08/0310 - MCU - Wellbeing Type 2 - Social [As Published] · 132008.310

of 89

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 21.0, 3 September 2007

 

ACID SULFATE SOILS |

 

4.1.2

{s any of the operational work proposed in a local government area listed‘ in State Planning Policy 2/02: Planning and Managing
Development Involving Acid Sulfate Soils?

‘1E) No

OO Yes
If yes, is the natura! ground level of any point where work is being carried out less than 20m AHD?
OO No
0) Yes
If yes, does the proposed operational work involve the following?
¢ — Excavating more than 1,000m of soil or sediment at or below 5m AHD OONo (1 Yes

Filling the premises with 1,000m: or more of material with an average depth of 0.5m [J] No [_] Yes
on land, soil or sediment at or below 5m AHD

If yes to either or both - this application must to be referred to the Department of Natural Resources and Water (NRW) as Advice Agency

JP Regulation, schedule 2, table 3, item 4
State Planning Policy 2/02: Planning and Managing Development involving Acid Sulfate Soils section 3.6

 

EASEMENTS AND SUBSTATIONS

 

413

\s any of the proposed operational work for filling or excavation?
0 No
OO Yes
If yes, is the filling or excavation associated with reconfiguring a lot?
OO Yes
(No - Answer both (a) and (b) below
(a) Is any part of the premises subject to an easement in favour of a distribution entity or transmission entity under
the Electricity Act 1994?
O No
C) Yes
if yes, is any of the operational work proposed to be located in any part of the easement?

 

i)

(Yes - This application must be referred to the entity as Advice Agency.

{b) Is any of the operational work proposed to be located within 10m of a substation site under the Electricity Act 1994?
O No

(1 Yes - This application must be referred to the entity responsible for the substation as Advice Agency.

IP Regulation, schedule 2, table 3 item 10(a)
IP Regulation, schedule 2, table 3, tem 10(b)

 

414

 

 

Is any part of the premises subject to an easement in favour of the holder of Pipeline Licence Number 1 issued under the
Petroleum Act 1923 for the construction or operation of the Moonie to Brisbane strategic pipeline under that Act?
O No
CI Yes
If yes, is any of the proposed operational work for filling, excavation, compaction, drilling, boring or piping, not associated
with reconfiguring a lot?
No
{] Yes
If yes, is any of the operational work proposed to be located in any part of the easement?
OO No

C1 Yes - This application must be referred to the licence holder as Advice Agency.
IP Regulation, schedule 2. table 3. item 17

 

 

+ Aurukun, Bowen, Brisbane, Broadsound, Bundaberg, Burdekin, Burke, Bumett, Caboolture, Caims, Calliope, Caloundra, Cardwell, Carpentaria, Cook, Cooloola, Douglas,
Fitzroy, Gladstone, Gotd Coast, Hervey Bay, Hinchinbrook, isis, Johnstone, Livingstone, Logan, MacKay, Maroochy, Maryborough, Miriam Vale, Momington, Noosa, Pine
Rivers, Reddiffe, Redland, Rockhampton, Sarina, Thuringowa, Tiaro, Torres, Townsville, Whitsunday.

-30-

Used in these records

About this file

File size
4.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

08_0310 - MCU - Wellbeing Type 2 - Social [As Published].pdf · 4.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.