Operational Plan 2024 – 2025 Performance Progress On Track Initiatives
OP Ref Initiative Lead Service Area Status Comments
Completed Initiatives
2.1.1 Continue to implement key actions of the Strategy and The Housing Strategy update and
OP Ref Initiative Lead Service Area Status Date Delivered Noosa Housing Strategy including: Environment proposed Housing Monitoring
– Development of a Housing Monitoring program were reported to Council
2.2.3 Maintain the standard of pathways throughout the shire Infrastructure Services 30/06/2025 program. in March 2025. Housing Monitoring
through the delivery of the pathway’s renewal program. – Partnering with State Housing Department, report is being prepared and
Community Housing providers and industry external service provider engaged
to advance the planning and development for data analysis.
2.3.1 Finalise and commence implementation of the Public Art Community Services 14/03/2025
of affordable housing.
Policy to improve the character and aesthetics of public
– Continue site investigations at Lake Engagement with the State
spaces.
Macdonald Drive, Cooroy, for affordable government for State-driven
housing outcomes. development continues. The
2.3.2 Prepare for the delivery of the biennale Floating Land 2025 Community Services 30/06/2025
– Identifying grant and funding opportunities State government confirmed a
event which brings arts and culture to a contemporary
for affordable housing outcomes. social housing development of 32
community.
dwellings in Tewantin and purchase
2.4.3 Deliver the Cycling and Walking Implementation Plan to guide Infrastructure Services 30/06/2025 of an additional site.
Council’s planning, development and promotion of bike and
walking networks in the future. Site investigations completed
at 62 Lake Macdonald Drive,
2.5.3 Complete community halls Disability Discrimination Act Development and 01/02/2025 community engagement
(DDA) compliance and asset management condition Regulation undertaken and report submitted
assessments to ensure quality, accessible and fit for purpose to Council presenting revised site
community facilities. option. Tender process has been
completed, and the report will be
2.6.2 Review and complete the Community Grants program and Community Services 23/01/2025 presented to Council in July 2025.
Noosa Council Annual Report 24/25
policy to further support community organisations to deliver
community development initiatives. Tenders under review for master
planning of Council sites for
2.8.1 Deliver the Living Well Noosa program to improve the health Community Services 01/02/2025 affordable housing using grant
and well-being of the community. funding; proposed planning
scheme amendments on housing
2.8.2 Undertake a proactive auditing programme of wastewater Development and 30/06/2025 affordability awaiting Minister’s
treatment systems to keep community safe and maintain Regulation sign-off submitted February 2025.
water quality and the health of waterways.
2.1.2 Continue to implement and monitor the Short Development and Short Stay Local Operational
Stay Letting Local Law to manage the impacts Regulation Review has significantly progressed.
of short-term letting. The stakeholder survey has been
completed and the feedback
reviewed. Stakeholder roundtable
session completed, feedback from
roundtable included completed
briefing to Council. Report with
recommendations to be presented
at August 2025 round of Council
meetings.
2.2.1 Complete the upgrade of the Woondum Infrastructure Project Reference Group has been
and Wahpunga trails in accordance with Services re-established to guide scope
the Noosa Biosphere Trails Master Plan of works. On the ground works
to improve the condition of trails, increase has commenced, with ongoing
connectivity between Cooran, Kin Kin and procurement and scope refinement
Lake McDonald, and recreational activity. underway for remaining works
to meet grant obligations. QPWS
permit Section 34 application for all
trails progressing well. This project
is funded until November 2026.
2.4.1 Complete and deliver the Movement Strategy and Review of actions included in
and Connection Delivery Plan to improve Environment the Transport Plan and Cycling
transport links, walking and cycling and Walking Strategy has been
connections and movements. undertaken. A draft Delivery Plan
has been prepared for internal
review. The draft was discussed at
Councillor workshop in April 2025.
62 63
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.