Preliminary Acid Sulphate Soil Management Plan
Noosa on Weyba
6.2 Level of Treatment
In order to determine the level of treatment required, the total amount of lime required to neutralise the
existing and potential ASS on the site must be estimated. Table 6-2 provides an estimation of the amount of
lime needed to neutralise the existing and potential ASS and an indication of the level of treatment
classification for the site.
Table 6-2 Treatment Categories and Liming Rates (Sources from QASSIT Guidelines)
Disturbed Soil Analysis – Oxidisable Sulphur (S%) or equivalent TPA/TAA
soil
(tones) 0.03 0.06 0.1 0.2 0.4 0.6 0.8 1 1.5 2 2.5 3 4 5
1 0 0 0 0 0 0.05 0.05 0.05 0.1 0.1 0.1 0.1 0.2 0.2
5 0 0 0 0.05 0.1 0.1 0.2 0.2 0.4 0.5 0.6 0.7 0.9 1.2
10 0 0.05 0.05 0.1 0.2 0.3 0.4 0.5 0.7 0.9 1.2 1.4 1.9 2.3
15 0 0.05 0.1 0.1 0.3 0.4 0.6 0.7 1.1 1.4 1.8 2.1 2.8 3.5
20 0.05 0.1 0.1 0.2 0.4 0.6 0.7 0.9 1.4 1.9 2.3 2.8 3.7 4.7
25 0.05 0.1 0.1 0.2 0.5 0.7 0.9 1.2 1.8 2.3 2.9 3.5 4.7 5.9
35 0.05 0.1 0.2 0.3 0.7 1.0 1.3 1.6 2.5 3.3 4.1 4.9 6.6 8.2
50 0.1 0.1 0.2 0.5 0.9 1.4 1.9 2.3 3.5 4.7 5.9 7.0 9.4 12
75 0.1 0.2 0.4 0.7 1.4 2.1 2.8 3.5 5.3 7.0 8.8 11 14 18
100 0.1 0.3 0.5 0.9 1.9 2.8 3.7 4.7 7.0 9.4 12 14 19 24
200 0.3 0.6 0.9 1.9 3.7 5.6 7.5 9.4 14 19 24 28 38 47
500 0.7 1.4 2.3 4.7 9.4 14 19 24 35 47 59 70 94 117
750 1.1 2.1 3.5 7.0 14 21 28 35 53 70 88 105 141 176
1,000 1.4 2.8 4.7 9.4 19 28 38 47 70 94 117 141 187 234
2,000 2.8 5.6 9.4 19 38 56 75 94 141 187 234 281 375 468
5,000 7.0 14 23 47 94 141 187 234 351 468 585 702 936 1171
10,000 14 28 47 94 187 281 375 468 702 936 1171 1405 1873 2341
L Low treatment: (<0.1 t lime). Submit disturbance dimensions & Lab Analysis proof to Local
Government (L.G.). Apply 0.05 t (1 bag) or 0.1 t (2 bags) of lime as per Error! Reference source not
ound.Table 6-2.
M Medium treatment: (0.1 to 1 t lime). Submit disturbance dimensions & Lab Analysis proof to L.G.
Thoroughly mix lime (0.1-1 t) as per Table 3 & bund the site.
H High treatment :(> 1 to 5 t lime). Submit Earthworks Application, Management Plan & Lab Analysis
proof to L.G. Management, bunding & monitoring required.
VH Very High treatment: (>5 tonne lime). Earthworks Application or Impact Assessment required for
L.G. (& State agencies). Detailed management, monitoring & bunding required.
A detailed management plan is required if disturbing > 1,000 tonnes of ASS (oxidisable S 0.03 %S or
equivalent TPA or TAA).
Lime rates are for pure fine CaCO3 using a safety factor of 1.5. A factor that accounts for Effective
Neutralising Value is needed for commercial grade lime (see Ahern et al. 1998).
The SPP02/2 Guideline indicates that the highest single laboratory result and the total volume of disturbance
must be used to determine the level of treatment.
10 October 2013 Cardno 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.