Page 7                                                                      <s
 a                                                                             =pmm
                                                                                  \        a conics company
        18.3    Parking Provision Rate - The parking provision rate per square metre proposed for the
                Bunnings development is significantly higher than has previously been agreed to be
                appropriate for a use of this type. This higher provision rate should be explained and/or
                justified. Further, if parking provision rates are to be higher than normal, will design traffic
                generation rates be similarly increased?
TTM states in their attached response that justification to increase traffic generation rates due to the ‘over
supply’ of parking spaces is not required “as they are directly related to and reflect the proposed rate of
parking supply’. Please refer to the attached response as prepared by TTM Traffic in Attachment C.
        18.4    Roundabout at Eumundi Road and Rene Street — At Section 11 of the TTM report, it is
                advised that the Rene Street roundabout should be upgraded to provide two circulating
                lanes with a central island diameter of not less than 23 meters. A design for the upgrade
                roundabout has been previously agreed. However, the proposal plans (for example, the
                John R. Brogan plan 1096-030A) do not show either dedication for, or construction of, the
                upgraded roundabout. The upgrading proposed needs to be clarified/confirmed
The applicant proposes to provide the necessary road upgrades to the Eumundi Road and Rene Street
roundabout to accommodate future development. All necessary land dedications will also be undertaken to
accommodate this. Please refer to the attached response as prepared by TTM Traffic in Attachment C.
        18.5    Queue Provisions —- The queues at the Rene Street roundabout site access need to be
                reviewed in detail to ensure long term satisfactory operations, particularly taking account
                of the roundabout upgrading. Also Council believes that access to and from the site at the
                roundabout should be single lane in each direction not two lanes as indicated on the
                proposed plans, please amend.
TTM have advised as part of their response that the proposal will have little effect on queuing on the
roundabout except for the Rene Street approach. To limit any potential impacts there maybe on the
queuing for this approach, the applicant has undertaken some amendments to the internal traffic
arrangements as is illustrated in the amended plans provided by Brogan and Associates (Attachment A).
Please refer to the attached response as prepared by TTM Traffic in Attachment C.
       18.6     Access to Gateway Drive - Two public access driveways are proposed to Gateway Drive
                (in addition to the primary site access via the Rene Street roundabout). At most, one
                public access driveway to Gateway Drive is likely to be justified. The proposed access
                arrangements should be justified or amended.      Queue provisions and turning lane
                treatments at these proposed driveways should also be examined.
TTM have advised in their attached response, that the access to Gateway Drive is sufficient as it
represents sound traffic engineering principles. The accesses proposed are typical to that of a normal
Bunnings Warehouse, which has proven to work in the past. Please refer to the attached response as
prepared by TTM Traffic in Attachment C.
       18.7     Future Connection of the Gateway Drive with Venture Drive — Please assess and address
                the impact of development on the future intersection of Venture Drive and Gateway Drive
                and the future additional traffic flows in Gateway Drive. Also investigate any impact of the
               additional road traffic on the design of the proposed accesses from the Gateway Drive
                frontage of the site

                                                                                    6631_Info Req Response_010807_ke.doc

Used in these records

About this file

File size
18.5 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015E256.001.pdf · 18.5 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.