BROWN CONSULTING (QLD) PTY LTD – SUNSHINE COAST
DIVISION 20: WATER SUPPLY AND SEWERAGE RETICULATION CODE
Table 14-59 Water Supply
Specific Outcomes Probable Solutions Proposed Measures
(if code assessable)
14.181 Design and Construction
(Water)
O1 Water Supply Infrastructure S1.1 Water supply infrastructure A water supply analysis has been
is designed in accordance with undertaken. The results of the
(a) Meets the needs of the
Section 3 of PSP 6 – Engineering study indicate that sufficient
users;
Design Standards – Water and capacity is available for the
(b) Is designed to be Sewerage and As Constructed proposed development.
compatible with existing data submitted in accordance with
infrastructure; and Section 7 of PSP 6 – Engineering
Design Standards – Water and
(c) Is deigned using materials Sewerage.
that are suitable for the
use, durable, easy to
maintain and cost effective,
taking into account the
whole of life cycle cost and
Council’s maintenance
inventory.
O2 Water supply infrastructure S2.1 Water supply infrastructure All water supply infrastructure will
is constructed: is constructed in accordance with be constructed and tested in
Section 6 of PSP 6 – Engineering accordance with Council
(a) in accordance with
Design Standards – Water and requirements.
appropriate engineering
Sewerage;
standards; and
AND
(b) to minimise adverse
environmental impacts.
S2.2 Erosion and Sediment Erosion and sediment control
control measures are designed measures will be prepared as part
and implemented in accordance of the operational works (civil)
with the Institution of Engineers design drawings.
Australia (Qld Division) Soil
Erosion and Sediment Control –
Guidelines for Queensland
Construction Sites.
O3 Water supply infrastructure No solution provided. Water supply infrastructure will be
is proven to be suitable for its constructed and tested to
use prior to Council accepting Council’s satisfaction prior to hand
the dedicated asset. over.
O4 Water supply infrastructure No solution provided. Water supply infrastructure will be
is provided with all supporting supported by all required technical
technical documentation. documentation.
O5 Where buildings or other S5.1 The footing of any building All existing infrastructure will be
structures are in proximity to or structure is located clear of the protected from the proposed
Council’s water supply zone of influence but no closer works.
infrastructure, provision is than 1.5m (measured horizontally)
made to protect the from infrastructure including
infrastructure from physical sewers, water mains and
damage and to allow ongoing stormwater structures.
maintenance by Council.
AND
DEVELOPMENT APPLICATION (MCU): RSL CARE, TRADING POST ROAD, COOROY PAGE 23
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Engineering report [As Published]Related documentApplication case desk ↗
About this file
- File size
- 354 KB (small file)
- File type
No other editions are linked here.