                                                                                                   Engineering Report
                                                                                                     Noosa on Weyba



> Regular (daily) inspections of erosion protection measures.
> Inspections during, or following each significant rainfall event for erosion incidence.

2.5.4          Reporting
It is recommended that a weekly check sheet be filled out and monthly reports, including any testing results,
are prepared by the Contractor. The monthly reports should contain information on the performance of the
erosion and sediment control devices and any water quality monitoring results and a brief description of the
same (including any incidences of non-compliance and corrective actions implemented).

2.5.5          Corrective Action
Non-compliance with the water quality ‘Discharge Performance Criteria’, the strategies outlined in the ESCP
and / or conditions of approval must be dealt with immediately. If there is a breach or infringement of
conditions, action will be taken consistent with the nature and seriousness of the breach or infringement.

2.6            Acid Sulfate Soils Management Plan
The purpose of the Acid Sulfate Soils Management Plan (Appendix F) is to identify potential areas of concern
in regards to acid sulphate soils across the development area and provide possible proposed treatment
processes for these areas to support the preliminary development application.
This plan aims to provide a preliminary identification of the acid-producing potential of the soils in relation to
the proposed works, for the development of management strategies to protect sensitive receptors such as
groundwater and adjacent waterways. The aim of this plan is to minimise the impact of the project on the
physical and social environment.
A geotechnical investigation of the site was undertaken by Cardno Bowler on the 10th May 2012. This
investigation included acid sulphate soils sampling and testing at 8 locations across the site.
At the locations shown on Cardno Bowler drawings, boreholes were excavated to a depth of 2 metres. Field
analysis were carried out on 64 samples taken from the boreholes, with the following results.
> The field pHF testing indicated that actual acid sulphate soils were unlikely to be present at the borehole
  locations.
> The field pHFOX testing indicated a low likelihood of Potential Acid Sulphate Soils at the locations tested.
Further laboratory tests (Chromium Reducible Sulfur (Scr) Suite) were undertaken on a total of 16 of the 64
samples taken from the boreholes, with the following results:
> The levels of potential sulfidic acidity (SCR or SPOS) ranged between 0.005% and 0.208%, with the more
  significant levels generally being encountered at depths of 1.0m to 1.5m at boreholes BH4, BH30, BH31.
> The levels of actual acidity (s-TAA) ranged between 0.003% and 0.208%, with the more significant levels
  generally being encountered at depths of 1.0m to 1.5m at locations BH4, BH30, BH31.
> Recommended liming rates are provided in the test reports located in Appendix B of the geotechnical
  investigation report enclosed with this document.
The previous investigations undertaken by Cardno Bowler, and the desktop study indicate that further
investigation of the site will be required and a detailed Acid Sulphate Soils Management Plan be prepared.
This detailed plan will be prepared once the nature and extent of the works in each area has been
determined, and the locations of the further testing required can be accurately provided.

2.6.1          Performance Objectives
To avoid detrimental impact on the soil and water quality and habitat values of the region, as a result of the
discharge of acidic waters from the site during construction activity through the following aims:
> to minimise the potential for the transport of acidic leachate;
> to prevent the development of actual acid sulphate soils; and
> to protect surface water and groundwater quality on the site.



October 2013                                          Cardno                                                         9

Used in these records

About this file

File size
61.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 8- Amended Engineering Report MCU12_0208.pdf · 61.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.