Engineering Report
Noosa on Weyba
2.6.2 Performance Criteria
The following are the main items, though not extensive, to be addressed to ensure the performance
objectives are met. Refer to management plan for further detail:
> Site Preparation
> Staff Training - Site Induction
> Storage of Lime on Site
> Site Drainage
> Transportation
> Earthworks
- In areas where excavations may disturb potential or actual ASS, testing shall occur to determine the
liming rate. Acidic materials shall be neutralised in situ prior to any transport within the site.
> Neutralisation
> Dewatering
- In areas where dewatering is required, extracted waters shall be directed to a temporary holding pond.
The extracted waters will then be tested for the parameters. Should the water held in the pond achieve
the release criteria, it may be discharged, however if it doesn’t meet the release criteria, the water is to
be neutralised, and then retested to verify compliance.
> Filling
> Stockpiling
> Monitoring
October 2013 Cardno 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.