3.1.3 Mitigated Scenario
When comparing the peak flows in the existing and developed scenarios, increases in
the peak discharge occur at the catchment outlet. As a result, a detention system will
be required to be implemented in order to demonstrate non-worsening from the site.
All modeling parameters remain consistent between the developed and mitigated
scenarios, with the addition of a detention basin downstream of SUB1 and SUB2. The
storage details included within the model are provided in Table 11.
The catchment for the mitigated scenario is the same as the existing scenario as shown
in Figure 4, however, the local detention system has been applied to SUB2.
Table 11: Storage and Outlet Details of Detention System
Basin 1
Elevation Storage (m3) Comment
5.7 0 Top of Bioretention Extended Detention
6.1 23 Weir Level
Pipe Outlet 450mm Dia at RL5.7m
Weir Outlet 2.7m wide at RL6.1m
Q100 WSL RL6.08m
Q100 Volume 22m3
Q10 WSL RL5.98m
Q10 Volume 16m3
A comparison of the peak flows between the existing, developed and mitigated
scenarios are presented below in Table 12. It can be seen that non-worsening of peak
flows is achieved at the outlet to the site.
Table 12: Comparison of Existing, Developed and Mitigated Peak Flows at SUB1
Existing Peak Developed Peak Mitigated Peak Change in Peak
Flow (m3/s) Flow (m3/s) Flow (m3/s) Flow (m3/s)
1 year 0.101 0.107 0.100 -0.001
2 year 0.142 0.146 0.138 -0.004
5 year 0.192 0.195 0.185 -0.007
10 year 0.220 0.223 0.212 -0.008
20 year 0.259 0.261 0.249 -0.010
50 year 0.279 0.280 0.269 -0.010
100 year 0.314 0.315 0.302 -0.012
WBNM outputs are provided in Appendix 2 of this report.
Preliminary design plans of the system have been prepared by TOD Consulting and are
provided in Appendix 3.
14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 5 - Stormwater Managment Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.