                                                                        Preliminary Erosion & Sediment Control Strategy
                                                                                                     Noosa on Weyba




2            Existing Site and Proposed Development
2.1          Existing Site Description
The development site is located within Sunshine Coast Council (SCC), in the suburbs of Noosaville and
Weyba, south of the Noosa CBD. The site is traversed by two existing road reserves, north-south Walter
Hay Drive, and east-west Hollett Road.
The total site area is 303 hectares (ha) consisting of Lot 1667 on M3772, Lots 11 and 12 on RP 893393, Lot
2 on RP160983, Lot 7 on RP46782, Lot 53 on SP16357 and Lot 2 on SP179590.
Significant areas of the site have already been previously cleared as part of the current rural land use. The
development footprint is generally located within these existing cleared areas to maximise the retention of
existing vegetation and minimise clearing requirements.
A preliminary geotechnical investigation undertaken by Cardno Bowler identified that the sub-surface
conditions generally encountered across the site comprised of either loose, clayey sands or soft to firm silty /
sandy clays underlain by stiff or better clays.
A review of available existing aerial contour information indicated that the subject site has an undulating
terrain, with four main watercourses transecting through the site. Refer to Cardno Sketch No. 510119/002-
SK002 in Appendix A for the existing site contours. The existing surface levels within the development
footprint range from approximately RL 20m AHD (Australian Height Datum) through the centre of Lot 53 on
SP163571, down to approximately RL 0.0m AHD along the eastern boundary with Lake Weyba. Existing site
grades vary from greater than 10% on the upper slopes down to less than 1% within the watercourse
alignments.

2.2          Developed Site Description
The development proposes to redefine the existing lots into approximately 139.5ha of koala habitat
protection / enlargement of the Noosa National Park, approximately 105.5ha of environmental protected land
and approximately 58ha of net development area. The development will consist of a mix of residential,
retirement living, age care and retail precincts accommodating approximately 2,000 people.
Bulk earthworks are anticipated across the development areas in order to service the allotments and
construct allotment and road gradients in accordance with Sunshine Coast Council’s design guidelines.
Earthworks areas have been minimised to limit the impact on the existing vegetation and retain significant
vegetation. Excavation is generally confined to existing road reserves, proposed roads and the development
footprint.
To understand the cut and fill requirements a preliminary bulk earthworks model was prepared for the site.
The earthworks model was based on preliminary road gradings and adopted building pad levels based on
the flood immunity requirements. Refer to Cardno Sketch No. 510119/002-SK004 in Appendix A for the
preliminary bulk earthworks levels and cut and fill zones.
The preliminary earthworks modelling was carried out over four earthworks zones, with the cut zones
generally located within Areas 1 and 3, and the fill zones generally within Area 2. The area fronting Lake
Weyba is expected to be maintained at existing levels to minimise any visual impact of the development.
Based on the preliminary earthworks modelling undertaken, maximum cut and fill depths are within 3m and
are proposed in areas with substantial buffers to Lake Weyba and the environment protection areas.
It is noted that further bulk earthworks analysis will be undertaken with subsequent development applications
for each precinct. The further analysis will consider the earthwork staging to improve the efficiencies of
hauling material between precincts.




27 September 2013                                    Cardno                                                          2

Used in these records

About this file

File size
61.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 8- Amended Engineering Report MCU12_0208.pdf · 61.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.