Engineering Report
Noosa on Weyba
2 Earthworks
2.1 Geotechnical Investigations
A Geotechnical Investigation has been carried out across the site to determine the likely geotechnical
conditions. In summary, the investigations concluded the following:
> The subsurface conditions at the site generally consist of a layer of either loose sands or soft to firm clay
underlain by stiff or better clays. Weathered rock was encountered in some of the boreholes;
> Soils types indicate that infiltration of stormwater will not be a suitable method of disposal;
> A topsoil stripping depth of approximately 100mm will be required; and
> A detailed acid sulfate management plan will be required. Once the nature and area of disturbance is
finalised, the requirement for further sampling and testing can be determined and an acid sulphate
management plan undertaken.
For further details refer to the Geotechnical Investigation prepared by Cardno.
2.2 Demolition and Clearing
Significant areas of the site have already been previously cleared as part of the current rural land use. The
development footprint is generally located within these existing cleared areas to maximise the retention of
existing vegetation and minimise clearing requirements.
It is proposed to utilise environmental sensitive construction techniques and tree protection zones during
construction to avoid impact on retained vegetation.
Site visits indicate there are no significant existing structures other than a few rural sheds within the
development areas. Any existing fencing and drainage structures will be removed and disposed offsite
during construction.
2.3 Excavation
To understand the cut and fill requirements a bulk earthworks model has been prepared for the site. Existing
site levels have been based on the aerial survey data provided by JFP and indicated on Cardno Sketch
SK003.
Earthworks areas have been minimised to limit the impact on the existing vegetation and retain significant
vegetation. Excavation is generally confined to existing road reserves, proposed roads and the development
footprint.
The earthworks model has been based on preliminary road gradings and adopted building pad levels based
on the flood immunity requirements. Cardno Sketch SK004 indicates the preliminary bulk earthworks levels
and cut and fill zones. No allowances have been included for compaction losses or bulking factors, and a
500mm deep road box has been assumed.
The earthworks modelling has been carried out over four earthworks areas as indicated in Table 2-1 below.
Cut zones are generally located within Areas 1 and 3, and fill zones generally within Area 2. The area
fronting Lake Weyba has been maintained at existing levels to minimise any visual impact of the
development. Maximum cut and fill depths are within 3m and located in areas with substantial buffers to
Lake Weyba and the environment protection areas.
In summary, the assessment indicates that an overall cut to fill balance can be achieved, potentially negating
the requirement for the importation of fill and haulage of material on existing Council roads or through the
local road network. It is noted that further bulk earthworks analysis will be undertaken with subsequent
development applications for each precinct. The further analysis will consider the earthwork staging to
improve the efficiencies of hauling material between precincts.
October 2013 Cardno 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.