Original PDF page 23, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Cut and fill as required to complete the works. Assumption that civil earthworks will provide finished levels +/-
150mm from required landscape levels. Refer to Civil documents to confirm provided finished levels.
Remove spoil and excess fill from site.

The Contractor will be required to achieve smooth even grading to landscape areas. The Contractor shall
allow to remove existing plant matter, debris, rubble or other loose materials likely to interfere with the new
work, and consolidate the filling to all resulting excavations. The Contractor is required to carry out final
trimming of the entire works of the grades. Any areas of discrepancy from the Drawings should be brought to
the attention of the Landscape Architect. Fine grading shall be undertaken with a tolerance of ± 25mm.

Spot levels take precedence over contour lines and ground profile lines.

The subgrade is to be compacted to 95% minimum dry density ratio (+ 0mm- 25mm of design levels) prior to
sub-base placement. Any areas of soft ground are to be excavated & replaced with suitable fill and
compacted to prevent subsidence. Provided that all areas are free draining, and no ponding of water occurs.
Subsoil drains to have minimum fall of 1:100.

Filling in layers approximately 150 mm thick compacted to 85% of the dry density ratio of the surrounding soil
as determined by AS 1289, to minimise slumping and further internal packing down. Corners and
intersections of planes shall be rounded gradual and curves generous. To grading from edgings, provide
horizontal shoulders, minimum width 500 mm, before any change of level.

Earth Mounds
Planting mounds shall be formed from topsoil to the depths as required. The profile shall be such that the
placement of topsoil, soil mix and mulch shall bring the mounds to the finished levels shown on the drawings.
Slopes to mounds shall be no greater than 1:3 unless otherwise shown on the drawings. Ensure existing
ground levels in locations of mounds are deep ripped 150mm prior to formation of mounds.

Rake over all mounds for smooth profile.

Filling in layers as stated above.


3.5.        SETTING OUT
Prior to commencing each stage of the Landscape works, set out alignments of all paths, walls and planting
must be inspected and approved by the Landscape Architect. This may include key set-out points for
pavement pattern.




URBIS
URB -P0003847-001-SP                                                                                       PAGE   8
Log in to download the original file

SUPERSEDEDApproved Plan OPW22-0123.pdf · 10.2 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.