Preliminary Acid Sulphate Soil Management Plan
Noosa on Weyba
2 Desktop investigation
The desktop investigation component of this plan provides an assessment of the potential for the proposed
development to impact on acid sulphate soils on the subject site.
2.1 Description of Works
The total site area is 303 hectares consisting of Lot 1667 on M3772, Lots 11 and 12 on RP 893393, Lot 2 on
RP160983, Lot 7 on RP46782, Lot 53 on SP16357 and Lot 2 on SP179590.
The development proposes to redefine the existing lots into approximately 139.5ha of koala habitat
protection / enlargement of the Noosa National Park, approximately 105.5ha of environmental protected land
and approximately 58ha of net development area. The development will consist of community title schemes
including a mix of residential, retirement living, aged care and retail precincts accommodating approximately
2,000 people. Cardno Drawing Number 510119/002 - Sketch 002 illustrates the proposed development
areas, and the allocated precinct names A through to K.
The site’s primary access is the proposed roundabout on Walter Hay Drive, with a secondary access from
the south via Tidswell Road. An emergency access connection is also proposed from the west with
connection via Hollett Road to Eumundi-Noosa Road.
It is anticipated that the development works will include:
Stripping of topsoil (expected maximum depth of 0.5 metres);
Earthworks across the site with an expected maximum of 2.5m fill and 2.5m cut;
Excavations required for road construction, services and stormwater.
Preliminary earthworks for the precincts have been undertaken as shown on Cardno Drawing Number
510119/002 - Sketch 004
2.2 Site Features
The SPP 2/02 Guideline prescribes geomorphic and site description criteria to assess the probability of acid
sulphate soils occurring on the site. Table 2-1 provides and assessment of the site features in relation to the
criteria outlined in the SPP Guideline. Based on the information provided in Table 2-1 there is a reasonably
high probability that acid sulphate soils occur on parts of the subject site.
10 October 2013 Cardno 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.