P-EA-100527093 - EA Permit - Noosa Shire Council - 20231108 (3)
Attached to the e-mail MCU23/0039 & OPW23/0052 - SARA concurrence agency response.
Permit
Environmental authority P-EA-100527093
The dredging activity must be undertaken in accordance with the Dredge Management
G12.4
Plan required in condition G12.0.
Sediment Sampling
Prior to commencing a dredge operation, a Sampling Program must be designed and
signed off by an appropriately qualified person, which meets the following minimum
requirements in the latest edition of the National assessment guidelines for dredging:
G13.0
a) testing for parameters listed in Table 1: Practical quantitation limits for typical
sediment contaminants, and other analytical parameters; and
b) number of sampling locations listed in Table 6: Minimum number of sampling
locations.
Prior to commencing a dredge operation, sediments from the dredge footprint must be
G13.1
sampled in accordance with the Sampling Program.
A written statement of compliance must be submitted4 to the administering authority at least
20 business days prior to the commencing a dredge operation that:
a) is prepared by an appropriately qualified person; and
b) states whether the sampling was undertaken in accordance with the Sampling Program;
and
c) states whether the sediments sampled exceed the Practical Quantitation Limits for the
parameters in Table1: Practical quantitation limits for typical sediment contaminants, and
G13.2
other analytical parameters of the National assessment guidelines for dredging; and
d) contains any supporting information relied upon in making the statement.
4 Submission can be via email to [email protected] or mailed to:
Department of Environment and Science
Permit and Licence Management
Implementation and Support Unit
GPO Box 2454
Brisbane QLD 4001
A Dredge Operation Completion Report must be prepared by an appropriately qualified
person and submitted5 to the administering authority within 3 months of the completion of
a dredge operation.
5 Submission can be via email to [email protected] or mailed to:
G14.0
Department of Environment and Science
Permit and Licence Management
Implementation and Support Unit
GPO Box 2454
Brisbane QLD 4001
The Dredge Operation Completion Report required by condition G14.0 must include:
a) the results, including all raw data, from any monitoring conducted during the carrying
out of the dredge operation;
b) a description of actions taken to minimise any environmental risk identified during
G14.1 the dredge operation, including but not limited to actions taken as a result of risks
identified from monitoring and environmental complaints; and
c) a hydrographic survey prepared by an appropriately qualified person of the
dredge footprint and the surrounding adjacent area likely to have been affected by
the dredging during the relevant dredge operation; and
Page 9 of 18 • ESR/2016/3415 • Version 3.00 • Last reviewed: 29 MAR 2023 Department of Environment and Science
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.