                              Sediment basins
                          -
                              Sediment fences                                                                  .   Foreman
                          -
                              Field inlet sediment controls
             .
                 Stockpiles of soil shall be controlled by sediment fences on the down slope side.
             .
                 Any stockpiles of fine soil material (excludes coarse sandy materials) shall be covered
                 with plastic sheeting and sandbags if there is no requirement to access a stockpile
                 within three (3)days.
             .   Water from the external catchment will diverted around/through the site via established
                 road kerb and channel and stormwater system and not allowed to enter disturbed
                 areas of the site.

             .   Stormwater runoff within the site shall be directed via stabilised swales to silt traps.
             .   Disturbed areas should be progressively stabilised as quickly as possible completion
                 of cell and rehabilitation earthworks.
             .   Stabilise disturbed areas with heavy mulch (50mm thick) to ensure that erosion does
                 not occur in disturbed   areas   within 20 days of inactivity, even though works      might
                 continue later.


Monitoring   The Contractor will carry out weekly inspections to check:                                        Foreman            Weekly
                 )Works are only occurring within designated area

                 )Erosion and Sediment Control measures to ensure they are cleaned out and
                     maintained in working order.

                 )Stabilisation is occurring on a progressive basis.

                 )For litter and debris

                 )For discharges from sediment basins.

             The Contractor shall take samples during 4 rainfall events every six months to determine
                                                                                                               Foreman            As required
             levels of TSS, turbidity, pH, Dissolved Oxygen. Total Nitrogen, Total Phosphorus and oil &
             grease in runoff discharging from the construction site.


Reporting    )Contractor to maintain a log of inspections, maintenance actions.                                )Project Manager   )As required

             )Records are to be logged and kept for verification of compliance on a need basis.

             )Records of water quality testing to be retained for compliance.

Used in these records

About this file

File size
27.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

REFERENCED DOCUMENT - REC13_0015.pdf · 27.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.