Attachment 3 - Construction Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Westcon Site Management Pty Ltd
4.4 Chemical management
Dangerous goods must be stored as far as practicable from residences, drains and
watercourses in correctly labelled containers or packages. A file listing the hazardous
materials used or stored on site is to be established and maintained. This file must also
contain a copy of each material safety data sheets (MSDS).
Fire extinguishers and absorption materials for mopping up spills are to be provided and
made readily accessible to provide a first response. Staff handling hazardous material must
be provided with instruction in the safe use, handling and storage of that material, and
training in appropriate emergency procedures, including clean-up of spills.
Any waste and surplus dangerous goods and any containers that cannot be recycled must
be arranged for disposal at a local council transfer station.
Liquids stored in drums and tanks are to be stored in an area under cover, whenever
possible, and provided with secondary containment (ie. bunding) of a capacity of not less
than 110 % of the largest drum in storage. All drums and tanks (including those containing
wastes) must be clearly labelled as to their contents. Care must be taken to ensure that
incompatible materials are not stored together.
Any liquid spilt from drums during handling is to be cleaned immediately. Any drum
found leaking or in poor condition is to be emptied and the contents transferred to an
appropriate labelled container. Metal trays are to be used under taps fitted to containers
containing oils, thinners, cleaning solvents etc.) to catch any drips. Maintenance of
vehicles must not be undertaken on-site. Refuelling of mobile plant must occur in a
designated area, and the contractor is required to maintain spill kits while refuelling occurs.
4.5 Air Quality Management
The identification of potential sources of dust emission from the site has facilitated the
nomination and design of measures for the control of dust. An adequate water supply forms
one of the principal cornerstone for dust control at the site. Specific control measures to be
implemented for particular operational phases or activities include, but not necessarily
limited to:
4.6 Excavation Activities
• Limiting the removal of soil at any one time to that necessary to provide adequate
access to the construction area;
• Limiting soil removal and vegetation clearance to periods of favourable weather
conditions or maintaining materials in a damp state to avoid dust generation;
• Carrying out progressive revegetation of areas no longer in use;
Issue 2 July 1 Page 11