 198
JOB PURCHASE ORDER #:
AACTION TRAFFIC REPRESENTATIVE
TMD Contact Name: Petrina Tilyard
Contact Number: 0447 797 596
Contact Email: [email protected]
TMD Licence OP 262
Signature
Aaction Traffic Department of Transport & Main Roads
Registration Licence TMR # 0202
Date 12/07/2021
DOCUMENT CONTROL
REGISTER OF AMENDMENTS
Date Page Version Description of Amendments Revision Approved
No No Date by
12/07/2021 ORIGINAL DOCUMENT 30/10/2021
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed
Revised: Version 1 Author: Shaylene Rubach Approved by: Wayne Grice Page 1 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 8 pages
Page 2
TRAFFIC CONSIDERATIONS AND CONTROL MEASURES
1. Project Activity/Scope: Site Entry/Exit from building site at #21 Nannygai St
2. Site specific TGS:
21-2999 – Site Entry/Exit
3. TC requirements – Not Required
4. Site Operating Times preferred –24hr times (subject to Permit approval) : 0600-1800 as per One
Property and Design Pty Ltd’s Schedule of Works
5. Project Start Date and duration of job: As per One Property and Design Pty Ltd’s Schedule
of Works
6. Speed: Speed prior to work commencement 50k. Speed has not been reduced as per
attached TGS.
7. How close to the trafficable lanes will the workers be working? >3m
8. Highlight D Value
Table 4.2 – Value of Dimension D (m)
dimension D Speed limit¹
(km/h)
40 or less 5 to 10
50 10 to 15
60 15 to 45
70, 80 60 to 80
90, 100 80 to 100
110 100 to 120
9. Direction of Closure: All directions
10. Is there open Excavation? No
What’s Depth of excavation?
Width Excavation?
Length Excavation?
Is barrier System required?
Barrier System selected?
Are Steel Plates being used?
Table E1 – Protection / delineation adjacent to excavations
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed
Revised: Version 1 Author: Shaylene Rubach Approved by: Wayne Grice Page 2 of 9
Page 3
Speed of Traffic Clearance to Depth of excavation, mm
traffic¹ km/h volume² vpd excavation³
m 50 to 250 260 to 500 > 500
< 70 All < 2.5 Standard Close Safety
delineation delineation barrier
2.5 to 5.0 Standard Standard Close
delineation delineation delineation
> 5.0 None None None
≥ 70 ≤1500 ≤ 5.0 Standard Close Safety
delineation delineation barrier
> 5.0 None None None
> 1500 ≤ 6.0 Standard Close Safety
delineation delineation barrier
> 6.0 None None None
NOTES:
1. Posted speed limit during roadworks.
2. For multilane roads, one way volume. For 2-lane, 2-way roads, sum of both directions.
3. Clearance to nearest edge of traffic lane or nominal edge if the edge is not marked.
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed
Revised: Version 1 Author: Shaylene Rubach Approved by: Wayne Grice Page 3 of 9
Page 4
11. Taper Lengths
Table 4.6
Permanent posted Recommended taper length, m
speed, km/h
Traffic control at Lateral shift taper Merge taper
beginning of taper
40 or Less 15 5 15
50 15 15 30
60 30 30 60
70 30 60-80 120-160
80 30 60-80 120-160
90 30 60-80 120-160
100 30 60-80 120-160
Greater than 100 30 60-80 120-160
The speed of traffic in Table 4.6 is the permanent posted speed of the road before the work
site is established.
12. Are there Bus Stops Taxi Ranks to be considered? No bus stops are within the road closure.
13. Pedestrian and Cyclist control? Cyclists can pass the site via the detour route.
14. Are Local Businesses and property owners affected? All residents and local business will
have continual access to their driveways. Closures will be in place after the last driveway.
15. Is Containment Fencing on site? N/A
16. N/Area of Job Site: Length N/Am Width: N/Am
17. Traffic Controller Sign
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed
Revised: Version 1 Author: Shaylene Rubach Approved by: Wayne Grice Page 4 of 9
Page 5
18. Traffic controllers shall be relieved from their duty after not more than 2 hours for a period
of rest or “other duties” of at least 15 minutes. [NOTE: “Other duties” does not include
operation of a STOP/SLOW bat to control traffic or any duties involving standing in one
position, or controlling traffic with a traffic control device] as per TCAS 2.4 Page 7
19.
As this sign is used to warn of the presence of personnel, it shall
only be displayed when they are actually working, or are visible to
traffic, or both, and shall be removed or covered when workers
have left the work area or are no longer visible to traffic.
