                                                                              Preliminary Erosion & Sediment Control Strategy
                                                                                                           Noosa on Weyba




3              Performance Criteria
The ‘Queensland Water Quality Guidelines (2009)’ (QWQ guidelines) (which is referenced by the
Environmental Protection (Water) Policy (2009), a subordinate document of the Environmental Protection Act
(1994)) provides a summary of design objectives for the management of stormwater quality and flow for the
construction phase of developments in Queensland. This summary provided in Table 8.2.1 of the QWQ
guidelines outlines design objectives for a number of pollutants including sediment, nutrients, litter and
hydrocarbons.
Based on the above information, the release criteria for controlled runoff events or pumped discharges from
the construction site is to be as shown in Table 3-1 below.

Table 3-1      Discharge Performance Criteria
Parameter                               Release Criteria                           Criteria Type
Total Suspended Solids                  < 50 mg/L                                  Maximum
Coarse Sediments                        To be retained on site                     Descriptive
Turbidity (NTU)                         < 10% above receiving water                Maximum
Nutrients (N and P)                     Manage through Sediment Control            Descriptive
pH                                      6.5-8.5                                    Range
Litter                                  No visible litter washed from site         Descriptive
Hydrocarbons                            No visible sheen on receiving water        Descriptive
Dissolved Oxygen                        > 6 mg/L                                   Minimum
Stormwater drainage/flow                Peak flows for 1-year and 100-year         Maximum
management                              ARI event to match the pre-
                                        development condition of the site

For the management of sediments, Table 8.2.1 of the QWQ guidelines outlines the following:
     Testing of suspended solids and pH within any temporary sediment basins is to occur prior to any
     controlled discharges.
     Testing of turbidity within the temporary sediment basins and the receiving waters, is to be performed
     before the controlled discharging of the sediment basins. If the turbidity of the sediment basin is greater
     than 10% above the receiving waters further dosing with gypsum or lime is required until acceptable
     levels are reached.




27 September 2013                                       Cardno                                                             3

Used in these records

About this file

File size
61.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 8- Amended Engineering Report MCU12_0208.pdf · 61.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.