Cc 9 Cardno
3501-54 2 :
13 June 2007
Attenuation
Cardno’s Surface Water Management Plan (8 February 2007) quantified the increase in
impervious area on the site and the consequent potential increase in runoff. In order to mitigate
this effect and prevent increased downstream flood risk, an attenuation basin was proposed for
the south-west corner of the site. Some 1300m?® in volume, the basin was found, through a
process of hydraulic modelling, to successfully attenuate stormwater flows from the site to rates
lower than in the existing situation, for all events up to and including the 100 year average
recurrence interval.
External Catchments
The site currently drains in a northerly direction. Sheet flow and minor ditches and gullies feed
to an open drain at the northern boundary, which then flows westwards towards Gateway Drive.
Flows then pass through a culvert under the road, before entering an open lake area, situated
north of the existing retail area.
The influence of external catchments on the site is limited. The site falls from the highest levels
in the south east to its point of discharge in the north west. It is bounded to the west by
Gateway drive and a low-lying wetland corridor, to the south by the Eumundi Noosa Road, and
to the east and north by an existing developed site. Levels to the west are lower than on site
and fall to an area of wetland, but the other external catchments are examined in turn:
South
The Eumundi-Noosa Road follows the ridgeline of the hill, and levels fall away on the other side
of the road to the south. It is not expected that the road itself will produce a significant amount
of runoff, falling as it does to both the east and west (i.e. away from the site).
East
An existing developed site is situated to the east, and continues north of the subject site. It
features a drainage network which runs south to north on the other side of the eastern boundary
of the subject site. Based on a site inspection and discussions with the owner of the site, this
line discharges northwards, away from the subject site. Three drainage manholes have been
located and their invert levels recorded, and are shown on Figure 4. Consequently, the site
receives no runoff from the east.
North — Adjacent Site Developed Area
Flows from the developed area of the adjacent site to the north of the subject site are collected
and discharged via a headwall towards, but not on, the subject site. Consideration will be given
to this discharge at the detailed design stage and, if necessary, it will be routed to join the flows
from the undeveloped area described below. The position of the two drainage manholes and
the headwall are shown in Figure 4.
North — Adjacent Site Undeveloped Area
A small area of the adjacent site to the north appears undeveloped and contours indicate that it
may drain back towards the subject site. The area, of approximately 1200m?, would produce
approximately 80 litres per second of runoff in the 100-year event (using a conservative time of
concentration of 10 minutes). Provision will be made along the northern boundary of the subject
site to intercept these flows and convey them westwards to join flows from the subject site at the
legal point of discharge.
North — Subject Site Vegetated Area
The proposed development extends as far as the existing premises to the north. This will leave
an area of undisturbed vegetation that could potentially drain back towards the point of
discharge. Although approximately 2600m? in area, the time of concentration is likely to be
considerable (calculated at 20 minutes), resulting in runoff of approximately 135 litres per
second in the 100-year event.
J:\3501-54\WP\Letter Response to RFI.docSee the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
0015E256.001.pdfRelated documentPublic source context ↗
Response to Information Request [As Published]Related documentApplication case desk ↗
About this file
- File size
- 18.5 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.