Environmental Advisory Notes
5. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
6. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
7. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
8. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the plan sealing inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as in
the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
Road Reserve Permit
9. This development permit provides the applicant with written authority to undertake the
development in accordance with the conditions. Any additional activities that are undertaken
inside Council’s Road reserve for the purpose of acting on this development permit may
require a Road Reserve Permit. These additional activities may include, but are not limited
to, hoarding, pedestrian diversions, laneway closures, etc. To apply for a Road Reserve
Permit, or for more information, Contact Council’s Road Reserve Officer at
[email protected] Act 2014 – Fire Ant Control
10. Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
individuals and businesses are responsible for ensuring that they follow the movement
controls for specific organic materials to help prevent the spread of fire ants within South
East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
ant biosecurity zone may need a biosecurity instrument permit. More information is available
on https://www.fireants.org.au/treat/business-andindustry/movement-controls.
8. PROPERTY NOTES
Not applicable.
9. VARIATION APPROVAL DETAILS
Not applicable.
10. FURTHER DEVELOPMENT PERMITS REQUIRED
Development Permit for Building Works All building work.
11. SUBMISSIONS
Not applicable.
Page 8 of 10
Document Set ID: 24343665
Version: 2, Version Date: 28/11/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice MCU25 0053 & OPW25 0074 (As Published)Related documentApplication case desk ↗
Decision Notice MCU25 0053 & OPW25 0074 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 171 KB (small file)
- File type
No other editions are linked here.