20. Truck Turning
3.16.2 Trucks (T2-25), Trucks The Trucks (T2-25) sign should
(W5-22) T2-25 be used where trucks may cross,
enter or leave the road from an
adjoining property at a frequency
and in circumstances which
create a hazard. The sign should
be displayed only when the need
exists and removed or covered
when truck activity has ceased.
The sign should be placed on the
side of the road from which trucks
will be crossing or entering
21. Traffic controllers must ensure that they have a clear escape path to a non-traffic (closed)
section of the roadway, shoulder, footpath or median.
22. Signage: All static signage erected is compliant to the MUTCD Part 3 Works on Roads
Eleventh Issue November 2019 and AS1742.4 including the size and reflectivity.
23. Conflicting signage: Any conflicting fixed signage must be covered and uncovered after the
work ceases.
24. Short Term Signage: Erections of signage for short term operations should be arranged so
that the signs are prominently displayed to all vehicular traffic as safety warning devices for
traffic control works. The sign shall be erected on the signage legs so that signs are clearly
off the ground and free of obstruction, the minimum height from the shoulder surface to the
bottom edge of sign is 200mm
Long Term Signage: Signs continuously required for works going longer than two (2) weeks
should be erected in a permanent manner, e.g on posts sunk into the ground - Ref 4.75 Sign
Display- MUTCD Part 3. (Will be determined by Site visits)
On open road areas, uncurbed roads, built-up areas where signs are to be erected on posts,
they should normally be placed clear of the outer edge of shoulder and at least 2m clear of
the travelled path, whichever is the greater clearance. They should be erected 1 to 1.5m
above the level of the nearest edge of the travelled path to the underside of the sign
25. Vehicle Mounted Warning Devices: Signage vehicles that are required for the
implementation of the Traffic Guidance Scheme must be fitted with an electronic arrow
board and two flashing beacons as described by the MUTCD Part 3 Eleventh Edition 2019
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed
Revised: Version 1 Author: Shaylene Rubach Approved by: Wayne Grice Page 5 of 9
Page 6
26. Work Method Statements: Preparation of a Safe Work Method Statement (SWMS) involves
identifying potential hazards, assessing their risk and recording how to eliminate or minimize
the risk to employee and public safety. Where potential hazards are identified they are
assessed using the Site-Specific SWMS and a Hazard Report is completed
27. Prior to commencement of work: On site SWMS will be reviewed based on the Traffic
Guidance Scheme, which conforms to the MUTCD and AS 1742.3. SWMS update will be
reviewed every three monthly unless otherwise requested. All site traffic controllers are
regularly audited and tool boxed to ensure SWMS, TGS’s and State Guidelines and AS1742.3
are followed. Any amendment to the SWMS is noted during audit and safety inspections.
28. Traffic controllers: Have a duty of care to raise any concerns in regard to safety issues on
site. If there is a change to TGS, Scope of works traffic controller must contact Aaction
Traffic’s TMD immediately. Any identified safety concerns must contact Aaction Traffic
Workplace Health and Safety Manager. Traffic Controllers are to only engage in traffic
control duties, remain on designated point and maintain that position unless advised by
Aaction Management.
29. Record Keeping: All traffic management records will be maintained in accordance with the
MUTCD Part 3 2019, Eleventh Issue November 2019 and the QLD Code of Practice for Works
on Roads. Signage must be checked regularly and times notes on the Daily Signage Pre start
Register.
30. Site Communications: Visual contact and two ways radio contact must be maintained by the
Traffic Controllers at all times. Radio channel to be selected upon arrival at site and agreed
upon with all other personnel.
31. Traffic Cones, Barriers and Bollards: Delineating devices (eg: traffic cones, bollards, post
mounted delineators) should generally be placed 1mtr clear of the travel path. Cones should
be spaced so as to discourage entry to the work area, generally from 5mtr to 25mtr apart.
Spacing of cones and bollards may need to be reduced to as little as 1mtr if needed. Barriers
are shown on TGS to separate motorists from work area to provide more protection to
workers on site
32. Setting out and recovery of Signage and devices (as per MUTCD part 3 2019 clause 2.5.3):
Before work commences, signs and devices at the approaches to and within the work area
should be set out in accordance with the traffic guidance scheme in the following sequence:
• Advance warning and regulatory signs (including temporary speed zone signs)
• All intermediate advance warning and regulatory signs and devices required in
advance of the taper or start of the work area
• All delineating devices required to form the taper including the illuminated flashing
arrow signs at the end of the taper where required
• Delineation of the work area or side track
• All other required warning and regulatory signs including termination and end of
temporary speed zone signs
Recovery of signage and devices at the conclusion of the work shall be done in the reverse
order using the same work method as for setting out
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed
Revised: Version 1 Author: Shaylene Rubach Approved by: Wayne Grice Page 6 of 9
Page 7
33. Scope of works and TGS: The controlled version of this Scope of works and TGS will be held
electronically by Aaction Traffic Control Pty Ltd and will be made available to all project
personnel. Aaction Traffic TMD will maintain, review and update Scope of works and TGS
