Council archive · source document
Minor Change Existing Approval 132005 1292 04 [As Published] · 132005.1292.04
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
headworks contributions not be paid at the due time, Council shall call upon the trading bank
guarantee in full.
In the event that the Development Permit for Material Change of Use of Premises lapses or
is cancelled, the contribution or trading bank guarantee will be returned.
Stormwater Drainage
26. Stormwater runoff from the development must be discharged to the existing stormwater
system without causing scour or damage to the subject site or any adjoining property.
5. REFERRAL AGENCY CONDITIONS
Not Applicable
6. ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. This proposal has not been assessed in relation to the spread of fire between properties /
buildings. It is the building certifier’s responsibility to assess the requirements for fire
separation and appropriate methods of construction as part of the building works approval
process. Referral to the Queensland Fire and Rescue Service (QFRS) may be required as
part of the Building Approval process.
2. The plans for the proposed building work have not been assessed for compliance with the
requirements of the Building Code of Australia as they relate to people with disabilities. Your
attention is drawn to the matter that either or both the Disability Discrimination Act 1992
(Commonwealth) and the Anti-Discrimination Act 1991(Queensland) may impact on the
proposed building work.
Noosa Council recommends that the following matters be considered to address equitable
access and facilities in the building:
a. The building and environs should be designed to meet the requirements of the Human
Rights and Equal Opportunity Commission “Advisory Notes on Access to Premises”
and AS1428.2;
b. Applicants should be aware that a “Disability Standard on Access to Premises” is being
developed and most likely will result in changes to the Building Code of Australia;
c. Any services and facilities in the building complex must allow independent, dignified
and equitable use of the services and facilities for all people.
3. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
Local Law No. 12, prevents a builder or building contractor carrying out building work on a
building site in a way that makes or causes audible noise to be made from the building work:-
3.1 On a Sunday or public holiday, at any time; or
3.2 On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
4. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act
if the cost of operational works exceeds $80,000, then a portable long service leave levy is
required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
the approved form issued by the Building and Construction Industry (Portable Long Service
Leave) Authority that confirms that the requirements of the Act have been satisfied. A
statutory declaration outlining the cost of the operational works must be submitted to Council
with the lodgement of any application for operational works over the site.
Page 5 of 8
Document Set ID: 23682995
Version: 5, Version Date: 10/04/2025
See the original