Preliminary Erosion & Sediment Control Strategy
Noosa on Weyba
3 Performance Criteria
The ‘Queensland Water Quality Guidelines (2009)’ (QWQ guidelines) (which is referenced by the
Environmental Protection (Water) Policy (2009), a subordinate document of the Environmental Protection Act
(1994)) provides a summary of design objectives for the management of stormwater quality and flow for the
construction phase of developments in Queensland. This summary provided in Table 8.2.1 of the QWQ
guidelines outlines design objectives for a number of pollutants including sediment, nutrients, litter and
hydrocarbons.
Based on the above information, the release criteria for controlled runoff events or pumped discharges from
the construction site is to be as shown in Table 3-1 below.
Table 3-1 Discharge Performance Criteria
Parameter Release Criteria Criteria Type
Total Suspended Solids < 50 mg/L Maximum
Coarse Sediments To be retained on site Descriptive
Turbidity (NTU) < 10% above receiving water Maximum
Nutrients (N and P) Manage through Sediment Control Descriptive
pH 6.5-8.5 Range
Litter No visible litter washed from site Descriptive
Hydrocarbons No visible sheen on receiving water Descriptive
Dissolved Oxygen > 6 mg/L Minimum
Stormwater drainage/flow Peak flows for 1-year and 100-year Maximum
management ARI event to match the pre-
development condition of the site
For the management of sediments, Table 8.2.1 of the QWQ guidelines outlines the following:
Testing of suspended solids and pH within any temporary sediment basins is to occur prior to any
controlled discharges.
Testing of turbidity within the temporary sediment basins and the receiving waters, is to be performed
before the controlled discharging of the sediment basins. If the turbidity of the sediment basin is greater
than 10% above the receiving waters further dosing with gypsum or lime is required until acceptable
levels are reached.
27 September 2013 Cardno 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.