4.1 Stormwater Quality Management
A Stormwater Management Plan (SMP) has been prepared for the development to determine the overall
Water Sensitive Urban Design (WSUD) strategy for the site. The plan outlines WSUD measures that will be
adopted for each precinct and the site as a whole. MUSIC modelling has also been undertaken to ensure
water quality objectives can be met.
Due to the ecologically sensitive location of the site, appropriate stormwater quality treatment is of the
upmost importance. The proposed WSUD strategy for the site includes:
> Community education;
> Reducing potable water demand through use of water efficient devices and appliances;
> Large rainwater tanks (around twice the QDC size requirements) connected to all practically available
roof area to maximise rainwater harvesting and reduce potable water demand;
> Bio-retention basins;
> Bio-retention gardens within the road reserve;
> Bio-retention tree pits within the road reserve;
> Bio-retention swales;
> Vegetated swales;
> Litter baskets;
> Buffer areas; and
> Rehabilitation of Keyser Creek waterway corridor.
Cardno Sketch SK300 provides indicative sizing and locations for the proposed treatment devices. The
proposed treatment devices have been located outside of ecologically sensitive areas and outside of the 100
year ARI extent of inundation, but within the development footprint.
The outlets for stormwater will be designed to minimise concentration of stormwater flows by dispersing the
flows over the terrain of the receiving environment.
MUSIC modelling has shown that the water quality objectives and frequent flow objectives for the site can be
met. The resultant pollutant loads are less than those resulting from the existing rural use of the site. Final
sizing and locations will be refined through the preparation of subsequent development applications and
detailed design.
For further details refer to the SMP prepared by Cardno.
4.2 Flood Study
A flood study has been prepared for the development to determine the flood levels and the potential impact
of development on peak flood levels and flows for neighbouring areas. The study also provides details of the
proposed flood mitigation strategies to be implemented.
In summary, the flood modelling has indicated:
> There is no adverse impacts on flood levels and flows for surrounding properties for local and regional
flood events;
> A reduction in the 100 year ARI event the peak flood level around Lake Entrance Boulevard can be
achieved due to flow attenuation proposed within the site;
> Flood attenuation can be provided through controlled culverts and detention basins;
> 100 year ARI trafficability can be achieved for all proposed and upgraded roads; and
October 2013 Cardno 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.