Engineering Report
Noosa on Weyba
Table 2-1 Preliminary Earthwork Design Results
Area Net Cut Net Fill Balance
(m3) (m3) (m3)
1 96,200 14,300 81,900
2 2,200 128,200 -126,000
3 44,500 6,000 38,500
4 5,800 100 5,700
Total 148,700 148,600 100
2.4 Retaining Structures
The development areas generally consist of gentle grades and therefore it is assumed that no inter allotment
retaining walls will be required.
Retaining walls are currently proposed on the eastern boundary of Precinct G, western boundary of Precinct
F, and the road connection between Precincts G and F. Further assessment and refinement of the bulk
earthworks model at the subsequent development application stage will determine final locations and confirm
suitable retaining wall types.
2.5 Erosion and Sediment Control Plan
The aim of the Erosion and Sediment Control Plan (ESCP) plan (Appendix E) is to provide performance
criteria, strategies and procedures to assist in minimising the impact of construction activities on the physical
and social environment.
This ESCP has been prepared with reference to the ‘Best Practice Erosion and Sediment Control (2008)’
guidelines published by the International Erosion Control Association (IECA) Australasia, and current local
best practice engineering and environmental management.
The objective is to control soil erosion on the site and prevent sediment discharge to downstream local water
courses or road stormwater drainage systems during storm events for the construction phase of the project.
Following are the phases for effective erosion and sediment control with details outlined firther within the
report.
2.5.1 Phase 1 Construction – Site Setup Works
The Phase 1 construction works generally involves activities such as installing appropriate stabilised site
access points, establishing site compound areas, and undertaking initial clearing works to allow for the
installation of erosion and sediment control measures and haul roads.
2.5.2 Phase 2 and 3 Construction – Bulk Earthworks and Civil Works
The Phase 2 construction works generally involves the clearing works and bulk earthworks necessary to
create the allotments and roads outlined on the nominated engineering drawings. The Phase 3 construction
works generally involves the civil works associated with the sealing of roadways, the installation of services
and permanent stormwater treatment devices, and the stabilisation of the allotments.
2.5.3 Monitoring
As a minimum the following monitoring should be carried out during the construction phase to confirm
compliance as follows:
> Inspection of any disturbed / filled areas for their potential erosion.
October 2013 Cardno 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.