               16.    Refuse containers must be provided in accordance with the requirements of the
                      Environmental Protection (Interim Waste) Regulations 1996 and (Waste Management)
                      Regulation 2000, for the storage and collection of refuse.
               17.    The developer must provide a suitably screened imperviously paved area large enough for
                      all refuse and recycling containers. A roofed wash down area is required with a cold-water
                      tap, hose and drain outlet connected to sewer.
               18.    All refrigeration plant including motors, shall be situated within the building or suitably
                      provided with noise reduction measures and located as to prevent a noise nuisance beyond
                      the subject land in accordance with the nuisance provisions of the Environmental Protection
                      Regulation 1998. On the spot fines apply for such offences.
               Trade Waste
               19.    A Trade Waste Permit is required to discharge each type of Trade Waste. The hydraulic
                      drawings are to show all the Trade Waste requirements in accordance with the Noosa Trade
                      Waste Policy.
               20.    Full truck access is to be provided to each grease arrestor and/or pre-treatment device for
                      cleaning and servicing. Where access is restricted, a pump out line is required.
               21.    A roof is to be installed above the refuse bin wash facility and over the cleaners sink to
                      prevent rainwater from entering the sewerage system.
               Additional Conditions 06/06/06
               Public Open Space Contributions for Outdoor Dining Area
               22.    A Public Open Space contribution of $63 towards the acquisition of additional parkland or
                      the improvement of existing parkland and facilities in the locality shall be paid to the Council
                      prior to the commencement of the use in accordance with Council’s Planning Scheme Policy
                      PSP12 Public Open Space Contributions. This amount will be subject to variations in the
                      Consumer Price Index, All Groups Brisbane from March 2006 until the date of payment.
               Pathway Contributions for Outdoor Dining Area
               23.    A pathway contribution of $64 towards external major pathways, in accordance with Planning
                      Scheme Policy PSP20 Pathway Trunk Network Contributions, shall be paid to the Council
                      prior to the commencement of the use. This amount will be subject to variations in the
                      Consumer Price Index, All Groups Brisbane from March 2006 until the date of payment.
               Stormwater Drainage Contributions for the Outdoor Dining Area
               24.    A contribution of $116 shall be paid to Council towards the cost of the Noosaville Master
                      Drainage Plan prior to the commencement of the use. The amount of the contribution shall
                      be adjusted in line with changes to the Consumer Price Index, All Groups Brisbane from
                      March 2006 until the date of payment.
               Headworks Contributions for the Outdoor Dining Area
               25.    Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP17
                      and PSP16 on Water Supply Headworks Contributions and Sewerage Headworks
                      Contributions respectively and at the rates applicable at the time of payment. An estimate
                      only of the contribution rates under the current policies is outlined below. These amounts
                      will be adjusted in line with changes to the Consumer Price Index, All Groups Brisbane from
                      March 2006 until the date of payment.

                        Water Supply     $42

                        Sewerage         $38

                        TOTAL            $80

                      All headworks contributions must be paid prior to the commencement of the use.


                                                                                                        Page 4 of 8
Document Set ID: 23682995
Version: 5, Version Date: 10/04/2025
Log in to download the original file

Minor Change Existing Approval 132005 1292 04 [As Published].pdf · 160 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.