ORDINARY MEETING MINUTES 19 JANUARY 2017
Pedestrian and Bicycle Facilities
22. Pedestrian and bicycle facilities must be provided for the development. The
works must be undertaken in accordance with an Operational Works approval
and must include in particular:
a. signage and lighting at strategic locations to direct people to building
entries.
b. any required pedestrian refuge areas within the carpark to ensure safe and
convenient pedestrians movements within the site.
c. a total of 9 bicycle parking spaces and 5 end of trip lockers.
Electricity and Telecommunication Services
23. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits
and pipes to accommodate the future connection of optic fibre technology
telecommunications.
24. Any requirement by a service provider to alter, upgrade or encase an existing
service within the work site must be carried out at the applicant’s expense.
25. Certification must be submitted to Council from all relevant service providers
which certifies that the development has met the requirements of this Decision
Notice and all applicable legislation at the time of construction.
Damage to Services and Assets
26. Any damage caused to existing services and assets above or below the ground
must be repaired:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing
services and assets must first be referred to the relevant service authority
for approval.
Stormwater Drainage
27. The site must be provided with a stormwater drainage system connecting to a
lawful point of discharge. The works must be undertaken in accordance with an
Operational Works approval and the Queensland Urban Drainage Manual, and
must include in particular:
a. No adverse impact on other properties and the road’s footpath and grassed
verge (e.g. by diverting flows and/or blocking flows and causing additional
ponding)
b. The use of gravity stormwater drainage only and not surcharge pits or
pumps.
c. collection and discharge of stormwater to Taylor Court.
d. A stormwater detention system to manage peak flows for all storms up to
and including 1 in 100 years storm event
Page 7 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.