Preliminary Acid Sulphate Soil Management Plan
Noosa on Weyba
7 Acid Sulphate Soil Management Plan
The State Planning Policy requires that all pollutants (acid, water soluble iron, aluminium and heavy metals)
must be contained and managed within the site boundaries and treated to acceptable levels.
To achieve compliance with this policy, it is proposed to neutralise any acid sulphate soils which are
disturbed by works on the subject site, including existing and potential acid sulphate soils, by incorporating
alkaline materials (lime) into the soil and water where required.
7.1 Assessment of Management Issues
Table 7-1 provides an assessment of the potential disturbances and the risk associated with each type of
disturbance.
Table 7-1 Assessment of Disturbances
Disturbance Performance criteria Monitoring Verification Management
type Considerations
Excavation of Neutralisation of all All areas, including those Following the application Treatment of acidic and
materials where existing identified as non acidic of the recommended potential acidic materials
Known ASS and potential ASS should be visually volume of lime,
Existing, are identified to achieve a monitored for jarosite, verification testing must Contamination prevention
Potential and soil pH of 6.5-8.5 in black oozes, rust be conducted by the
Non ASS accordance with this coloration and other contractor in consultation
Materials plan. visual indicators during with a geotechnical
works. specialist to ensure all
materials have been
neutralised and display a
zero or negative net
acidity value.
Filling Ensure fill materials are Sampling of all material Validation testing of all fill Fill assessment prior to
outside the action criteria. imported onto the site areas at a rate of 2 test placement.
prior to placement. pits per hectare is
Waters collected in wick Sampling shall be required to ensure
drains shall be collected, undertaken at a rate of 1 imported fill is in
tested and treated where sample per 500 cubic compliance with the
required. metres. QASSIT Action Criteria
outlined in Table 6-1 and
treated site fill displays a
zero or negative net
acidity value
Soil Minimise the potential for Ongoing water quality All extracted waters must Develop and implement a
oxidation of PASS and monitoring of be tested to ensure detailed dewatering plan
Dewatering the treatment of disturbed groundwater bores where compliance with the should extensive soil
ASS and PASS to applicable adopted release criteria. dewatering be necessary.
achieve a pH of 6.5-8.5.
Storage or Ensure that no cross Visual monitoring to Update site log with Restrict the movement of
contamination occurs ensure diversion drains, necessary details. potential contamination
stockpiling of from the storage of acidic bunding and sediment by containing all
Acidic materials. fences are functioning, materials within each
materials where applicable. stage.
Untreated materials shall
not be stockpiled for
more than 70 hours.
All materials must be
contained within each
zone until verification
testing confirms that all
materials display a zero
or negative net acidity
value.
10 October 2013 Cardno 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.