GIA application and Court Judgement Part 1 of 2 132006.268..02

of 26

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

AMENDMENT 2
The Cooroy Mountain Spring Water facility will operate with a maximum of 10 employees and a maximum of 3 visitors. As
such, it is requested that Condition 13, which refers to the required number of carparks, be amended as follows:

13. A minimum number of 28 13 uncovered carpark spaces shall be provided on site, including 1 clearly
defined disabled carpark space.

AMENDMENT 3
It is requested that a payment plan be implemented for the contributions outlined within Conditions 15 and 16. As such, itis
requested that the following notation be included:

Payment of the applicable contributions outlined by Conditions 15 and 16 is to be made in
accordance with the approved payment plan.

AMENDMENT 4

Condition 18A (i) - (vii) refers to Effluent Disposal requirements, which will now be superseded by the Site and Soil
Investigation for On-site Wastewater Treatment and Effluent Disposal prepared by Future-plus Environmental (refer to
Attachment Ill). This report addresses each provision within Condition 18A and integrates the relevant requirements or
changes, where applicable. As such, the following amendments are requested:

18A. The design and construction of the on-site effluent disposal system and disposal area shall be in
accordance with the Concepty fluen eatment_and—Disposal_Strategy_prepared_by_Gilben_and

   

prepared by Future-plus Environmental, dated November-2009-November 2013, subject to the following
requirements:

(i) | Ongoing monitoring of treatment process and disposal areas shall be undertaken to ensure both
are functioning effectively over time. They shail be undertaken generally as follows:

e Annual monitoring shall be undertaken form the time of commissioning to determine the
quality of the wastewater produced from the effluent treatment system;

¢ Monitoring of the soils, vegetation and groundwater in the application area shall be undertaken
every three years to establish that such is not percolating into the groundwater;

e Sampling and testing shall be in accordance with relevant regulatory requirements and
manuals such as those provided by the Environmental Protection Agency, with testing
undertaken by an accredited Laboratory;

¢ Continuous monitoring shall be undertaken by the system for any water on the surface of the
application area, downslope resurfacing, changing plant growth on or around the application
area and any other signs of problems, and addressed through maintenance or servicing.

 
Log in to download the original file

GIA application and Court Judgement Part 1 of 2 132006.268..02.pdf · 807 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.