Council archive · source document
Decision Notice MCU25 0053 & OPW25 0074 (As Published) · OPW25/0074
For the purpose of this condition, an effectively stabilised surface is defined as one that does
not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
or lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
26. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
PTG/01608 – O Geotechnical Investigation Report prepared by 28/02/2025
0001 PTG Consulting
PTG/01608 – 1 Acid Sulfate Soil Investigation Management Plan 11/04/2025
0002 prepared by PTG Consulting
ADG1777.25 O Dewatering Management Plan prepared by ADG 1/05/2025
Consulting
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
1. An applicant for a development application may make an agreement with an assessment
manager, referral agency or other person to establish the responsibilities, or secure the
performance, of a party to the agreement about a development condition.
Building and Construction Industry (Portable Long Service Leave) Levy
2. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
General Advisory Notes
3. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
4. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Page 7 of 10
Document Set ID: 24343665
Version: 2, Version Date: 28/11/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice MCU25 0053 & OPW25 0074 (As Published)Related documentApplication case desk ↗
Decision Notice MCU25 0053 & OPW25 0074 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 171 KB (small file)
- File type
No other editions are linked here.