Preliminary Acid Sulphate Soil Management Plan
Noosa on Weyba
Table 7-4 Frequency and Duration of Groundwater Monitoring and Reporting
Development Phase Monitoring Frequency Duration Reporting Frequency
Construction Weekly During Construction Two Monthly
Within 24 hours of a >25mm
rainfall event
Should results prove stable,
frequency may be renegotiated
with Council.
Post Construction Monthly For the duration of the Two monthly
maintenance period
7.16 Validation
The Contractor shall undertake testing of lime treated and placed fill material at a frequency of at least one
3
test per 500m . Tests shall monitor fill for acid generating potential by SPOCAS Method or approved
equivalent such as the Chromium Reducible Sulphur Method.
Laboratory determination of Total Potential Acidity shall be conducted on at least 10% of the samples.
7.17 Contingency
Non-compliance with approved management plans, approved drawings and conditions of consent must be
dealt with immediately. If there is a breach or infringement of the plan or conditions, action will be taken
consistent with the nature and seriousness of the breach or infringement. Action may include:
Issue of “stop work notice”;
Notice to comply pending re-inspection of the site;
Retesting and further neutralising of non-compliant waters;
Rehabilitation of areas degraded by the non-compliance.
Table 7-5 outlines the responses required by the contractor for non-complying monitoring test results.
Table 7-5 Non Compliance Responses
Indicator Response Comments
pH too low <6.5 within Take action to stop discharge and store runoff on site. Reporting as shown
temporary water bodies lime dose to restore to acceptable pH before further discharge. in monitoring
Notify the Site Superintendent and Consultant of non-compliant
discharge (within 24 hours) .
pH too high >8.5 within Take action to stop discharge and store runoff on site.
temporary water bodies Dilute with other water until pH in acceptable range.
re-test for compliance before further discharge.
Suspended Solids / Identify if non-compliance is due to storm event greater than design Noncompliance
Non Filterable Residue storm of control devices. If so accept non-compliance. If not then:- may occur, by
(NFR) >50mg/litre Take action to stop discharge and store runoff on site. design, in >
within temporary water Use flocculation agents to lower NFR or; 3month ARI event
bodies Pump contaminated water over grassed filter strips or buffer (deemed to be 50%
areas to lower NFR. of the ARI one year
Identify (by inspection and/or analysis) if non-compliance is due event)
to damage or ineffectiveness of erosion and sediment control
devices. Repair or redesign/replace if necessary (or required by
Council) to ensure future compliance.
Aluminium (Al) and/or Take action to stop discharge and store runoff on site. Aluminium (Al)
Iron (Fe) too high > 60 Undertake flocculation in consultation with a suitably qualified and/or Iron (Fe) too
µg/litre and 20 µg/litre environmental practitioner. high > 60 µg/litre
respectively within Re-test for compliance before further discharge and 20 µg/litre
temporary water bodies respectively
10 October 2013 Cardno 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.