34. Review: TGS and Scope of works be reviewed every twelve months from the date of issue.
35. TGS Risk Assessment
SAFETY AND ENVIRONMENTAL HAZARD IDENTIFICATION/RISK ASSESSMENT
LIKELIHOOD CONSEQUENCE
Almost Event will occur on a Catastrophic Safety: Fatality/ Multiple Fatalities or significant irreversible effects
Certain yearly basis Revenue: High Financial Impact
Likely Event has occurred Major Safety: Severe irreversible to 1 or more persons
several times or more in Revenue: Medium Financial Impact
your career
Possible Event might occur once Moderate Safety: Moderate irreversible disability or impairment to 1 or more
in a year persons
Revenue: Medium Financial Impact
Unlikely Event does not occur Minor Safety: Objective but reversible disability requiring hospitalisation
somewhere from time to Revenue: Low Financial Impact
time
Rare Heard of something like Insignificant Safety: No medical treatment, no damage to equipment
the event occurring Revenue: Low Financial Impact
somewhere
CONSEQUENCE
Likelihood
Insignif. (1) Minor (2) Modera. (3) Major (4) Catastr. (5)
Almost Certain (5) 3 3 4 4 4
Likely (4) 2 3 3 4 4
Possible (3) 1 2 3 4 4
Unlikely (2) 1 2 2 3 4
Rare (1) 1 2 2 3 3
4 Very High (VH) URGENT - Stop work immediately, the risk requires immediate attention
3 High (H) Continue with supervision and control measures in SWMS or site risk assessment
2 Medium (M) Use control measures to ensure risk is low as reasonable possible
1 Low (L) Manage by routine procedures and safe practices
RA-TGS PREPARATION HIERARCHY OF CONTROL
Project Coordinator completes TGS in To properly manage exposure to foreseeable risks a person on
accordance with Aaction Traffic and DTMR location, consider the appropriateness of control measures in the
(MUTCD) standards and client requests (OPS- following descending order of effectiveness:
FORM-008) • Elimination: Elimination the hazard entirely
↓ • Substitution: If not possible to remove, minimise the risk
Project Coordinator prepares RA-TGS as per by substitution of a lesser risk.
drawings • Isolation: Isolating the hazard giving rise to the risk
↓ • Engineering: Minimise the risk by engineering means
Identify risks/impacts associated with each • Administration: Applying administrative measures
activity step • Personal: Protective Equipment: Wear appropriate PPE
at the worksite
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed
Revised: Version 1 Author: Shaylene Rubach Approved by: Wayne Grice Page 7 of 9
Page 8
↓
Assess consequences and likelihood of each risk This Risk Assessment has been prepared as per the
↓
Assess level of risk Manual Of Uniform Traffic Control Devices Part 3, Eighth
↓ Issue, ( July 2018), Clause 2.2.3.b – A Risk Assessment is
Determine appropriate control measures to appropriate, “When preparing traffic guidance schemes
eliminate the risk or reduce it to as low for more extensive or complex works where site specific
reasonably practicable (refer to Hierarchy of
risks will assume importance. “
Control)
↓
Project Coordinator in charge of RA-TGS to sign
Cover Page
↓
All Stakeholders to monitor activity and make
suggestions for improvement to the RA-TGS
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed
Revised: Version 1 Author: Shaylene Rubach Approved by: Wayne Grice Page 8 of 9
Page 9
Risk Assessment Schedule Likelihood (1-5), Consequence (1-5), Risk Level (L-VH)
Ref Risk Associated Safety Hazard Curren Safety Control Residual Action Required By
. With t Risk Measure(s) Required Risk
Description Description
1. Work Area/Workers Work area are inside 4 Site Entry/Exit with 2 Client
the normal traffic signage and delineation
lane. to be placed out prior to
the worksite to allow
notifications of the works
being conducted.
2. Pedestrians Pedestrians moving 4 If any Pedestrians 2 Client
within the work appear near the site
area and signage will eb situated
tripping/falling. at the entrance to site
to warn them of
vehicle movement in
the area.
3. Traffic Traffic being 4 Signage will be in place 2 Client
confused by the for the duration of the
changes in travel closures to notify
path. vehicles of workers
onsite.
4. Local Access Local residents not 4 Access to driveways to 2 Client
being able to access be maintained at all Traffic Control
properties and times.
worksite causing
delays
Issued: Traffic Guidance Scheme & Scope of Works Uncontrolled when printed