APPENDIX 1: Preliminary Stormwater Quality Management Plan
EROSION AND SEDIMENT CONTROL PROCEDURES
-
- - - . ~_..-
-, ’~ ._-~ -’-
Construction Phase
Objective Minimise erosion of soils during civil works construction.
Minimise loss of sediment from site during civil works construction.
E&SC measures shall be designed to achieve discharges from the construction site during rainfall events (1 year ARI) to meet the following
criteria:
~ pH 6.5 to 8.5
~ Suspended Solids < 50mg/L (80th percentile)
Turbidity to be calibrated.
Description Responsibility Timeframe
. Install construction fencing to ensure works only occur within designated area. . Foreman . Prior to works
Actions
. Establish a single stabilised entry / exit point. commencing
. Trucks shall use designated entry to site works areas and shall be washed down at a . Foreman .
Ongoing
prior to exiting the site.
. Undertake drainage control measures including: . Foreman .
Ongoing
-
Bypass ’clean’ up-slope water around any soil disturbances
-
Transport stormwater through the work site in a non-erosive manner
-
Minimise hydraulic damage to the adopted erosion and sediment control
measures during storm events.
. Undertake erosion control measures including: .
Ongoing
-
Limit the area of exposure
. Foreman
-
Progressive stabilisation of disturbed areas with native groundcovers
-
Heavy mulch to cover on disturbed areas open without activity for more
than 20 days
. Undertake sediment control measures including: .
Ongoing
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
REFERENCED DOCUMENT - REC13/0015Related documentApplication case desk ↗
About this file
- File size
- 27.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.